Building
1508 Clare La, Minnetonka
New, New 55+ multi family, consisting of 121 units with amenity spaces
- Apr 9, 2026·9:00 AM - 11:00 AM
Commercial Final
scheduledInspectorBrian Stemwedel
- Apr 6, 2026
Commercial Final
PARTIAL APPROVALInspectorBrian Stemwedel
all 3rd floor units N. of firewall. Window opening limiters were NOT installed. need to limit openings to <4" where sill is >72" from grade
- Mar 3, 2026
Commercial Final
SEE COMMENTSInspectorBrian Stemwedel
at mechanical inspection, noted fire doors protecting elevator lobby doors are required to have listed H gaskets installed. (verify at final) additionally, there is a clearance issue with the bottom of the door and the tile in the elevator lobby. contractor proposed cutting down the bottom of the fire door for clearance (includes bottom latch) told contractor that any modifications to door would need to be approved by the listing agency (Intertek) [NFPA 80] follow up on this
- Jan 28, 2026
Commercial Framing
SEE COMMENTSInspectorBrian Stemwedel
looked at transition to deck from interior FF elevation (looked at worst condition) Contractor made every attempt to meet accessibility requirement given elevation diff. told contractor that proposed threshhold condition would be acceptable with mini 'ramp'
- Jan 7, 2026
Commercial Framing
APPROVEDInspectorBrian Stemwedel
met with Steve on site to discuss Accessibility requirements particularly at grade level entry doors. All framing complete
- Jan 7, 2026
House Wrap/Lathing
APPROVEDInspectorBrian Stemwedel
remaining lath for cultured stone (exterior)
- Jan 7, 2026
Commercial Footing
APPROVEDInspectorBrian Stemwedel
All footings complete
- Dec 30, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorBrian Stemwedel
at elevators/ trash chutes- OK to install final layer of gyp. framing between shaft/ interior ISCWAP
- Dec 23, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
Looked at interior framing at shaft wall in elevator B. All penetrations still need to be firestopped. told contrctor to take pictures and could frame in 2nd wall in front of shaft concealing elevator door mechanism. also verified shaft integrity and separation between trash chute shaft and adjacent mechanical shaft .
- Dec 11, 2025
Commercial Wallboard
APPROVEDInspectorBrian Stemwedel
Level 1 Shear walls. plywood/ gyp nail schedule
- Nov 20, 2025
Meet Contractor
SEE COMMENTSInspectorBrian Stemwedel
fireblocking identified on 11/19 in level -01 started and approved. need to finish in corridor prior to concealing
- Nov 19, 2025
House Wrap/Lathing
PARTIAL APPROVALInspectorBrian Stemwedel
screened in porch on west elevation: Level -1, 1
- Nov 19, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Level -1 *** Fireblocking required at floorline at framed wall against CMU firewall. verify before concealing. Noted lid of corridor level -1, FG batt in joist cavities
- Nov 12, 2025
Commercial Framing
NOT APPROVEDInspectorBrian Stemwedel
3 hour firewall penetration with pvc dwv. Units 015 and 017 NEED 3 hour detail for through penetrations of firewall
- Nov 10, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorBrian Stemwedel
shear wall details on 1st floor phase II
- Nov 6, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorBrian Stemwedel
2nd floor shear walls phase 1, 2, and 3
- Nov 4, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
unit framing :101, 102, 103, 104, 105, 106, 107, 108, 109, 110, 111, 112, 113
- Nov 4, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
ex wall FG batt and VB Units: 121, 123, 124, 125, 126,127, 128, 129, 130, 132, 133, 134, 135, 136, 138, 174
- Oct 28, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorBrian Stemwedel
verified GYP behind FD frames as required on 1st and 2nd floors. gyp extends to firewall liner as required
- Oct 27, 2025
House Wrap/Lathing
PARTIAL APPROVALInspectorBrian Stemwedel
North facing wall of south courtyard, prepped for scratch coat
- Oct 27, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorBrian Stemwedel
2nd floor phase 3. Shear walls
- Oct 23, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
Unit framing: 117, 121, 123, 124, 125, 126, 127, 128, 129, 130, 131, 132, 133, 134, 135, 136, 137, and 138
- Oct 22, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Lids blown in FG Units: 201, 202, 203, 204, 205, 206, 207, 208, 209, 210, 211, 212, and 213
- Oct 20, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
SPF in rims, Ex. wall FG batt w/ VB Units: 201, 202, 203, 204, 205, 206, 207, 208, 209, 210, 211, 212, and 213
- Oct 16, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
