Building
10702 Red Circle Dr, Minnetonka
New, Full Permit: Market Rate Apartment Building w/ 269 units.
- Apr 21, 2026·7:00 AM - 8:00 AM
Commercial Final
scheduledInspectorMarshall Lind
- Apr 20, 2026·7:00 AM - 8:00 AM
Commercial Final
scheduledInspectorMarshall Lind
- Apr 16, 2026·7:00 AM - 8:00 AM
Commercial Final
scheduledInspectorMarshall Lind
- Apr 15, 2026·7:00 AM - 8:00 AM
Commercial Final
scheduledInspectorMarshall Lind
- Apr 14, 2026·1:30 PM - 3:00 PM
Commercial Final
scheduledInspectorMarshall Lind
- Apr 13, 2026·7:00 AM - 8:00 AM
Commercial Final
scheduledInspectorMarshall Lind
- Apr 8, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Units: 482, 480, 478, 476, 474, 472, 470, 465, 463, 461, 459, 457, 455, 454, 453, 452, 451, 450, 449, 443, 441, CORRECTIONS: Need fire caulk in elect/data room, Carpet under fire rated doors
- Apr 8, 2026·7:00 AM - 8:00 AM
Commercial Final
scheduledInspectorMarshall Lind
- Apr 7, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Units: 582, 580, 578, 576, 574, 572, 570, 565, 563, 561, 559, 557, 555, 554, 553, 552, 551, 550, 549, 543, 541, Storage, CORRECTIONS: 557 ceiling & insulation removed, Carpet under fire rated doors
- Apr 6, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Units: 282, 280 278, 276, 274, 272, Storage ABC, 265, 263. 261, 259, 655, 654, 653, 652, 651, 650, 649, 641, CORRECTIONS: Data room needs fire caulk around pipes & wires, Common restrooms need pipe protection, Need to remove carpet under fire rated doors
- Apr 1, 2026
Commercial Final
CANCELLED APPOINTMENTInspectorMarshall Lind
Per BN, Inspection canceled 8:20 4/1/26
- Mar 31, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Common area: Office suite 1-4, Leasing area & office 1-2, Work room lunch room, Conference room, Maintenance Office, Golf simulator, Club room, Fitness/work out room, Sauna, CORRECTIONS: All restrooms need pipe protection
- Mar 30, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Units 217, 219, 221, 223, 224, 225, 226, 227, 228, 230, 233, 236, 237, 238, 239, 240, Data room, Trash room, CORRECTIONS Unit 229 threshold to deckto high, Carpet under rated doors
- Mar 27, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
308, 313, 315, 317,320, 323, 326, 327, 328, 329, 330, 333, 336, 337, 338, 339, 340, Trash room CORRECTIONS: carpet under fire doors, 4 Storage units no name plates
- Mar 25, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Finals units 406, 408, 415, 423, 425, 427, 428, 429, 430, 432, 433, 434, 435, 436, 437, 438, 439, 440, Electrical room 4th floor, Elevator B, Trash room Corrections: Carpet under fire rated door in corridor
- Mar 24, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Units 508, 515, 523, 526, 527, 528, 529, 530, 532, 533, 534, 535, 536, 537, 538, 539, 540, 542 Storage, Trash room, CORRECTIONS 541 & 543 NOT READY, 536 ENTRY DOOR DOES NOT CLOSE, ELEVATOR B NEEDS SPRINKLER HEAD, FIRE RATED DOORS HAVE CARPET GOING UNDER THEM
- Mar 23, 2026
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
608, 615, 623, 627, 628, 629, 630, 6432, 633, 634, 635, 636, 637, 638, 639, 640 CORRECTIONS: Fire door Area B has carpet under doors, 649 needs window fall protection, Common area patio guard rail not 42" high/Check reach to shelve per ADA
- Jan 21, 2026
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation on Units 170, 157, 155, 154, 153, 152, 158, 158, 161, 163, 165 OK, Hallway between Units 180 - 158 & Hallway 158 - 165
- Jan 20, 2026
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation for units 180, 178, 176, 174, 172 CEILING CLOSED CELL INSULATION Unit 267 GENERATOR ROOM
- Jan 14, 2026
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire Blocking: Units missing FB around plumbing pipes 180, 178, 176., 174, 172, 170, 165, 163, 161, 159, 158, 157, 155, 154, 153 Unit 153 NEED TO COVER PIPE BREAKING FIRE RATED WALL & GAS LINE, UNIT 157 COVER PLUMB PIPE BREAKING FIRE WALL, UNIT 165 ROD & ELECTRICAL LINE COMING THROUGH CONCRETE CEILING, UNIT 170 NOT READY, UNIT 178 & 180 2 HOLES
- Dec 26, 2025
Commercial Insulation
CANCELLED APPOINTMENTInspectorMarshall Lind
Showed up for inspection, No one on site, Text Doug & he said inspection is canceled
- Dec 23, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 100, 123 Mechanical room, 128, 130, 136, 137, 138, 139, 140, 141, 142, 143, 146, 148, 149, 150 OK
- Dec 18, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
1st floor pre firestop inspection. no issues found Spoke with David re: Fire doors installed in firewalls at horizontal exits.
