Permit / Ramsey← Search
#RA060571Building
6960 148th La NW, Ramsey
IssuedMar 17, 2025
StatusUnknown
Value$28,717
Inspections6
Scope of work
Addition
Location context
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedMar 6, 2025
IssuedMar 17, 2025
Inspection record
Inspections6
Passed4
Failed0
- Aug 29, 2025
Fire Wall
PassInspectorDave Rankin
- Aug 29, 2025
Final
PassInspectorDave Rankin
- Aug 27, 2025
Fire Wall
Orders IssuedInspectorDave Rankin
Firewall required on exterior side
- Aug 26, 2025
Framing
PassInspectorDave Rankin
- Aug 22, 2025
Framing
Orders IssuedInspectorDave Rankin
- Beam splices must be over posts. Provide engineering or fix - Diagonal bracing required per engineer - contractor ran full length 2x8 tying all posts together. Engineer must provide updated plans - Finish nailing off brackets for roof joists - missing nail holes - Blocking required to be to underside of sheathing and on both sides of trusses below 6x6 posts on garage - Garage heater vent must be 12" above roof line - Firewall must be on both sides of wall.
- Aug 22, 2025
Footing
PassInspectorDave Rankin
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.