Kevin Johnson has been on site to look at the project. Removal of gas piping on the center section of the roof, replacement of the gas piping after the roof has been replaced. Temporary removal of 3 package units, reinstall the package units after the roof has been replaced. Please speak with Kevin about this job, plan review not required.
Replace rooftop unit 14, 5 ton DX Cooling and 150,000 gas heating, 14 SEER2. Total cost on project $17,290.00
(S008882) HC #93247 MCDOWALL COMPANY - CALVARY CHURCH - REMOVE EXISTING RTU AND INSTALL NEW
Remove rock, replace flat roof rubber 60 mil edpm, includes 4” of additional iso board, build up ac box
Refeed well pump and installed VFD
demo of old shed 30x 36 size