Saint Paul, MN
Saint Paul, MN
285
1
Add/Relocated sprinkler heads to conform to new walls/ceilings per NFPA 13 2016.
Well Works Clinic - Provide installation for a Commercial Fire Alarm System: o (16) FDOT-421 o (2) XTRI-R o (11) SC-SS-CW-F Speaker Strobes o (2) SC-ST-CW-F Strobe Only o (1) 8 Hours Demo with assistance from Siemens
Well Works Clinic - Provide installation for a Commercial Fire Alarm System: o (16) FDOT-421 o (2) XTRI-R o (11) SC-SS-CW-F Speaker Strobes o (2) SC-ST-CW-F Strobe Only o (1) 8 Hours Demo with assistance from Siemens
Same as permit PWROWOB-027381-2026. Setup small boom truck on 7th Pl E to hoist 1 hood and 1 HVAC Fan. requesting 7:00 AM start time
We are performing roof repairs on 400 N. Robert St. We will need to set up a boom truck (crane) on 7th Place E. taking up the entire road and 7 parking spaces. We will have a person on the ground along with a crane operator, the ground person will monitor pedestrian traffic on the sidewalk while we are lifting over the area. We anticipate approx. 3 hrs. of closure two times. One day for loading materials and equipment to the roof and one day for downloading materials and equipment.
We are performing roof repairs on 400 N. Robert St. We will need to set up a boom truck (crane) on 7th Place E. taking up the entire road and 7 parking spaces. We will have a person on the ground along with a crane operator, the ground person will monitor pedestrian traffic on the sidewalk while we are lifting over the area. We anticipate approx. 3 hrs. of closure two times. One day for loading materials and equipment to the roof and one day for downloading materials and equipment.
Setup crane on 7th Pl E St Paul, MN to hoist HVAC equipment to roof
Remodel of existing office space, inclusion of new exam rooms, IT room.
Replace (19) diffusers and 14 return air grilles
Minor Refresh of 2nd floor space. Moving some doorways, building a wall, new finishes (from dental office to wellness clinic)
Suite 1400 We are pulling 2 sinks and replacing them with new sinks in lab and replacing electric water heater like for like
14th floor Tenant build out space for Westin Construction. Use existing branch circuits. Reconfigure existing lights. Add one circuit for water heater.
Securian Fitness Center HVAC controls - 1 AHU, 11 VAV's, 2 UH's and 1 EF.
Feed 30KVA 480/208V transformer to supply 100A 208/120V panel.
(2) 60A 480V feeders to 70A ATS serving domestic water booster pump skid.
Suite 1430. Small interior tenant remodel of decreasing a conference room to add an office, closet and breakroom.
Lighting Control on 12th Floor
Modify existing sprinkler system to accommodate new arch walls and ceilings per NFPA 13 (2016)
Provide new AHU with condensing unit. Provide (2) gravity intake/relief hoods. Provide (2) exhaust fans. Provide new VAVs per plans. Ductwork distribution and new GRDs per plans.
Securian 400 Fitness Center - Provide installation for a Commercial Fire Alarm System: o (1) FDOT-421 o (2) XTRI-R o (2) Duct Detector o (18) Speaker/Stobes Ceiling Mount o (4) Speaker/Strobes Wall Mount o (2) Speaker/Strobe Guard o (14) Demo Existing Fire Alarm Devices o (2) Strobe Only
Refrigeration piping for new AHU and condensing unit.
Securian 400 Firness Center - Provide installation for a Commercial Fire Alarm System: o (1) FDOT-421 o (2) XTRI-R o (2) Duct Detector o (18) Speaker/Stobes Ceiling Mount o (4) Speaker/Strobes Wall Mount o (2) Speaker/Strobe Guard o (14) Demo Existing Fire Alarm Devices o (2) Strobe Only
Plumbing per plans, contractor to change address to 400 Robert St Suite 100.
Installation of new fitness center into existing space
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.