- Dec 16, 2025
Meet Contractor
SEE COMMENTSInspectorMarshall Lind
Met with Doug about building finals /7 requirements to occupy the building
- Dec 15, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Screw patterns Units 280, 278, 276, 274, 272, 270, 268 ABC, 265, 263, 261, 265, 259, 255, 254, 253, 252, UNIT 268 ELECTRICAL NEEDS TO FIX SCREW SPACING
Show 163 earlier inspections
- Dec 12, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Final for Units 303, 305, 306, 307 Electrical Room, 309, 310 Storage, 319, 321, 322, 324, 325 CORRECTIONS UNITS 317, 320, 326 NEED TO ADJUST CLOSERS ON DOOR TO HALLWAY, UNIT 308 NO RAILING, UNIT 311 NEEDS GASKET ON MECHANICAL ROOM DOOR, UNITS 315 & 315 NOT READY, UNITS 323 NEEDS CO DETECTOR IN BEDROOM CHECK ON TYPE A REQUIREMENTS
- Dec 10, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
UNIT FINALS 401, 403, 405, 407 A Electrical, 407 BCD, 409, 410 Storage, 411, 413, 417, 419, 420, 421, 422, 424, 426 CORRECTIONS UNITS 406 NEEDS GASKET ON MECHANICAL ROOM, 408 NEEDS CO IN BEDROOM, 415 NEEDS CO IN BEDROOM & NEEDS TO FIX THRESHOLD ON MECHANICAL DOOR, 423 NEEDS CO IN BEDROOM, 425 NEEDS GASKET ON MECHANICAL DOOR
- Dec 9, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Final Units 624, 625, 626, 501, 503, 505, 507 Electrical room, 506, 509, 510 Storage, 511, 513, 517, 519, 520, 521, 522, 624, 526 UNITS THAT CO DETECTORS 623, 523, 515, 508 UNIT 526 NEEDS DOOR TO HALLWAY TO HAVE SPRINGS SET SO DOOR IS SELF CLOSER
- Dec 8, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Units 601, 603, 605, 606, 607 BC, 608, 610, 611, 613, 617, 619, 620, 621, 622 UNIT 615 HAS FURNACE IN BEDROOM/ NEED CO DETECTOR IN FURNACE ROOM & DOOR SEALED TIGHT
- Dec 5, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Screw patterns for units 380, 378, 376, 374, 372, 365, 363, 361, 350, 357, 355, 354, 353, 352 CORRECTIONS Unit 370
- Dec 3, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation for units 252, 253, 254, 255, 257 258ABC, 258 Data, Hallway between Units 280-258A,, Units 259, 261, 263, 265, Hallway between Units 258 Data - 258,
- Dec 2, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 270, 272, 274, 276, 278,,280 OK
- Dec 2, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Screw patters Units 482, 480, 478, 476, 474, 472, 470, 468, 465, 463, 461, 459, 457, 455, 454, 453, 452 OK
- Dec 1, 2025
Commercial Wallboard
CANCELLED APPOINTMENTInspectorMarshall Lind
Texted at 6:21 12/1/25 don't need inspection David
- Nov 25, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Gypsum board in rim area only, Units 252, 253, 254, 255, 257, 259, 261, 263, 265, 270, 272, 274, 276, 278, 280
- Nov 24, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 353, 355, 357, 359, 361, 363, HALLWAY between Uni359-363
- Nov 21, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full Insulation Units 352, 354, Hallway from Units 368 Data - 352, Units 368 Data, 368 ABC, 370, 372, 374, 376, 378, 380, Hallway between Units 380 - 368 A, EXTERIOR walls Only 252, 253, 254, 255, 257, 259, 261, 263, 265, 270, 272, 274, 276, 278, 280
- Nov 19, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
FULL WALL BOARD & SCREW PATTERNS Units 552, 553, 554, 555, 557, 559, 561, 565, 568, 570, 572, 574, 576, 578, 580 NEEDS SCREWS UNIT 563
- Nov 19, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire caulk NEEDS FIXING Units 259, 265 in 2 locations, UNITS INSULATED REMOVE INSULATION TO VERIFY FIRE CAULK Units 259, 261, 263
- Nov 18, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire Caulk for Units 255 & 272 OK
- Nov 18, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
FULL INSULATION Units 461, 463, 465
- Nov 18, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Drywall in Rim Area Only, Units 352, 363, 354, 355, 357, 359, 361, 363, 365, 370, 372, 374, 376, 378, 380
- Nov 17, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire Caulk Units 252, 253, 254, 257, 268 ABC 268 Data, 270, 274, 276, 278, 280. MISSING FIRE CAULK Units 272, 255
