Rochester, MN
Rochester, MN
201 W CENTER ST, Rochester
Ryan Taylor/ROCH22C0010 CH1-249 INPT space re-fit
201 W CENTER ST, Rochester
ELECTRICAL FOR CH1-249 IN PT SPACE REFIT- MAYO# ROCH22C0010 EGAN FOREMAN: BEN SCHNEIDER 612-456-8549 EGAN JOB# 611056-910
201 W CENTER ST, Rochester
Ventilation system demo of existing distribution and install of new HVAC distribution system for the project. Provide and install new VAV boxes and distribution duct as shown on the plans. Provide and install new smoke dampers and fire dampers as shown ion the plans.
2017 NW 31 PL, Rochester
Gas line for generator 300,000 BTU
201 W CENTER ST, Rochester
Building Controls Electrical Work 1st Ave Tunnel Mayo Project Number: 80958 JCI Project Number: 2N53-0266 CRM
2017 NW 37 ST, Rochester
-ELECTRICAL FOR EXHAUST FAN INSTALLATION. A102201
201 W CENTER ST, Rochester
Temperature Controls Electrical Theranostics Phase 2 Mayo Project: ROEI21C0010 JCI Project: 2N53-0491 CRM
201 W CENTER ST, Rochester
Hydronic work to provide heating hot water to four (4) new VAVs. Mayo Project : ROCH22C0010 Eisenberg Building Harris Job # 56738-5080
201 SW 28 ST, Rochester
Breezeway addition; repair foundation wall, new roof | Other
2017 NW 31 PL, Rochester
Generator Install
2015 SE 25 ST, Rochester
REPLACE FURNACE & AC
201 SE 9 ST, Rochester
Full Building Demo (K-Mart)
1201 SW 12 ST, Rochester
Build out for Lululemon store
201 W CENTER ST, Rochester
ELECTRICAL - DEMO AND FIT UP EXISTING SPACE FOR NEW SCANNER- CHARLTON BUILDING- SIEMENS QUADRA PET- MAYO# ROCH22C0020 EGAN FOREMAN- PETE ULBRICHT 507-696-1999 EGAN JOB# 611091-910
201 W CENTER ST, Rochester
ROCH22C0020-Ryan Taylor Replace PET scanner with Quadra whole body PET scanner for Charlton Building
201 W CENTER ST, Rochester
Mayo Project ROCH22C0020 - Replace existing PET Scanner with a new Quadra PET Scanner Ventilation modification for Scanner Room. Modify existing exhaust ducting, install a new inline exhaust fan and motorized dampers. Fabricate and install a low return air system for the Scanner Room 1-265E.
201 W CENTER ST, Rochester
Plumbing work associated with the installation of a new Chilled water branches to new Siemens Quadra Machine. Install new sink and floor drain. Disconnect Fan Coil Unit. Harris Job # 56736-01-5080
201 W CENTER ST, Rochester
Hydronic work associated with the installation of a new Chilled water branches to new Siemens Quadra Machine. Install new sink and floor drain. Disconnect Fan Coil Unit. Harris Job # 56736-02-5080
1201 S BROADWAY AVE, STE# 36, Rochester
Plumbing work for tenant fit-up of new Mayo Clinic Retail Store
2011 NE 15 ST, Rochester
Installation of a new Springfield 36 into a masonry fireplace opening on the main level of an existing home. Remove existing gas insert
1201 SW 12 ST, Rochester
New air handler & ductwork per plans - Lululemon Space 314 (C4031)
1201 SW 12 ST, Rochester
Remodel plumbing per plans - Lululemon Space 314 (C4031)
1201 SW 12 ST, Rochester
Unhook, reconnect (2) new air handlers - Lululemon Space 314 (C4031)
3201 SE 41 AVE, Rochester
electric work install mini split and 2 heads one in living room and 1 in master bed room run #10 wire from 30 AMP breaker to disconnect box and condenser unit on west end of house.
2010 NE 5 AVE, Rochester
Install Water Heater Rework Water Piping