Add CHW CRAC unit to B2, E3079, PB3667, H0229B, CK1843, CK2799, H3117, E87D6. Add refrigeration CRAC unit to PB6600D, W7114E. Add AHU to serve R1 Data rm. Provide and install miscellaneous duct, vavs, grds, CHW and refrigeration piping. BLDG1167097
Waste and vent work at Abbott Northwestern Hospital. This project is for a state licensed health care facility and the plumbing plan review has been completed by the Minnesota Department of Labor and Industry in lieu of a review by the City of Minne
Reroof -ACW certificate of occupancy required no special inspections required no 2020 MSBC
Updating the Abbott Northwestern TAF and Main hospital west Building Data closets with new technology on 2nd and 3rd floor. Work includes Electrical and HVAC (Rooms 2903M, 2905M, and W2701). This work is related to Projects BLDG1143753, BLDG1155448, and B
ABBOTT NORTHWESTERN PIPER BUILDING AND MAIN EAST BUILDING DATA CLOSET UPGRADES. WORK TO BE DONE ON 2ND, 3RD, 6TH FLOOR. SEE PAGES "LEVEL 02 LIFE SAFETY PLAN", "LEVEL 03 LIFE SAFETY PLAN", AND "LEVEL 06 LIFE SAFETY PLAN" FOR DATA CLOSET LOCATIONS.
Duct alterations to data room K2 through K8. Adding 2 owner CRAC units.
Replace GRDs and rebalance area.
In existing hospital, update Data closets on LL, 1st, 2nd, and 7th floors (Rooms G928A, CK1842, CK2799 H0229, W7114G). This work is related to Projects BLDG1143753 and BLDG1155448 -ACW certificate of occupancy required no special inspections requi
Abbott northwestern 5th Floor Replace one water fountain and demolishing 4 sinks (and capping water lines) in office area of 5th floor.
Install waste stand pipe and RPZ water line for new bone saw. Total job valuation: $20,100.00.
Update Heart Hospital Data Closets certificate of occupancy required: no special inspections required: no SEPARATE PERMITS ARE REQUIRED FOR ELECTRICAL, PLUMBING, AND HEATING/AIR CONDITIONING/VENTILATION WORK. occupancy: B/I-2 2020 MS
Replace existing boilers with new AHU in mechanical room. Remodel MRI-D with added piping, ductwork, accessories and equipment. BLDG1138373 New ducts and piping though out building including roof.
Rework ductwork in ED CT and Mechanical equipment room. Replace VAV and add chilled water station with heat exchanger, pump and associated accessories per plans
DEMO SINK, INSTALL NEW FAUCET AND SINK
Install new domestic water to MRI-D expansion, along with (3) lavs and (1) mop-sink.
" Controls are not included in this permit. The controls contractor shall obtain a separate permit. " HVAC system, installing VAV boxes with hot water reheat coils, GRDs and all associated ductwork per approved plans.
remodel of CT room E1612 for new equipment. certificate of occupancy required no const type: 1a occupancy: I2 2020 MSBC sprinklered: yes architect: Leo Daly engineer: MBJ
abbott west. restrooms & drinking fountain
alterations to replace emergency department CT machine and associated equipment. certificate of occupancy required no const type: 1a occupancy: I2 2020 MSBC sprinklered: yes architect: nelson #42247 leo daly architects
remodeling outpatient clinic areas of 3rd and 6th floor. piper neuro expansion. certificate of occupancy required no const type: 1a occupancy: B - outpatient clinic space 2020 MSBC sprinklered: yes architect: Abeln #5382
REMODEL ON 1ST FLOOR FOR EQUIPMENT const type: II-B occupancy: I-2 2020 MSBC architect: 53825 - Abeln, Daniel Jonathon @ EAPC engineer: 23148 - Trofimova-Peterson, Irene @ MBJ
BLDG1111397 3 new Data Center cooling systems. Data rooms are located on level 2,3, and 4 Ducted fan coils units. Condensers are located on the roof.