- Nov 17, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation for Units 452, 5453, 454, 455, 457, 459, Hallway between units 452-457. Exterior walls insulation only Units 352, 353, 354, 355, 357, 359, 361, 363, 365, 370, 372, 374, 376, 378, 380
- Nov 14, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation for units 468, 470, 472,474, 476, 478, 480, NW hallway between units 474-480 Stuffed mineral wool for fire blocking in dead space where building comes together in units 353, 354, 368
- Nov 12, 2025
Meet Contractor
SEE COMMENTSInspectorBrian Stemwedel
walking with David, noted fireblocking at floor level(s) in devising walls adjacent 352, 353, and 355, as well as shaft adjacent storage 363 were missing fireblocking at floor level. [718.2 MSBC]
- Nov 10, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
lids blown FG Units: 552, 553, 554, and 555
- Nov 10, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorBrian Stemwedel
above membrane gyp @ exterior walls. Units: 452, 454, 455, 457, 459, 461, 463, 465, 470, 472, 474, 476, 478, and 480
- Nov 7, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Rim insulation prior to gyp. Area 4C
- Nov 6, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Lids blown, units: 570, 572, 574, 576, 578, 580
- Nov 4, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorBrian Stemwedel
Gyp cover at rim above membrane (exterior wall rated assembly) Units: 552, 553, 554, 555, 557, 559, 561, 563, 565, 570, 572, 574, 576, 578, and 580
- Nov 3, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
SCREW PATTERNS Units 652, 653, 654,655, 657, 661, 663, 665, 668 Data, 668 ABC, 670, 672, 674, 676, 678, 680
- Nov 3, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
EXTERIOR WALLS Units 552, 553, 554, 555, 557, 559, 561, 563, 565, 570, 572, 574, 576, 578, 580 Hallways between units 552-580 OK
- Oct 31, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
UNITS 578 & 580 NEED CORRECTIONS, Fire Caulk corrections OK, Units 576, 574, 555, 554, 561, 3rd & 4th Floor hallway on West side of bldg & West side of hall OK, 3rd & 4th Floor NW hallway on South wall of hallway OK
- Oct 31, 2025
Commercial Wallboard
SEE COMMENTSInspectorMarshall Lind
Screw patterns 6th floor 1st layer in West hallway on exterior side OK, 6th floor NW hallway on South side of hallway wall OK
- Oct 29, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire Caulk Units 574, 572, 570, 568 Storage, 565, 557, 563, 561, 559, 553, 552, CORRECTIONS NEEDED UNITS 576, 574 Hallway, 555, 554, 561 Hallway, 565 Hallway
- Oct 28, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Exterior walls only, Units 652, 653, 654, 657, 659, 661, 663, 665, 670, 672, Interior hallway no poly between Units 652 - 668, Exterior hallway between Units 668A - 680 REMOVE 3 NAILS & SEAL
- Oct 27, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Exterior walls only Units 672, 674, 676, 678, 680
- Oct 24, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire caulk for Units 659, 676 & 659 hallway OK
- Oct 24, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Screw pattern for unit 227 OK
- Oct 23, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
FIRE CAULK Units 651, 652, 654, 655, 657, 663, 665, 668, 668ABC, 670, 672, 674, 678, 680 NEED FIX UNITS 676, 654, 654 Hallway STAIRWAY E & D Grid on ceiling for fire rated assembly OK
- Oct 23, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Screw patterns Units 228, 229, 230, 233, 236, 237, 238, 239, 240, 241, 242 ABC, 242 Data, 249, 250 MISSING SCREWS Unit 227
- Oct 21, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 243, 249, 250, 251 & Corrections on 236 OK
- Oct 20, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 237, 238, 239, 240, 241, 242 ABC, 242 Data, 247, Elevator A, Hallway Unit 236 - 249, MISSING INSULATION 236
- Oct 17, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
FULL INSULATION Units 227, 228, 229, 230, 233 HALLWAY & SHAFT in hallway Units 227 - 233
- Oct 15, 2025
Commercial Wallboard
CORRECTION NOTICEInspectorBrian Stemwedel
