Building
5727 164th Ave NW, Ramsey
New, New Dwelling
- Sep 29, 2025
Topsoil
PassInspectorAaron Madsen
Per email from Aaron Madsen on 9/29/25; passed
- Sep 26, 2025
Landscaping Final
PassInspectorChris Anderson
Erosion blankets were installed next to driveway. Yard is more than 90% established.
- Sep 24, 2025
Landscaping Final
Partial PassInspectorChris Anderson
Seed has established throughout the yard and existing trees satisfy the planting requirement. There is an area just north of driveway that is a steep slope of bare, exposed soil. I let the home owner know that they need to get an erosion blanket down so that during rains, there is not a bunch of soil spilling out onto the public road. She was going to let me know when this was completed.
- Jun 25, 2025
Topsoil
Not approvedInspectorJake Hoel
Per email from Jake Hoel on 6/25/25, mostly sand; failed
- Jun 12, 2025
Final Building
PassInspectorDave Rankin
No topsoil or landscaping. Driveway complete Septic permit still open
- Jun 12, 2025
Lath
Not RequiredInspectorDave Rankin
- Jun 11, 2025
Well Affidavit
PassInspectorAlejandra Sanchez
Received Wall and boring construction record
- Jun 11, 2025
Water Test Results
PassInspectorAlejandra Sanchez
Received Drinking water laboratory test report
- Jun 10, 2025
Final Building
Orders IssuedInspectorDave Rankin
Roof above front window not installed. Window to the right of fireplace does not close/broken Smoke and CO's covers must be removed throughout Septic not inspected or closed in our system No lath inspection No well certification paperwork
- Jun 9, 2025
Backflow Preventer
PassInspectorDave Rankin
- Jun 9, 2025
Final Building
Orders IssuedInspectorDave Rankin
Roof above front window not installed. Basement window not trimmed out Window to the right of fireplace does not close/broken Smoke and CO's covers must be removed throughout Stairs in garage not correct Septic not inspected or closed in our system No lath inspection No well certification paperwork
- Jun 9, 2025
Fireplace Final
PassInspectorDave Rankin
- Jun 2, 2025
Plumbing Final
PassInspectorDean Becker
Includes manometer test. Basement bar lav not going to be installed for the building final inspection (on back order).
- May 7, 2025
Heating Final
PassInspectorDean Becker
Included air test.
- Mar 24, 2025
Insulation
PassInspectorEric Hoffman
Remaining completed. Contractor to ensure roof jack for radon gets installed prior to insulating attic.
- Mar 24, 2025
Rough Heating
PassInspectorDean Becker
All corrections are complete.
- Mar 20, 2025
Insulation
Partial PassInspectorEric Hoffman
Rim space spray foam only, OK
- Mar 19, 2025
Fireplace Rough In
PassInspectorDave Rankin
- Mar 19, 2025
Framing/Sheathing /Rim Joist
PassInspectorDean Becker
Truss screws are verified.
- Mar 17, 2025
Rough Heating
Partial PassInspectorDean Becker
Dryer exhaust duct still not insulated on the hallway side. All ductwork through top plate must have protective straps/plates installed. Can be verified at the insulation inspection.
- Mar 17, 2025
Heating Final
Not ReadyInspectorDean Becker
Scheduled by accident by the contractor.
- Mar 17, 2025
Plumbing Final
Not ReadyInspectorDean Becker
Scheduled by accident by the contractor. Shower head lowered to conditioned space.
- Mar 17, 2025
Framing/Sheathing /Rim Joist
Orders IssuedInspectorDean Becker
Gold truss screws replaced with silver screws - contractor to submit fastener specifications for review. Once specifications are reviewed and approved this can be passed without an additional site visit.
- Mar 14, 2025
Framing/Sheathing /Rim Joist
Orders IssuedInspectorDave Rankin
Gold truss screws are incorrect. Provide documentation or install correct screws.
- Feb 26, 2025
Rough Plumbing
PassInspectorEric Hoffman
pressure tested. verify rain head in upper bath shower is within conditioned space. plumbing installer informed contractor that they need to drop down the ceiling to accomplish this. Plumber installed blocking to lower installed head.
Show 7 earlier inspections
- Feb 26, 2025
Rough Heating
Partial PassInspectorEric Hoffman
Observed breaks in insulation and vapor barrier on ducting doing through 2x4 wall coming from unconditioned space. Spoke with contractor to ensure the opening in the top plates is completely sealed with spray foam in an effort to keep continuity for the vapor barrier/insulation requirements. The basement also needed the ducting joints sealed, remaining house appeared OK. Check for duct sealing and top plates in upper level at framing for compliance.
- Feb 5, 2025
Floor Poly
PassInspectorDean Becker
Address to be posted per R319.1. Contractor responsible to protect all plumbing penetrations per MN Plumbing code 312.2 as discussed with Cory while on site.
- Jan 31, 2025
Underground Rough In
PassInspectorThomas Knight
included air test
- Dec 2, 2024
Foundation
PassInspectorTracy Davis
Viewed pictures on site for waterproofing.
- Nov 25, 2024
Poured Wall
PassInspectorDean Becker
All items corrected.
- Nov 19, 2024
Poured Wall
Orders IssuedInspectorDean Becker
Corrections: (1) Contractor to establish connection between the garage and house ICF's. (2) The garage is wider than the reviewed plan (26' on plan) back wall is about 30'. Install footing/poured wall per reviewed plan or submit updated plans. (3) No horizontal rebar installed at time of inspection. Contractor to pour house at own risk.
- Nov 14, 2024
Footing
PassInspectorNick Gilliland
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.