#ED225563

Building

5800 Drew Ave S, Edina

IssuedFeb 11, 2026
StatusUnknown
Value$750,000
Inspections14
Scope of work

Addition, Partial demo of existing home, then rebuild to plan

Location context
Parcel2002824320072
Coordinates44.89799, -93.32654
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$3,750
Total paid$3,750
Timeline
ApprovedJan 30, 2026
IssuedFeb 11, 2026
Inspection record
Inspections14
Passed11
Failed0
  1. Mar 20, 2026

    Floor Slab

    Approved

    InspectorRick Chase

  2. Mar 12, 2026

    Foundation Pre-Backfil

    Approved

    InspectorScot Jandro

    waterproofing, exterior insulation and slip sheet okl Soil is sand, no draintile required
  3. Mar 11, 2026

    Erosion Ctrl/Const Entrance

    Approved

    InspectorBrian Crask

  4. Mar 11, 2026

    Construction Fence

    Approved

    InspectorBrian Crask

    Construction safety fence installed around construction site with caution signs of danger do not enter.
  5. Mar 11, 2026

    Foundation Pre-Backfil

    Not Approved

    InspectorBrian Crask

    -Note: The water proofing, insulation, and drain tile are not ready for inspection -The Poured Foundation Reinforcement inspection is not fully approved and has outstanding action items required to be addressed before the Foundation Pre-Backfill inspection can be completed.
  6. Mar 5, 2026

    Poured Foundation Reinforcement

    Partial Approval

    InspectorScot Jandro

    8'-4" wall by 8" thick #4000 mix (no vertical rebar required) #4 rebar 24" o.c. horz Provide engineering on center wall for dual elevations
  7. Mar 4, 2026

    Construction Fence

    Approved

    InspectorScot Jandro

    Construction safety fence installed around construction site with caution signs of danger do not enter.
  8. Mar 3, 2026

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorScot Jandro

    Soil pile is not contained from going onto the neighbors propery. Clean out street gutters for dirt and debris. Maintain bio logs along excavated areas
  9. Mar 3, 2026

    Construction Fence

    Not Approved

    InspectorScot Jandro

    No safety construction fence on site. Install safety fence around construction site ASAP.
  10. Mar 3, 2026

    Poured Foundation Reinforcement

    Not Approved, Not Ready

    InspectorScot Jandro

    No walls ready at this time.
  11. Mar 2, 2026

    Footing

    Approved

    InspectorScot Jandro

  12. Feb 25, 2026

    Footing

    Cancelled

    InspectorBrian Crask

    Contractor no show and no footing forms set up. Contractor didn't answer phone call.
  13. Feb 20, 2026

    Bldg Progress

    Progress Report

    InspectorScot Jandro

    Discussed with contractor not to demo any more structure (at 50%), provide foundation engineering on existing and send in revised plan.
  14. Feb 19, 2026

    Footing

    Cancelled

    InspectorBrian Crask

    Contractor canceled the inspection.