In both stairways adjacent pass through (33) stack and full height exit enclosure, noted PVC plumbing penetrations in ceiling and shaft walls. this is not allowed per 713.8.1 MSBC, no exceptions apply to Code Section. Asked Doug to contact architect to find solution to issue and texted him photos and Code section (Doug- 612-382- 3729)
- Oct 14, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation in rim area Units #239, 240, 241, 243, 249, 250, 251 OK
- Oct 13, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation in Unit 333 OK
- Oct 13, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Rock in rim area Units 227, 228, 229, 230, 233 OK
- Oct 13, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire caulk in Units 229, 230, 231, 237, 238, 239, 421 OK, SCREW patterns in Units 430 & 443 OK
- Oct 10, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
INSULATION IN FLOOR JOIST AREA Units 227, 228, 230 233 NOT READY IN UNIT 229, SHEAR WALL & DEAD SPACE Units 228, 229, 333, MECHANICAL SHAFTS INSULATION ON NW & North side middle of hallway OK
- Oct 10, 2025
Meet Contractor
SEE COMMENTSInspectorBrian Stemwedel
walked with Doug to review dead spaces and fireblocking. approved adjacent units 233/333 and stairway D
- Oct 8, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
FIRE CAULK Units 227, 228, 236, 239, 240 242 ABC, 242 Data, 245, 249, 250, 251, CORRECTIONS Units 229, 230, 231, 237, 238 Hallway 239, 241
- Oct 7, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 339, 240, 241, 342 ABC, 343, 347 349, 350, 351, HALLWAY from units 336 - 351 OK
- Oct 3, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Screw patterns for Units 440 & 443 OK
- Oct 3, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 327, 328, 329, 330, UNIT 333 ceiling not blown until wall with void space is fixed, Hallway from units 328-333, Units full insulation 336, 337, 338
- Oct 3, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Pool room 123A Fire rated construction exterior wall OK, Interior steel studs OK
- Oct 2, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
Framing in mech. shafts adjacent 68 stack and 55 stack. OK to insualte
- Oct 1, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
ROCK IN FLOOR JOISt AREA Units 327, 328, 329, 330, 333 SCREW PATTERN FULL WALLBOARD Units 427, 428, 429, 432, 433, 434, 435, 436, 437, 438, 439, 440, 441, 449, 450, 451 MISSING SCREWS 430, 443
- Sep 30, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Rock in Floor Joist Area Units 336, 337, 338, 339, 340, 341, 343, 349, 356, 357
- Sep 30, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Exterior wall insulation Units 327, 328, 329, 330, 333, 357
- Sep 29, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
INSULATION ON EXTERIOR WALLS Units 336, 337, 338, 339, 340, 341, 343, 350, MISSING INSULATION IN LIVING ROOM Unit 349
- Sep 25, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
FIRE CAULK INSPECTION: Units 323, 329, 336, 337, 339, 349 HAVE CORRECTIONS, Units 328, 330, 333 DISCUSSING GAP BY WALL, 338, 340, 341, 342ABC, 343, 347, 350, 351 OK
- Sep 25, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation inspection Units 101 Club, 124, 126 OK
- Sep 24, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation: Units Elevator 445, 447, 449 450, 431 OK
- Sep 24, 2025
Commercial Framing
SEE COMMENTSInspectorMarshall Lind
TALKED TO DAVE & DOUG ABOUT VOID GOING DOWN FROM UNIT 333 & NEED ARCHITECT DETAIL
- Sep 23, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation for units 436, 437, 438, 439, 440, 441, 442, 443, Stairway A 4th floor
- Sep 22, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 427, 428, 430, 432, 433, 434, 435 OK, UNIT 429 NOT READY
- Sep 19, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Wallboard screw patterns NEED TO ADD SCREWS UNIT 535, 551. Units 527 - 550 OK Section B
- Sep 17, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Rock in rim area for units 427 - 451
- Sep 17, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
2nd floor exterior walls framing & insulation 205 Leasing room, Furred out wall & insulation 2nd floor next to 3 hr rated wall on South end OK, & 213 Package room OK