Unit framing: Units 201, 202, 203, 204, 205, 206, 207, 208, 209, 210, 211, 212, and 213
Show 79 earlier inspections
- Oct 15, 2025
House Wrap/Lathing
PARTIAL APPROVALInspectorBrian Stemwedel
NE wall above entry, lath approved and ok to apply scratch coat
- Oct 15, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Lids (Blown) Units: 214, 215, 216, 217, 218, 219, 220, 221, 222, 223, 224, 226, and Library
- Oct 14, 2025
Commercial Wallboard
CORRECTION NOTICEInspectorBrian Stemwedel
gyp does not extend behind fire door frame (3rd floor) remove frame and install gyp per NFPA 80 and approved details on plans
- Oct 13, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Ex wall insualtion w/ VB Units: 214, 215, 216, 217, 218, 219, 220, 221, 222, 223, 224, 226, 228, and library
- Oct 9, 2025
Commercial Framing
CALL FOR REINSPECTIONInspectorBrian Stemwedel
Need to verify door detail at firewall, at time of unit framing inspection, it was noted 5/8" gyp on corridor walls did not extend under frame each side (only partial coverage)
- Oct 9, 2025
House Wrap/Lathing
PARTIAL APPROVALInspectorBrian Stemwedel
Lath and underlayment for cultured stone adjacent N courtyard @ 38 stack
- Oct 8, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Insulation in Ex. walls, demising walls, lids. Units 225, 227, 228, 229, 230, 231, 232, 233, 234, 235, 236, 237, and 238
- Oct 7, 2025
Meet Contractor
PARTIAL APPROVALInspectorBrian Stemwedel
Looked at reinforcement for in ground pool (Shotcrete) all rebar ISCWAP does not include hot tub area (constructed after pool (connected) is complete and common pool wall stripped on hot tub side
- Oct 6, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
SPF @ rims. OK to net lids Units 225, 227, 228, 229, 230, 231, 232, 233, 234, 235, 236, 237, 238
- Oct 2, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
*** Note: missing blocking for ADA Type B in all units, spoke to Steve, Steve said they would be removing pre rock to install blocking. will monitor progress on future inspections. Unit framing: Units 225, 227, 228, 229, 230, 231, 232, 233, 234, 235, 236, 237, 238 -ok to insulate with understanding ADA blocking needs to be verified prior to concealing
- Sep 30, 2025
Commercial Framing
NOT READYInspectorBrian Stemwedel
no units ready for inspection at scheduled time
- Sep 29, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Unit insulation exterior walls FG batt and VB, interior demising walls Noted at unit demising walls, in roof/ ceiling assembly over fire partitions, they need to draftstop areas into volumes less than 160 cu. ft. Units: 301, 302, 303, 305, 306, 307, 308, 309, 310, 311, 312, and 313
- Sep 26, 2025
Commercial Framing
PARTIAL APPROVALInspectorDale Gronberg
* 11 - 3rd floor lids as marked on door cards. One was not ready
- Sep 25, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
Unit framing, Noted at unit demising walls, in roof/ ceiling assembly over fire partitions, they need to draftstop areas into volumes less than 160 cu. ft. Units: 301, 302, 303, 305, 306, 307, 308, 309, 310, 311, 312, and 313
- Sep 24, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
exterior unit walls with VB and interior demising walls Units: 316, 317, 318, 319, 320, 321, 322, 323, 324, and 326
- Sep 23, 2025
Commercial Framing
NOT READYInspectorBrian Stemwedel
- Sep 22, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
SPF insulation in rims and roof drains and leaders (where present) Unit(s): 316, 317, 318, 319, 320, 321, 322, 323, 324, and 326
- Sep 19, 2025
Commercial Framing
PARTIAL APPROVALInspectorBrian Stemwedel
unit framing, no shear walls. verified Aluminum clips @ fire wall. Units 314, 315, 316, 317, 318, 319, 320, 321, 322, 323, 324, and 326
- Sep 18, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
3RD FLOOR PHASE 1 CEILING ROCK SHOWING 18" OFFSET BETWEEN 1ST AND 2ND LAYER
- Sep 17, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
VIEWED FIXES FOR DAMAGED STRUCTURAL MEMBERS, UPLOADED TO PROJECTDOX MISSING FIRE CLIPS ON MIDDLE FIREWALL
- Sep 16, 2025
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Unit wall insulation, exterior wall insulation (FG Batt w/ VB) (11 units) Units 325, 327, 328, 329, 330, 331, 333, 334, 335, 336, 338
- Sep 15, 2025
Commercial Framing
PARTIAL APPROVALInspectorChris Weaver
3RD FLOOR, NORTH END, PREROCK INSPECTION, INSULATION IN SOFFITS
- Sep 12, 2025
Commercial Framing
SEE COMMENTSInspectorMarshall Lind
SHEAR WALL TOP FLOOR WEST END, Units 333, 332, 327, Unit 333 need to cut off rods and fix fire blocking or fire caulk penetration. STAIRWAY C pre-rock, NEED FIRE BLOCKING ON TOP LEVEL, NEED FIRE CAULK BETWEEN FLOOR 2 & 3 ELECTRICAL WIRE
