Rochester, MN
Rochester, MN
1216 SW 2 ST, Rochester
Plumbing work for week of 11/09/2009 SMH - Alfred GR-433 Equipment Room / WO283460
1216 SW 2 ST, Rochester
Hydronic work for week of 11/09/2009 / Water damaged rooms SMH - Joseph 1-241 Office / WO283821
1216 SW 2 ST, Rochester
Plumbing work for week of 11/09/2009 / Need eye wash installed on sink SMH - Alfred 9-445 Procedure/Treatment / WO283891
1216 SW 2 ST, Rochester
Plumbing work for week of 11/09/2009 / Relocate garbage disposal & other services SMH - Francis MN-37 Kitchen / WO284319
1216 SW 2 ST, Rochester
Plumbing work for week of 11/09/2009 / Install bag filter into cold soft supply main. SMH - Generose GR-203 Equipment Room Primary / WO284706
1216 SW 2 ST, Rochester
Plumbing work for week of 11/09/2009 / Work related to AB project # 7R090130 SMH - Mary Brigh MN-104 Office / WO284944
1216 SW 2 ST, Rochester
Hydronic work for week of 11/09/2009 / Work related to AB project # 7R090130 SMH - Mary Brigh MN-104 Office / WO284944
1216 SW 2 ST, Rochester
Hydronic work for the week of 11/09/2009 / Fan coil unit is corroded & falling apart. SMH - Joseph 3-172 Patien Room-Private / WO285150
1216 SW 2 ST, Rochester
Hydronic work for week of 11/09/2009 / Need manual & automatic air bleed installed. SMH - Mary Brigh 10-520 Garage/Hangar / WO285033
1216 SW 2 ST, Rochester
Hydronic work for week of 11/09/2009; Paape is upgrading the BAS controllers; change out for SMH - Francis 2-100 Patient Room/Semi Private
1216 SW 2 ST, Rochester
Plumbing work for week of 11/09/2009; eye washing stations SMH - Alfred 9-446 Work Area / WO284822
1216 SW 2 ST, Rochester
Alterations for the Emergency Department Critical Care Trauma Rooms. (St. Mary's Mary Brigh main floor - Mayo Project 7R090310)
1216 SW 2 ST, Rochester
Electrical work for week ending 10/16/2009 SMH - Mary Brigh MN-104 Remodel / WO284944 / WP# 7R090310 (T&M)
1216 NW 2 ST, Rochester
Deck Addition 8 x 10 | Deck Addition
1216 SW 2 ST, Rochester
Alterations for the CV Surgery Admninistrative Office relocation/expansion. (St. Mary's Hospital, Alfred Building, 2nd Floor - Mayo Project 8R090900)
1216 SW 2 ST, Rochester
Mechanical/ductwork/demo/vav/grd - CV Surgery Administrative Office Relocation/Expansion SMH - Alfred 2nd, Proj# 8R090090
1216 SW 2 ST, Rochester
Electrical - replacing underground fuel tank installing new sensors located by emergency entrance - 8R090560 - ST MARYS HOSPITAL
1216 SW 2 ST, Rochester
Electrical - CV Surgery Administrative Office Relocation/Expansion SMH - Alfred 2nd, Proj# 8R090090
1216 SW 2 ST, Rochester
Stair alterations. (St. Marys Mary Brigh Building main, 1st and 2nd floors - Work Order number 284108)
1216 SW 2 ST, Rochester
Electrical work for week of 09/04/2009 SMH - Generose MN221 Rec / WO284450
1216 SW 2 ST, Rochester
Electrical work for week ending 08/28/09 SMH - FRANCIS LOBBY, LIGHT / WO282595
1216 SW 2 ST, Rochester
Electrical work for week ending 08/28/09 SMH - MARY BRIGH M-573 REMODEL / WO283393
1216 SW 2 ST, Rochester
Electrical - add receptacles and data for Barcode Med Charting (8R080710) Multiple Buildings PO 601706-2-900-E
1216 SW 2 ST, Rochester
Alteration to an existing office area. (St. Mary's Hospital Mary Brigh Main Floor - Mayo Project R3789)
1216 NW 2 ST, Rochester
Electrical- Wire A/C
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.