Building

5740 157th La NW, Ramsey

IssuedJul 3, 2025
StatusUnknown
Value$327,995
Inspections26
Scope of work

New, New Dwelling

Location context
Parcel143225440078
Coordinates45.25661, -93.41180
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedJul 3, 2025
IssuedJul 3, 2025
Inspection record
Inspections26
Passed25
Failed0
  1. Nov 19, 2025

    As-Built Certificate of Grading

    Pass

    InspectorLogan Czech

    Per Logan Czech on 11/19/25; passed
  2. Oct 13, 2025

    As-Built Certificate of Grading

    Not approved

    InspectorJoe Feriancek

    Per email from Joe Feriancek on 10/13/25; This grading as-built does not pass; showing below 1.0% slope in several spots around the house. If they want to close on the house they’ll need to supply an escrow for grading and re-submitting the grading as-built.
  3. Oct 8, 2025

    Landscaping Final

    Pass

    InspectorChris Anderson

    Trees, sod, driveway in.
  4. Oct 7, 2025

    Plumbing Final

    Pass

    InspectorDean Becker

    All corrections from 9/30/2025 are complete.
  5. Oct 7, 2025

    Final Building

    Pass

    InspectorDean Becker

    Driveway and landscaping are complete.
  6. Oct 7, 2025

    Heating Final

    Pass

    InspectorDean Becker

    All diffusers are installed.
  7. Oct 7, 2025

    Fireplace Rough In

    Pass

    InspectorDean Becker

    Gas line is protected.
  8. Oct 7, 2025

    Fireplace Final

    Pass

    InspectorDean Becker

  9. Oct 1, 2025

    Topsoil

    Pass

    InspectorJake Hoel

    Per email from Jake Hoel on 10/1/25; passed
  10. Oct 1, 2025

    Water Meter & Remote Install

    Pass

    InspectorMatt Graf

  11. Sep 30, 2025

    Plumbing Final

    Partial Pass

    InspectorDean Becker

    Included a manometer test. Items to verify at the building final: (1) Water meter not installed at time of inspection - verify Hot/cold running water. (2) Fixtures being sealed at time of inspection - verify.
  12. Sep 30, 2025

    Heating Final

    Partial Pass

    InspectorDean Becker

    Included a manometer test. Items to verify at the building final: (1) Diffusers not installed at time of inspection - verify.
  13. Sep 30, 2025

    Backflow Preventer

    Pass

    InspectorDean Becker

  14. Aug 19, 2025

    Framing/Sheathing /Rim Joist

    Pass

    InspectorDean Becker

    All corrections are complete and verified via pictures.
  15. Aug 15, 2025

    Insulation

    Pass

    InspectorJosh Guin

  16. Aug 12, 2025

    Framing/Sheathing /Rim Joist

    Orders Issued

    InspectorDean Becker

    Corrections: (1) Add uplift screws or hurricane clips to trusses spanning over porch area - both sides. (2) Gable end blocking shall be 24" O.C. for overhangs 9" and over per Table R503.2.1.1(1). (3) Overhead door headers can not be continuous for multiple portal frame openings. Good Pictures are okay for re-inspection - dean@rumrivercc.com.
  17. Aug 12, 2025

    Lath

    Pass

    InspectorJosh Guin

  18. Aug 8, 2025

    Fireplace Rough In

    Partial Pass

    InspectorDean Becker

    The gas line shall be protected where it enters the fireplace. Fuel Gas code, 403.8 - Protective coating. To be verified at the final inspection.
  19. Aug 6, 2025

    Rough Heating

    Pass

    InspectorDean Becker

    Air pressure test included. Includes garage heater gas line & venting rough-in.
  20. Aug 6, 2025

    Rough Plumbing

    Pass

    InspectorDean Becker

    Included air test. Radon pipe is insulated in the attic.
  21. Jul 18, 2025

    Floor Poly

    Pass

    InspectorJosh Guin

  22. Jul 17, 2025

    Underground Rough In

    Pass

    InspectorDave Rankin

  23. Jul 17, 2025

    Sewer/Water

    Pass

    InspectorJordan Evans

  24. Jul 16, 2025

    Foundation

    Pass

    InspectorDean Becker

  25. Jul 14, 2025

    Poured Wall

    Pass

    InspectorDean Becker

Show 1 earlier inspection
  1. Jul 10, 2025

    Footing

    Pass

    InspectorDean Becker