- Sep 16, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
FLOOR JOIST RIM AREA Pre-rock Units 427 - 451
- Sep 15, 2025
Commercial Insulation
PARTIAL APPROVALInspectorChris Weaver
---STILL WAITING ON BRAUN REPORT REGARDING FIREWALL PENETRATIONS PREROCK INSULATION INSPECTION ALONG 4TH FLOOR PHASE 2 FIREWALL
- Sep 12, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
FIRE CAULK Units 427, 428, 429, 430, 433, 434, 436, 437, 438, 439, 440, 443, 449, 450, 451, North elevator & trash room OK, FIX FIRE CAULK IN UNITS 432, 435
- Sep 10, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Units 542, 543, 549, 550, Trash Room, 551 HAS MOISTURE IN CEILING
- Sep 9, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation for units 534, 536, 537, 538, 539, 540, 541, Hallway from units 534 - 541 OK
- Sep 9, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
South end Common Area 1st floor, NEED TO FIRE CAULK ALL PENETRATIONS GOING UP THRU CONCRETE CEILING, Rest of framing OK
- Sep 8, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
South end 2nd floor common area, Steel studs, NEED FIRE CAULK ON COUPLE OF HOLES ON 3HR RATED WALL, All other framing OK
- Sep 8, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
FULL INSULATION Units 527, 528, 529, 530, 532, 533, 535, UNIT 534 NEEDS BEDROOM CEILING BLOWN INSULATION, HALLWAY from units 526 - 535 OK
- Sep 5, 2025
Commercial Insulation
PARTIAL APPROVALInspectorDale Gronberg
* 5th floor rim gypsum in 5 units as noted on door cards
- Sep 4, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
---QUESTIONED TAPE AND MUD ON TRUSS SPACE DRYWALL, SCREWS AND SEAMS, U305 WALL TYPE PER DOUG VIEWED PREROCK ON 5TH FLOOR PHASE B
- Sep 3, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
PREROCK INSULATION ON ENTIRETY OF 5TH FLOOR PHASE B OK PREVIOUS CORRECTIONS MADE
- Sep 2, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
VIEWED 3 UNITS ON 5TH FLOOR PHASE B FOR PREROCK INSULATION - ONLY 3 DONE VIEWED SCREW PATTERNS ON 6TH FLOOR PHASE B, NOTES ON CARDS
- Aug 29, 2025
Commercial Framing
SEE COMMENTSInspectorMarshall Lind
Fire Caulk: Missing needs fixing Units 527, 529, 535 water pipe, 537, 538 gas line, 541 plumbing drain pipe, 543 - 2 holes Fire Caulk OK Units 528, 530, 532, 533, 534, 536, 539, 540, 542, Trash, 549, 550, 551
- Aug 26, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Units 640 & 641 corrections OK
- Aug 22, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
HEADERS/SQUASH BLOCKING/ROOF TRUSSES 655, 657, 659, 661, 665, 666 ABC, 670, 672, 674, 676, 678, 680 OK
- Aug 22, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
UNITS 640, 642 Trash, 649, 650, 657, Common area room, CORRECTIONS 641
- Aug 20, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation Units 627, 628, 629, 630, 632, 634, 635, 636, 637, 638, 639 Compete
- Aug 19, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorMarshall Lind
Per David, canceled inspection 6:06 am
- Aug 18, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire Caulk re-inspection, Units 628, 629, 630, 635, Common area are OK
- Aug 15, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire Caulk, CORRECTIONS FOR UNITS 628 Plumbing hole, 629 Bath fan wire 2 spots, 630 mechanical room 2 holes, 635 Water line on hallway wall, & COMMON AREA BY DOOR GOING TO EXTERIOR Units 627, 632, 633, 634, 636, 637, 638, 639, 640, 641, 644, Stairway A, 642, Trash room, 647, 649, 650, 657 OK
- Aug 14, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
HEADERS AND TRIMMERS ON 3RD FLOOR PHASE 2
- Aug 13, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
HEADERS/SQUASH BLOCKING & FLOOR JOIST Units 254, 255, 257, 270, 272, 274, 276, 278, 280, 268 Data/268ABC, 257, 261, 263, 265
- Aug 12, 2025
Fire
SEE COMMENTSInspectorLuke Berscheit
Preliminary radio signal testing done only in phase 1 since it has drywall and windows (no doors yet). Building will need an emergency responder radio coverage system. Emailed job sup. to notify of the requirement.
