Minneapolis, MN
Minneapolis, MN
15
5
$12,492,147
ALTER ROOF DRAIN SYSTEM 2020 MSBC architect: 53825 - Abeln, Daniel Jonathon @ EAPC engineer: 61683 - Wuollet, John Christopher @ MBJ
BLDG1161702 Rework HVAC to accommodate lab sterilizer replacement. Includes HPS piping modifications and duct modifications.
Remodel for lab sterilizer replacement. Other Fixtures: (2) Floor Sinks & (4) RPZ Backflow Preventers
HVAC system for pharmacy area remodel, installing DX split system, VAV boxes, return fan, air valve, GRDsand all associated ductwork per approved plans.
Structural drawings for the chiller have been uploaded into for reference folder. Chiller addition and chiller piping modifications. BLDG1108727
Abbott Northwestern TAF Pharmacy - Modify existing plumbing for new floor plan and new fixtures. See attached plumbing plans by Dunham Associates. Fixtures marked "other" are Emergency Eyewash Stations.
HVAC system, installing steam humidifier manifold in existing duct and associated piping per attached drawings.
REMODEL - STORAGE SPACE const type: IB occupancy: B 2020 MSBC architect: 53825 - Abeln, Daniel Jonathon
NEW ROOFTOP CHILLER AND STRUCTURAL WORK. 1ST AND 4TH FLOOR. (JJL) TAF CHILLER ALLINA HEALTH ENGINEER: IRENETROFIMOVA-PETERSON #23148 ARCHITECT: DANIEL ABELN #53825 SPECIAL INSPECTIONS: BRAUN INTERTEC
Allina Health - New 2nd Floor Pharmacy certificate of occupancy required: no special inspections required: no SEPARATE PERMITS ARE REQUIRED FOR ELECTRICAL, PLUMBING, HEATING/AIR CONDITIONING/VENTILATION WORK. const type: 1B occupancy:
BUILD 2 OFFICES ON 2ND FLOOR OF 10TH AVE FACILITY const type: IB occupancy: B 2020 MSBC architect: 53825 - Abeln, Daniel Jonathon
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.