Inspector’s Note: Do not remove any ROW structural concrete (sidewalk) or asphalt (roadway). The plan indicates that all boring points are located within the boulevard. Inform the Inspector at least 5 days in advance to arrange and obtain four (4) No Parking signs for this project (for Berry Street) and provide exact dates for this work to fill in NO Parking Signs template - Vugar.Gadzhiev@ci.stpaul.mn.us NOTIFY METRO TRANSIT BEFORE STARTING WORK TO DETERMINE IMPACT ON BUS ROUTES (Kimberly Stine - M: 612-418-3113 E: Kimberly.Stine@metrotransit.org); Provide them TCP. Description: Pull 96CT fiber through existing duct. Directional bore (1) 2" conduit containing 96CT fiber cable. Pull 96Ct fiber cable through existing duct. Restore work area to original condition. Please see prints for further details.