- Aug 11, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Wall board & screw patterns 303, 306, 308 309, 313, 315 317, 319, 320, 321, 322, 323, 324, 325, 326 382 OK, RECHECK UNITS 305 & 311, Units 217, 219, 221, 223, 24, 225, 226, 282 OK
- Aug 8, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
STEEL FIRE PROOFING, Stairway C & South elevator shaft, Braun inspected & tested thickness
- Aug 6, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
HEADERS & ROOF TRUSSES Units 630, 632, 633, 634, 635, 636, 637, 638, 639, 640, 641, 642, 643, 644A, Elevator A, 642 Trash, 649, 650, 651, 652, 653
- Aug 5, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
WALKED ROOF
- Aug 4, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation for Units 217, 219, 221, 223, 224, 225, 226, 282 OK
- Aug 1, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Sheathing inspection Grid 2 Grid A - L, Sheathing inspection Grid F Grid 7 -12 Court yard side, Some pieces damaged between 5 & 6 floor, fix when applying house wrap
- Jul 31, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
5TH FLOOR PHASE B HEADERS AND TRIMMERS INSPECTION OK
- Jul 30, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation & vapor barrier in floor truss area Units 224, 225, 226
- Jul 30, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Wallboard in floor truss area Units 217, 219, 221, 223, 282
- Jul 29, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation in Units 324, 325, 326, Insulation & vapor barrier in floor truss area in Units 217, 219, 221, 223, 282
- Jul 28, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Full insulation Units 311, 313, 315, 317, 319, 320, 321, 322, 323
- Jul 28, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Full rock Units 401, 403, 405, 406, 407 ABCD, 408, 409, 410, 411, 413, 415, 417, 419, 420, 421, 422, 423, 424, 425, 426
- Jul 25, 2025
Commercial Framing
SEE COMMENTSInspectorDale Gronberg
* Pre-insulation walk-thru of units 217-226 (OK)
- Jul 25, 2025
Commercial Insulation
PARTIAL APPROVALInspectorDale Gronberg
* Units 303 - 308 (OK)
- Jul 24, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
PRELIMINARY FRAMING 4TH FLOOR PHASE B, HEADERS AND TRIMERS INSPECTION OK
- Jul 23, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Wall board in floor joist area up to unit 326 OK
- Jul 22, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation in floor joist area exterior walls Units 319, 320, 321, 322, 323, 324, 325, 326
- Jul 22, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Rock in floor joist area Units 303, 305, 306, 308, 209, 382
- Jul 21, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation in floor joist area Units 303, 305, 306, 308, 309, 311, 313, 315, 317, 382 OK
- Jul 18, 2025
Commercial Framing
SEE COMMENTSInspectorMarshall Lind
Fire caulk & framing OK for units 303, 305, 306, 308, 309, 310, 311, 313, 315, 320, 321, 322, 323, 324, 325, 326, 382 CORRECTIONS NEEDED UNITS 307 ELECTRICAL ROOM - HOLE IN FLOOR & AROUND ELECTRICAL SMURF TUBE, 317 BIG HOLE ON HALLWAY WALL, 319 HALLWAY WALL WATER LINE PIPE
- Jul 17, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
PHASE B MECHANICAL SHAFTS LOOKED AT
- Jul 16, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
1st layer rock units 413 & 415, Rock completed units 524 & 526 4th floor break off clips on 3hr wall OK
- Jul 15, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Units 419, 420, 421, 422, 423, 424, 425, 426 OK, Hallway to Unit 426 OK
- Jul 15, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Units 401, 403, 405 OK Units 501, 503, 505 506, 508, 509, 510, 511, 513, 515, 517, 519, 520, 521, 522, 523, 525, 582 All screw patterns OK
- Jul 14, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
2nd layer of rock in stairway C between floors 6/5 and 5/4
- Jul 14, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation OK for units 408, 410, 411, 413, 415, 417, 490 elevator lobby, Hallway from unit 408 - 417
- Jul 11, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation OK Units 401, 403, 405, 406, 407 ABCD, 409, Hallway from units 401 - 405
