281
16
$74,610,182
Add (1) drop-in sink. Add (1) plumbed connection for owner provided coffee machine plan review is done by DOLI, not Mpls, no Mpls Plumbing Plan Review required.2023-08-08 - lea
FOR PARKING RAMPS 1 AND 3 AT 880 28TH ST E - Reroute parking Ramp 3 stairwell drains, and one roof drain out of Ramp 1. Ramp 1 is being demolished.
Lab hood modification per attached plans.
2ND FLOOR HISTOLOGY LAB UPGRADE- NEW RESTROOM SINK
Remodel lower level Courage Kenny Building for office space associated with BLDG982846 certificate of occupancy required: no const type: 1-B occupancy: B 2020 MSBC occupant load: 60 sprinklered: yes
break room sink in new lower level office of courage kenny building
Installation of storm drainage for hospital skyway
1. Shall install CO2 sensors as specified. Alteration of HVAC system, reusing existing system to support the new layout. Installing GRDs and all associated ductwork. Refer to attached drawings.
Interior remodel certificate of occupancy required: no special inspections required: no const type: 1A occupancy: I-2 2020 MSBC sprinklered: yes architect: Thomas Beck #46352
Remodel lower level Courage Kenny Building for office space certificate of occupancy required: no const type: 1-B occupancy: B 2020 MSBC occupant load: 45 sprinklered: yes
Skyway HVAC system, installing 4 packaged units with DX coil and gas heat, VRF system with 8 fan-coil units and 3 VRF condensing units, cooling only split system, electric unit heater, GRDs and all associated ductwork. Refer to attached drawings.
Renovation to the Tenth Avenue Facility restrooms on the mezzanine level of 3rd and 4th floors. including mens and womens restroom, replacement of all fixtures and floor drains.
Rework of exhaust systems on level 3 and 4. Existing life safety damper and ducts for electrical room exhaust to be re-used , new electrical room exhaust fan only. Alternate 1 in note two wasn't exercised. Plans attached.
Drawings attached. Complete snow melt system per design. Also conditioning new entrance/lobby area. 2 CHU west Vesibule and CK Vestibule.
Replace (1) existing sink with new using existing rough plumbing. Add plumbed coffee machine using existing sink rough plumbing.
reinstall wastelines accomodate new drive lane
repiping gas for generator RTU and skyway due to meter moves. Also new 3" gas for n2 new boilers. Plans attached.
temp heat
(DMH-ProjectDox) SELECT DEMO AT WEST MAIN FLOOR ENTRY AND COMMON AREA . DEMO SELECT PARTITION WALLS FOR FUTURE REMODEL. SEPARATE APPLICATION, PLANS, PERMITS AND APPROVALS REQUIRED FOR REMODELING. REMOVAL OF ESCALATOR AND EQUIPMENT REQUIRES SEPAR
In neuro room replacing existing fan coil unit adding one cooling only vav box, GRDs and all associated ductworks. Refer to attached drawings.
CONVERT ROOM 1294 INTO TEMPORARY POP UP CAFETERIA , TAKE OUT NO SEATING (MAA) const type: II occupancy: B 2020 MSBC occupant load: 20 sprinklered:YES 20% accessibility upgrades____FULLY______ Tenant: ABBOT NORTH WESTERN HOSP
Modifying existing doctors lounge with new food service Project is at a hospital DOLI to review plumbing. No Minneapolis plumbing plant review.
CONCRETE AND POST TENSION REPAIRS LEVEL 3. (JJL) ENGINEER: MBJ ENGINEERS - DAN MURPHY #13373 SPECIAL INSPECTIONS: SEE SHEET S001