Saint Louis Park, MN
Saint Louis Park, MN
6500 Excelsior Blvd 3W, Saint Louis Park
Principal Building, Complete remodel of 3West birthing center
6500 Excelsior Blvd 3W, Saint Louis Park
Principal Building, Remodel exisiting birthing center on 3rd floor west of main hospital. Most areas are full demo &..
6500 Excelsior Blvd, Saint Louis Park
Principal Building, Disconnecting one sink *No new Plumbing*
6500 Excelsior Blvd 3W, Saint Louis Park
Principal Building, demo of existing inside of Phase 1 area, DEMO PERMIT ONLY
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Add/relocate sprinkler heads to bring up to code - 97 heads
6500 Excelsior Blvd, Saint Louis Park
Principal Building, Rebuild RPZ
6500 Excelsior Blvd, Saint Louis Park
Principal Building, add double door to storage area, 1st FL cancer center storage area
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Add/relocate sprinkler heads to bring 4th Fl to 100%
6500 Excelsior Blvd, Saint Louis Park
Water Line, Install 1" poly water service for sprinkler system from manhole
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Relocate heads for new layout one for one for coverage
6500 Excelsior Blvd 2-359, Saint Louis Park
Principal Building, Remodel existing offices into waiting rooms
6500 Excelsior Blvd, Saint Louis Park
Principal Building, Remove sinks for new wall coverings and reinstall
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Relocate 9 heads
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Relocate 2 heads for coverage of patient lift
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Relocate heads for new layout - see comments
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Relocate heads for new layout one for one - see comments
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Relocate heads for new layout - see comments
6500 Excelsior Blvd, Saint Louis Park
Principal Building, remodel 2 exam rooms into injector room @ 4th floor HVC
6500 Excelsior Blvd, Saint Louis Park
Principal Building, general EL for January and February
6500 Excelsior Blvd, Saint Louis Park
Principal Building, general EL for March and april
6500 Excelsior Blvd, Saint Louis Park
Principal Building, general EL for may and june
6500 Excelsior Blvd, Saint Louis Park
Principal Building, general EL for july and august
6500 Excelsior Blvd, Saint Louis Park
Principal Building, general EL for sept and oct
6500 Excelsior Blvd, Saint Louis Park
Principal Building, general EL for nov and dec
6500 Excelsior Blvd, Saint Louis Park
Sprinkler System NFPA 13, Add/relocate 74 existing heads for new walls and ceilings
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.