Remove 3" galv piping that is leaking and replace with copper.
1216 SW 2 ST, Rochester
Install PRV on 120# line serving RPZs for core 400 sterilizers
1216 SW 2 ST, Rochester
Install PRV on 120# line that serves core 500 sterilizers
1216 SW 2 ST, Rochester
Toilet on plates needs to be lowered and new caulk, flushometer to be installed. Ligature hazard.
1216 SW 2 ST, Rochester
Install a 1" hot tap on LP condensate in Power plant
1216 SW 2 ST, Rochester
FCU condensate is flooding unit. Install the correct depth trap
1216 SW 2 ST, Rochester
RONT24C0040 - CONSTRUCTION INCLUDES 550 SF OF EQUIPMENT REPLACEMENT WITH MINOR PATCH WORK TO MATCH INTERIOR FINISHES IN NASSEFF TOWER.
1216 SW 2 ST, Rochester
Mayo-Mary Brigh Building-02-775 -Electrical work for new lactation room -Mayo work order number 0065989 Adair work order number WA0366 -This work is T&M
1216 SW 2 ST, Rochester
Mayo-Alfred Building-04-418 -Electrical work to install flammable cabinet -Mayo work order number 0042706 Adair work order number WA0888 -This work is T&M
1216 SW 2 ST, Rochester
Install a new ceiling fan. Mayo # ROXX24C0330 - SMC North Bike Storage Harris Job # 0800491-N5080
1216 SW 2 ST, STE# MN604, Rochester
0065989/ New Lactation Room/ Steve Rasmusson, Mary Brigh 2nd floor
1216 SW 2 ST, Rochester
Mayo-Domitilla Building-05-303 -Electrical work to remodel conference room 5-303 -Mayo work order number 0053954 Adair work order number WA0580 -This work is T&M
1216 SW 2 ST, Rochester
Steve Rasmusson/ROXX24C0330/SMC North Bike Storage, Domitilla Bldg
1216 SW 2 ST, Rochester
Mechanical work related to the replacement of two AHUs. Numbers 12 & 13. Mayo #ROMB24C0070 MBS 12 & 13 AHU Replacement Harris Job # 0800406-N5080
1216 SW 2 ST, Rochester
ROMB24C0070 Mary Brigh MBS-12 Mechanical Infrastructure/ Steve Rasmusson/ New MBS-12 (serving Locker rooms) and new exhaust and energy recovery (serving locker rooms); demolition of MBS-13 (no longer used). Plumbing work will require access to MB 1 ceiling, ICRA Level- high.
1216 SW 2 ST, Rochester
ROMB24C0070 - Replacement of Air Handling units 12 and 13.
1216 SW 2 ST, Rochester
ROMB24C0070 - Replacement of Air Handling Units 12 and 13
1216 SW 2 ST, Rochester
R53954 - Remodeling conference room DO-5-303 to support new AV equipment
1216 SW 2 ST, Rochester
Install a few new VAVs and GRDs to provide air to the locker room. Mayo #ROMB23C0040 - SMC Female Consultant and Locker Rooms Harris Job # 0800350-N5080
1216 SW 2 ST, Rochester
Remove existing ballasted EPDM system down to the deck and dispose of. Install vapor barrier, adhere tapered insulation adhere membrane, and install paver system over the EPDM.
1216 SW 2 ST, Rochester
Mayo-Mary Brigh Building-01-550 -Electrical work for a new command center -Mayo work order number 0100387 Adair work order number WA0761 -This work is T&M
1216 SW 2 ST, Rochester
FURNISH AND INSTALL DUCTWORK GRD CRAC UNIT GRD
1216 SW 2 ST, Rochester
Mayo-Saint Marys Power Plant-Operating Level-122 -Electrical work for a walk-in freezer and new workstations -Mayo work order number 0086977 Adair work order number WA0727 -This work is T&M
1216 SW 2 ST, Rochester
Mayo-Domitilla Building-Main Floor -Electrical work to install new hearing booths -Mayo work order 0064900 Adair work order number WA0599 -This work is T&M
1216 SW 2 ST, Rochester
Mayo-Francis Building-Ground Level-17 -Electrical work to install hot/cold food wells -Mayo work order number 0082123 Adair work order number W8495 -This work is T&M