10
$2,117,392
Change 3, 4 & 5 ton rooftop units.
Second level, temporary classroom partitions. sck
REPLACE 3, 4 TON RTU'S
REPLACE 1 TUBE IN BOILER #2
INSTALL 2 TON CARRIER MINI SPLIT TO BLACK 78 IT ROOM
(DMH) TEAR OFF AND REROOF (6,300 S.F.) CENTER, GRADE LEVEL ROOF AREA OF SCHOOL. INSTALL ADHERED 2 LAYER ISO. INSULATION AND ADHERED 60 MIL. EPDM. APPROVED PLANS AND PERMIT MUST BE ON SITE BEFORE INSPECTIONS WILL BE PROVIDED. SEPARATE PERMI
RETUBE BOILER #2
REPLACE 5 TON RTU
ADD HOT WATER UNIT HEATERS AND PIPING IN MECH LOWER LEVEL / ADD DUCTS IN CRAWL SPACE / PER APPROVED PLANS
RELACE 1 FCU & CONDENSOR FOR THE LOADING DOCK OFFICE
Just adding a chiller with the capacity of 200 Ton and connecting with 6" line to existing system. Talked to their representative Tanner Luhm and he was agreed to use the $284,350 as construction cost. Refer to attached drawings.
REPLACE 2 LOCHINVAR BRAND WATER HEATERS WITH RUUD BRAND 331000 BTU WATER HEATERS(MODEL #GBC331) FOR THE MAIN BUILDING
BOILER REPAIRS
REPLACE DOMESTIC HOT WATER BOILER AND (2) 120 GALLON STORAGE TANKS
TWO 120 GALLON HOT WATER STORAGE TANKS ATTACHED TO NEW BOILER(SEPARATE MECHANICAL PERMIT)
WARREN BUILDING - REPLACE 8 ROOFTOP UNITS RTUS 2, 3, 4, 7, 9, & 12 @ 115MBH RTU A @ 224MBH & RTU B @ 180MBH
REPLACE RTU "D" WITH (1) 10 TON/184MBH HIGH EFFICIENCY RTU NOTE: (8) RTU's HAVE ALREADY BEEN APPLIED FOR ON 10/5 CUSTOMER ADDED ANOTHER UNIT
WARREN BUILDING - REPLACE TWO BOILERS @ 10MBH EACH & PUMP SYSTEM
replace leaking tubes in boiler
REMOVE EXISTING CLAY TILE AND ROLL ROOFING ON SOUTH PORTION OF SCHOOL AND INSTALL NEW STANDING METAL ROOF WITH LAYER OF ISO. INSULATION. ROOF IS INSULATED BELOW DECK. (DMH#1) APPROVED PLANS AND PERMIT MUST BE ON SITE BEFORE INSPECTIONS WILL BE PROVIDED
gymnasium to office conversion certificate of occupancy required: yes mechanical plans required for certificate of occupancy mechanical plans/letter of means of compliance submitted\ special inspections required: yes const type: occupa
Interior renovation phase 1A -ductwork & equipment - New York AHU HW Coil & DX Coil, 3 Patterson Kelly boilers @ 399mbh each, Condensing Unit, Fan Powered Box, 26 VAV's, heat exchanger, restroom exhaust fan, ductwork & piping per engineered plans
new fixtures
interior demolition in preparation for remodeling. sck gym area demolition
TEAROFF AND REROOF WEST PORTION OF ROOF. SCK