- Jul 10, 2025
Commercial Framing
PARTIAL APPROVALInspectorChris Weaver
HEADERS AND TRIMMERS CHECKED ON 4TH FLOOR PHASE 2 OK
- Jul 9, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Rock in rim area for units 401, 405, 406, 413 OK
- Jul 8, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation in rim area for units 417 - 426 OK
- Jul 8, 2025
Commercial Wallboard
CORRECTION NOTICEInspectorMarshall Lind
UNITS 401 & 413 ROCK IN RIM AREA EXTENDS TO FAR DOWN GOES BELOW INSULATION & POLY, TALKED TO DOUG ON SITE
- Jul 7, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Pre rock insulation inspection in truss space for units 401, 403, 405, 406, 408, 409, 411, 413, 415, 482
- Jul 3, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
WALKED 4TH FLOOR PHASE A FOR FIRECAULK AND INSULATION BLESSING ---LOCATED MULTIPLE PENETRATIONS NOT CAULKED, INCLUDING TIE DOWNS AND ALARM ---FIREWALL HAS BEEN PENETRATED BY "SMURF TUBE" AND A LOT OF ELECTRICAL PENETRATIONS, REQUESTED DETAILS ---WET WALL ALONG FIRE WALL HAD MOST FIRE CLIPS RIPPED OUT FOR PLUMBING RE-WALK WITH ML
- Jul 2, 2025
Meet Contractor
SEE COMMENTSInspectorChris Weaver
PHASE B 2ND FLOOR FRAMING OK MISSING MISC TRIMMERS, SQUASH BLOCKS, WILL BE READY FOR NEXT INSPECTION
- Jul 1, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation OK in units 521, 523, 525, NEED INSULATION IN CEILING AREA IN UNITS 524, 526
- Jun 30, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Units 506, 508, 509, 510, 511, 513. 515, 517, 519, 520, 522 OK, 5th floor hallway from 501-522 OK
- Jun 27, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Exterior sheathing on East side and North East section of apartment, East side from East entrance North, North section from East wall to one section before jog in building to the North
- Jun 26, 2025
Commercial Insulation
PARTIAL APPROVALInspectorDale Gronberg
* Units on 5th floor as noted on door cards (OK)
- Jun 25, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Exterior walls only Units 515-526 OK
- Jun 25, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Stairway C 1st layer on 6th floor only screw pattern OK Drywall screw patterns units 601-626 & 682 OK UNIT 515 NOT DONE NEED TO FINISH WALL BOARD WHEN TRASH CHUTE IS REMOVED Wallboard in rim area units 515-526
- Jun 24, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
Pre-rock drywall in truss space for units 501-525 OK
- Jun 24, 2025
Commercial Insulation
CORRECTION NOTICEInspectorMarshall Lind
WANTED INSULATION INSPECTION ON EXTERIOR WALLS FOR UNITS 515-526, NO VAPOR BARRIER AT THIS TIME, Text Dave not ready
- Jun 23, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Framing units 517, 519, 520, 522, 523, 524, 525, 526
- Jun 23, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
INSULATION EXTERIOR WALLS ONLY Units 501, 503, 505, 506, 508, 509, 511, 513, 515, 582
- Jun 20, 2025
Commercial Framing
PARTIAL APPROVALInspectorDale Gronberg
* Framing 5th floorunits as marked on door cards (OK) ***UNIT #582 NEEDS FIRECAULK AT 2 PLUMBING PENETRATIONS IN BATHROOM TOP PLATES*** ***UNIT 511 NEEDS STUD BELOW CUT TOP PLATE ON TRUSS BEARING WALL***
- Jun 18, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Fire blocking unit 682 OK SECTION B Roof sheathing,NEED TO REPLACE SHEATHING WITH FIRE RATED SHEATHING AT RATED WALL LOCATION Talked to Dave about access to mechanical units & needing ladders
- Jun 16, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Corrections on units 605, 608, 613, 615, 619, 621, 623 OK, Insulation in units 624, 625, 626 OK
- Jun 13, 2025
Commercial Framing
PARTIAL APPROVALInspectorDale Gronberg
***AIR SPACE IN DOUBLE HEADERS MUST BE INSULATED TO AVOID CONDENSATION** * The following un its needs headers insulated 605,608,613,615,619,621,623 * Insuation in units 601,603,606,609,611,617,620,622 (OK) * Re-inspection on Monday. Take photos of 605 & 608 headers if drywalling today
- Jun 11, 2025
Meet Contractor
SEE COMMENTSInspectorKevin McDermott
Amenity roof deck and phase 2 roof deck with parapet wall framing OK.
