Permit / Ramsey← Search
#RA061851Building
17711 Vicuna St NW, Ramsey
IssuedJun 11, 2025
StatusUnknown
Value$166,416
Inspections11
Scope of work
Addition
Location context
Loading map…
192 nearby
This permitNearby
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedJun 11, 2025
IssuedJun 11, 2025
Inspection record
Inspections11
Passed9
Failed0
- Sep 16, 2025
Final
Partial PassInspectorDean Becker
Verified all smoke and carbon monoxide alarms via pictures and and a Remote Virtual Inspection. Once a siding permit is applied for and paid this permit can be closed.
- Sep 12, 2025
Final
Orders IssuedInspectorDean Becker
Corrections: (1) A separate siding permit is required for the existing dwelling. (2) Smoke and Carbon Monoxide alarms are required as follows: (addition is all compliant) Upper level of existing dwellling - hallway outside of bedrooms 1 - smoke & 1 - carbon monoxide alarm - 1 - smoke alarm inside of each bedroom (2 total - bedrooms - 3 total for upper level). Basement: 2 Smoke alarms (1 - hallway & 1 - bedroom). Carbon Monoxide alarm - 1 - within 10' outside of bedroom.
- Aug 1, 2025
Ice & Water Protection
PassInspectorDean Becker
Verified via pictures.
- Jul 31, 2025
Water-Resistive Barrier
PassInspectorDean Becker
- Jul 31, 2025
Framing/Sheathing /Rim Joist
PassInspectorDean Becker
All corrections from 7/25/2025 are complete.
- Jul 31, 2025
Insulation
PassInspectorDean Becker
- Jul 25, 2025
Framing/Sheathing /Rim Joist
Orders IssuedInspectorDean Becker
Corrections: (1) Overhead garage door header does not match the reviewed plans (2 ply. 11-7/8" header was installed and does not meet code minimum requirements) All garage walls were built using 2x4 construction not 2x6 as described on the reviewed plans. Contractor to submit engineering or an updated header to be reviewed. (2) T1SE Gable truss requires lateral bracing. (3) R317.3(1) - Fasteners into treated lumber.
- Jul 9, 2025
Floor Poly
PassInspectorDave Rankin
- Jun 26, 2025
Foundation
PassInspectorDave Rankin
- Jun 25, 2025
Poured Wall
PassInspectorDean Becker
Contractor responsible to ensure no standing water is present prior to pouring.
- Jun 20, 2025
Footing
PassInspectorNick Gilliland
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.