PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED217773

Building

5612 Johnson Dr, Edina

IssuedJan 29, 2025
StatusUnknown
Value$800,000
Inspections56
Scope of work

New, New Home with deck

Location context
Parcel3211721130081
Coordinates44.90166, -93.36598
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$4,000
Total paid$4,000
Timeline
ApprovedJan 24, 2025
IssuedJan 29, 2025
Inspection record
Inspections56
Passed46
Failed0
  1. Dec 2, 2025

    Building Final

    Approved, w/ Comments

    InspectorLindsay Evans

    All other aspects of permit have been verified and approved. OK to final/close permit.
  2. Dec 2, 2025

    Escrow

    No Inspection Required

    InspectorLindsay Evans

    NO ESCROW PAID After completing all final reviews, it appears there was no escrow paid when this permit was originally issued.
  3. Dec 1, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

    Conducted final inspection - everything OK. Took Final New Home photos and uploaded to PDox. IP removed from nearby CB.
  4. Nov 24, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

    Per Water Resources: Original house was built after the original watermain. A well is unlikely on the lot. If one is encountered during construction it will need to be sealed and documented with the city.
  5. Nov 17, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

  6. Nov 12, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

  7. Nov 10, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

    Received online escrow refund request. Working to process.
  8. Nov 3, 2025

    Tree Final (call 952-826-0308)

    Approved

    InspectorLaura Beres

    planted 3 new trees.
  9. Nov 3, 2025

    Final-NEW HOME

    Approved

    InspectorPeter Akmenkalns

  10. Oct 31, 2025

    Final-NEW HOME

    Partial Approval

    InspectorPeter Akmenkalns

    need trees ok then ok to issue full co
  11. Oct 29, 2025

    Final-NEW HOME

    Cancelled

    InspectorPeter Akmenkalns

  12. Oct 24, 2025

    Engineering (call 952-903-5728)

    Approved

    InspectorAndy Reinisch

  13. Oct 24, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  14. Oct 22, 2025

    Residential Redevelopment Coordinator

    Approved

    InspectorLindsay Evans

  15. Oct 22, 2025

    Planning

    Approved

    InspectorKris Aaker

  16. Oct 22, 2025

    Final As Built Survey

    Progress Report

    InspectorGodwin Annin

    - Final As Built Survey ok with Building - Distributed to other Dept for review.
  17. Oct 21, 2025

    Blower Door Test (Air Leakage)

    Approved

    InspectorPeter Akmenkalns

    recived via email 1.24 ACH
  18. Oct 20, 2025

    Final-NEW HOME

    Not Approved

    InspectorGodwin Annin

    - Egress ladder required in Egress window - Blower door test report not ready - Seal attic access in garage - Electrical final not ready - Plumbing permit still open requiring backflow report.
  19. Oct 15, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  20. Oct 2, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Get bio logs readjusted along the front property line at end of day.
  21. Sep 18, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  22. Sep 5, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  23. Aug 20, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  24. Aug 4, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  25. Jul 29, 2025

    Framing-New Home

    Approved

    InspectorPeter Akmenkalns

Show 31 earlier inspections
  1. Jul 18, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  2. Jul 16, 2025

    Lath

    Approved

    InspectorBrian Crask

  3. Jul 11, 2025

    Construction Fence

    Approved, w/ Comments

    InspectorLindsay Evans

    Safety fence still installed but no longer needed.
  4. Jul 11, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Rock entrance and site sign good. Need to clean up street at end of day. Need to replace damaged bio logs near entrance
  5. Jun 30, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  6. Jun 10, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  7. Jun 5, 2025

    Insulation

    Approved

    InspectorGodwin Annin

  8. May 29, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  9. May 28, 2025

    Framing-New Home

    Partial Approval

    InspectorPeter Akmenkalns

    tighten anchor add straps to front bump out per engineering
  10. May 12, 2025

    Erosion Ctrl/Const Entrance

    Approved, w/ Comments

    InspectorLindsay Evans

    Seasonal Inspection - Spring OK
  11. Apr 29, 2025

    Construction Fence

    Approved, w/ Comments

    InspectorLindsay Evans

    No longer needed
  12. Apr 29, 2025

    Erosion Ctrl/Const Entrance

    Approved, w/ Comments

    InspectorLindsay Evans

    Clean up street at end of day
  13. Apr 25, 2025

    Weather Barrier/Flashing

    Approved

    InspectorTedd Nelson

    - House wrap and flashing
  14. Apr 24, 2025

    Floor Slab

    Approved

    InspectorGodwin Annin

  15. Apr 17, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  16. Apr 17, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  17. Mar 21, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  18. Mar 21, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  19. Mar 4, 2025

    Foundation Pre-Backfil

    Approved

    InspectorScot Jandro

    pending TOF survey
  20. Mar 4, 2025

    Foundation Pre-backfil (Top of foundation survey)

    Approved

    InspectorScot Jandro

    931.1500 VS proposed 931.16
  21. Feb 28, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  22. Feb 24, 2025

    Poured Foundation Reinforcement

    Approved

    InspectorGodwin Annin

  23. Feb 18, 2025

    Poured Foundation Reinforcement

    Cancelled

    InspectorPeter Akmenkalns

    to cold
  24. Feb 11, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  25. Feb 11, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  26. Feb 7, 2025

    Construction Fence

    Approved

    InspectorScot Jandro

  27. Feb 7, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorScot Jandro

  28. Feb 7, 2025

    Footing

    Approved

    InspectorScot Jandro

  29. Jan 24, 2025

    Tree Protection (call 952-826-0308)

    Approved

    InspectorLindsay Evans

  30. Jan 24, 2025

    Preconstruction

    Approved, w/ Comments

    InspectorLindsay Evans

    Rock delivered in pile on old/existing driveway, will need to be spread out for proper construction entrance. Street needs to be cleaned and bio logs repositioned to eliminate runoff onto street.
  31. Dec 30, 2024

    Tree Plan

    Approved, w/ Comments

    InspectorLindsay Evans

    See tree escrow permit- NRMP ED217394, preserving 10 trees, removing 2 non-protected trees. LB

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.