- Sep 11, 2025
Commercial Wallboard
PARTIAL APPROVALInspectorBrian Stemwedel
Building B: South Elevator Shaft 3rd floor, 1st layer- screw patterns ok Building A: 'Center' Elevator Shaft 3rd floor, 1st layer- screw patterns ok Center mechanical shaft, 3rd floor, 1st layer Trash Chute, 3rd floor, 1st layer N. Mechanical Shaft, 3rd floor, 1st layer
- Aug 29, 2025
Commercial Insulation
CANCELLED APPOINTMENTInspectorDale Gronberg
- Aug 28, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
INSULATION PROGRESS CHECK
- Aug 27, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
DISCUSSED SPRINKLER BOXES, INLINE FAN IN LOCKER ROOMS, AND SHAFT SEPARATION WITH VENTILATION AND GARBAGE CHUTES
- Aug 26, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
PROGRESS CHECK ON ROOF MECHANICAL SHAFT WITH 4" SPRINKLER LINE NOT BIG ENOUGH FOR CONNECTION BOX, LOOKING FOR DETAIL OF SOLUTION
- Aug 25, 2025
Commercial Insulation
SEE COMMENTSInspectorChris Weaver
ROOF INSULATION PROGRESS CHECK OK
- Aug 22, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
FOUNDATION, South wall to jog in wall on East side, Marked on plans/ No grid lines
- Aug 22, 2025
Commercial Framing
NOT READYInspectorMarshall Lind
ROOF INSULATION NOT READY
- Aug 20, 2025
Commercial Framing
PARTIAL APPROVALInspectorChris Weaver
PARAPET INSULATION OK
- Aug 19, 2025
Commercial Insulation
PARTIAL APPROVALInspectorChris Weaver
PARAPET INSULATION OK LOW ROOF NORTH END 11" OF ISO ON ROOFS FIRST SECTION. WILL BE CALLING DAILY FOR PROGRESS INSPECTIONS
- Aug 18, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Aug 13, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
VIEWED ROOF AND PARAPET INSULATION ON TALL ROOF AND SHORT ROOFS
- Aug 11, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
OSHA ON SITE VISIT SITE CLOSED
- Aug 7, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Aug 6, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
VIEWED 2ND LAYER SOUTH END MECH AND STAIR SHAFTS
- Aug 4, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
VIEWED STAIR AND MECH SHAFT WALLS3RD FLOOR 1ST LAYER SOUTH END
- Jul 31, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
3RD FLOOR CENTER SHAFTS 2ND LAYER OK
- Jul 30, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
3RD FLOOR MIDDLE ELEVATOR, STAIR, MECH SHAFTS DRYWALL PATTERNS OK
- Jul 28, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
3RD FLOOR SHAFT PATERNS
- Jul 24, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Jul 23, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
VIEWED MECH SHAFT ROCK
- Jul 21, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Jul 17, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
2ND LAYER ON SOUTH STAIRS AND ELEVATOR SHAFTS
- Jul 16, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Jul 15, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
1ST LAYER ROCK SOUTH SIDE STAIR TOWER, ELEVATOR AND MECH SHAFT
- Jul 14, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Jul 9, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
VIEWED 2ND FLOOR CENTER MECHANICAL SHAFT
- Jul 7, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
2ND LAYER OF ROCK ON EXTERIOR OF SHAFTS ON 2ND FLOOR
- Jul 3, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
SOUTH STAIR TOWER EXTERIOR ROCK 1ST LAYER
- Jul 2, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
1ST LAYER ROCK ON NORTH STAIR TOWER 2ND FLOOR
- Jun 30, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
MORE VISUAL CONFIRMATIONS OF LAYERS OF DRYWALL ON MISC SHAFTS
- Jun 26, 2025
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Jun 25, 2025
Commercial Framing
PARTIAL APPROVALInspectorChris Weaver
VIEWED 2ND LAYER OF EXTERNAL SHAFTS
- Jun 24, 2025
Commercial Framing
PARTIAL APPROVALInspectorChris Weaver
VIEWED 2ND FLOOR 1ST LAYER OF ROCK ON STAIR TOWERSAND ELEVATOR ALSO VIEWED PATTERNS ON PARTITION WALL SHEAR PATTERNS
- Jun 18, 2025
Commercial Framing
PARTIAL APPROVALInspectorChris Weaver
VIEWED 2ND LAYER DRYWALL ON STAIR SHAFTS EXTERIOR STAGGERED
- Jun 17, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
VIEWED ALL LOWER LEVEL PARTY WALLS PREROCK RIP AND INSULATION MECHANICAL SHAFTS DRYWALL 2 LAYERS STAGGERED ON ALL BUT 1, WILL REPAIR TIE ROD HOLD DOWNS NOT INSTALLED YET LOWER LEVEL PARTY WALL SHEAR NAIL PATTERS OK
- Jun 10, 2025
Commercial Framing
SEE COMMENTSInspectorChris Weaver
CONSULTATION REGARDING INSPECTIONS AND EXPECTATIONS
- Jun 3, 2025
Meet Contractor
CANCELLED APPOINTMENTInspectorChris Weaver
- May 16, 2025
Radon
APPROVEDInspectorKevin McDermott
South side of residential area OK. Small rooms off residential corridor OK.