- Jun 10, 2025
Commercial Insulation
PARTIAL APPROVALInspectorChris Weaver
SHEATHING PATTERS ON PHASE B REVIEWED OF 7 AND 7 DRAFT STOPPING DALE REQUESTED COMPLETED
- Jun 9, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
INSULATION UER PREROCK AREA IN DEMO UNITS OK
- Jun 6, 2025
Commercial Framing
PARTIAL APPROVALInspectorDale Gronberg
* Mock up Units 301 & 603 okay to insulate * 6TH FLOOR UNIT FRAMING: Okay as signed fon door cards * Add draftstopping at ceiling on common wall from Party room to dwelling * Unit 625 needs spray foam on rim
- Jun 4, 2025
SOG/Vapor Barrier
PARTIAL APPROVALInspectorMarshall Lind
North side & West side along parking garage, Need to seal around all bolts penetrating poly & all ripped areas. All pipes going thru poly sealed OK, talked to Doug on site
- Jun 2, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
---SHAFT WALLS INSULATED AND DRYWALL 1ST LAYER, NO BLOCKING PRESENT AT ALL. SWH S4.4 INDICATES ALL SHAFT WALLS MUST BE BLOCKED
- May 30, 2025
SOG/Vapor Barrier
PARTIAL APPROVALInspectorMarshall Lind
North East side Phase B poly & seal OK
- May 30, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Phase A Mechanical shafts screw patterns floors 2 - 6 OK, Elevator shaft screw patterns floor 3, Elevator shaft floor 4 - 5 insulation OK, 6th floor elevator not ready
- May 28, 2025
SOG/Vapor Barrier
SEE COMMENTSInspectorChris Weaver
LOOKED AT UNTAPED SHAFTS, 1ST LAYER
- May 27, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
PHASE A 3rd floor headers & squash blocking, Add squash blocking Unit 330, Braced wall screw pattern OK units 301 & 303, Met with Rylan
- May 21, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
4TH FLOOR PHASE A Headers & squash blocking Ok CORRIDOR SIDE FLOORS 1-6 EXTERIOR SHEATHING From Tunnel to )( stack, Replace broken pieces when installing house wrap
- May 19, 2025
Commercial Framing
PARTIAL APPROVALInspectorDale Gronberg
* 4TH FLOOR: 1st layer gypsum on Elevator A and trash chute shaft * 5TH FLOOR PHASE A: Exterior wall headers (OK) * Add a 3rd 2x10 (H7) over Unit #508 Patio Door with top bearing floor trusses
- May 12, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
6th floor headers on South end of building OK, 1. Need fire blocking between rated walls on elevator shaft on South end. 2. Need squash blocking in elevator shaft on 3rd level on North end. 3. Shaft on East end of floor 6 on South end of building needs another layer of rock All other shafts/elevators shafts/chutes fire rating OK on 2nd thru 6th on South end and floors 2nd & 3rd on North end.
- May 12, 2025
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
South end of building, Insulation and roofing OK, Need to finish installing boots over all penetrations and seal. At roof drain, will be applying closed cell spray foam insulation to the bottom of roof deck, 4 1/2 inches to get R value
- May 7, 2025
Commercial Framing
SEE COMMENTSInspectorMarshall Lind
Roofers have less than 10% done, Roofers not on site today due to wind, Will inspect Mon Morning
- Apr 30, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Exterior sheathing inspection before house wrap, South end South side wall only, Fixing sheathing that is damaged as they install house wrap, Need to seal wrap around deck brackets, window installer will be doing exterior taping. Need to nail parapet sheathing
- Apr 25, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
B section Level 2 level NE part, Stairway A Shaft & Stairway E rock & nailing, 01 Stack 3-5th floor ATS rods OK, 5th floor 515-517 shaft & 29 stack rock & nailing OK
- Apr 14, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
South elevator fire rated assembly 4th floor W/insulation & house wrap, Shafts on South end fire rated assemblies, NEED TO FIX SHAFTS FIRE RATED WALLS WHERE FLOOR JOIST BUTT UP AGAINST
- Apr 9, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
South elevator 2nd floor 2 layers of rock, Shear walls South side level 3 OK
- Apr 9, 2025
SOG/Vapor Barrier
PARTIAL APPROVALInspectorMarshall Lind
SOG Vapor barrier South side Grid H.5 - Q, Grid 16 - 13
- Apr 8, 2025
SOG/Vapor Barrier
NOT READYInspectorMarshall Lind
Call for re-inspection
- Apr 8, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorMarshall Lind
South elevator 2nd floor wall rating OK, South rated fire wall fire clips OK
- Apr 1, 2025
SOG/Vapor Barrier
NOT READYInspectorMarshall Lind
Due to weather, Dave stated he called Beth & canceled
- Mar 31, 2025
Commercial Framing
SEE COMMENTSInspectorMarshall Lind
Met with head framer
- Mar 28, 2025
SOG/Vapor Barrier
PARTIAL APPROVALInspectorMarshall Lind
Lowest floor Grid J.6 - D, Grid 12 - 16
- Mar 18, 2025
Commercial Framing
SEE COMMENTSInspectorMarshall Lind
Pre construction meeting with Dave, Dave will be main contact for inspections, 847-845-6206
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.