PULLFIRST[THE RECORD]
Permit / Ramsey← Search
#RA061851

Building

17711 Vicuna St NW, Ramsey

IssuedJun 11, 2025
StatusUnknown
Value$166,416
Inspections11
Scope of work

Addition

Location context
Parcel063225140005
Coordinates45.29218, -93.49207
Loading map…
192 nearby
This permitNearby
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedJun 11, 2025
IssuedJun 11, 2025
Inspection record
Inspections11
Passed9
Failed0
  1. Sep 16, 2025

    Final

    Partial Pass

    InspectorDean Becker

    Verified all smoke and carbon monoxide alarms via pictures and and a Remote Virtual Inspection. Once a siding permit is applied for and paid this permit can be closed.
  2. Sep 12, 2025

    Final

    Orders Issued

    InspectorDean Becker

    Corrections: (1) A separate siding permit is required for the existing dwelling. (2) Smoke and Carbon Monoxide alarms are required as follows: (addition is all compliant) Upper level of existing dwellling - hallway outside of bedrooms 1 - smoke & 1 - carbon monoxide alarm - 1 - smoke alarm inside of each bedroom (2 total - bedrooms - 3 total for upper level). Basement: 2 Smoke alarms (1 - hallway & 1 - bedroom). Carbon Monoxide alarm - 1 - within 10' outside of bedroom.
  3. Aug 1, 2025

    Ice & Water Protection

    Pass

    InspectorDean Becker

    Verified via pictures.
  4. Jul 31, 2025

    Water-Resistive Barrier

    Pass

    InspectorDean Becker

  5. Jul 31, 2025

    Framing/Sheathing /Rim Joist

    Pass

    InspectorDean Becker

    All corrections from 7/25/2025 are complete.
  6. Jul 31, 2025

    Insulation

    Pass

    InspectorDean Becker

  7. Jul 25, 2025

    Framing/Sheathing /Rim Joist

    Orders Issued

    InspectorDean Becker

    Corrections: (1) Overhead garage door header does not match the reviewed plans (2 ply. 11-7/8" header was installed and does not meet code minimum requirements) All garage walls were built using 2x4 construction not 2x6 as described on the reviewed plans. Contractor to submit engineering or an updated header to be reviewed. (2) T1SE Gable truss requires lateral bracing. (3) R317.3(1) - Fasteners into treated lumber.
  8. Jul 9, 2025

    Floor Poly

    Pass

    InspectorDave Rankin

  9. Jun 26, 2025

    Foundation

    Pass

    InspectorDave Rankin

  10. Jun 25, 2025

    Poured Wall

    Pass

    InspectorDean Becker

    Contractor responsible to ensure no standing water is present prior to pouring.
  11. Jun 20, 2025

    Footing

    Pass

    InspectorNick Gilliland

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.