- May 13, 2025
Radon
PARTIAL APPROVALInspectorKevin McDermott
Under slab radon barrier at North half of west side at residential units OK. Sealed at edges. Toilet holes are open for plumber and will need to be sealed after plumbing work.
- May 12, 2025
Commercial Footing
NOT APPROVEDInspectorKevin McDermott
Under slab vapor barrier not done correctly. Also serves as a RADON barrier. Plans show poly going up the stem wall on all sides. Correct and call for re-inspection.
- Mar 19, 2025
Commercial Footing
CANCELLED APPOINTMENTInspectorChris Weaver
- Mar 18, 2025
Commercial Footing
PARTIAL APPROVALInspectorChris Weaver
PADS 12/J-H, 18-19/J-K POOL FOOTING W/ PADS, POOL HAS TURNED 180 DEG FROM CURRENT PLAN STRIP FOOTING 17-27/J
- Mar 17, 2025
Commercial Footing
CANCELLED APPOINTMENTInspectorChris Weaver
- Mar 14, 2025
Commercial Footing
PARTIAL APPROVALInspectorKevin McDermott
Strip footing partial along east side. 5 pads. Marked on site plan.
- Mar 13, 2025
Commercial Footing
PARTIAL APPROVALInspectorKevin McDermott
12 pad footings and strip footing along north end. Marked on site plan.
- Mar 12, 2025
Commercial Footing
CANCELLED APPOINTMENTInspectorChris Weaver
- Mar 11, 2025
Commercial Footing
APPROVEDInspectorDale Gronberg
* 7 1/2" bead board nd 1 1/2 rigidstyro R-30 (OK)
- Mar 7, 2025
Commercial Footing
PARTIAL APPROVALInspectorKevin McDermott
15 pads X'd on plan in job trailer.
- Mar 4, 2025
Commercial Footing
PARTIAL APPROVALInspectorKevin McDermott
Strip footings: Grid A continuance to north end. 4 interior pads on G and J.
- Mar 3, 2025
Commercial Footing
CANCELLED APPOINTMENTInspectorKevin McDermott
- Feb 28, 2025
Commercial Footing
PARTIAL APPROVALInspectorKevin McDermott
Strip footings 1,2,3/ E-A A/ 1-10. Pads D.2/ 7,8,10,11,13. 38 deg
- Feb 27, 2025
Commercial Footing
CANCELLED APPOINTMENTInspectorChris Weaver
- Feb 26, 2025
Commercial Footing
PARTIAL APPROVALInspectorChris Weaver
F4-6 PADS AT M/4,6,AND 7 & H, I/4 STRIP FOOTINGM/9 THRU G/3 PADS F5-6 AND F6-6 AT GRID F/4, 6, 7, 8, AND 10
- Feb 24, 2025
Commercial Footing
SEE COMMENTSInspectorChris Weaver
PADS AT GRIDS - ALL F-5-6 AND F6-6 REENFORCEMENT G,J,K / 6,7,8 - K/4 CALLING FOR DEMO PERMIT, LOTS OF CONCRETE RECYCLING HAPPENING APPARENTLY COUNTY WAS ALREADY OUT FOR INSPECTIONS, I REQUESTED REPORT
- Feb 18, 2025
Commercial Footing
CANCELLED APPOINTMENTInspectorDale Gronberg
* Called contractor due to -15 degree weather. No footings today
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.