Building
5740 157th La NW, Ramsey
New, New Dwelling
- Nov 19, 2025
As-Built Certificate of Grading
PassInspectorLogan Czech
Per Logan Czech on 11/19/25; passed
- Oct 13, 2025
As-Built Certificate of Grading
Not approvedInspectorJoe Feriancek
Per email from Joe Feriancek on 10/13/25; This grading as-built does not pass; showing below 1.0% slope in several spots around the house. If they want to close on the house they’ll need to supply an escrow for grading and re-submitting the grading as-built.
- Oct 8, 2025
Landscaping Final
PassInspectorChris Anderson
Trees, sod, driveway in.
- Oct 7, 2025
Plumbing Final
PassInspectorDean Becker
All corrections from 9/30/2025 are complete.
- Oct 7, 2025
Final Building
PassInspectorDean Becker
Driveway and landscaping are complete.
- Oct 7, 2025
Heating Final
PassInspectorDean Becker
All diffusers are installed.
- Oct 7, 2025
Fireplace Rough In
PassInspectorDean Becker
Gas line is protected.
- Oct 7, 2025
Fireplace Final
PassInspectorDean Becker
- Oct 1, 2025
Topsoil
PassInspectorJake Hoel
Per email from Jake Hoel on 10/1/25; passed
- Oct 1, 2025
Water Meter & Remote Install
PassInspectorMatt Graf
- Sep 30, 2025
Plumbing Final
Partial PassInspectorDean Becker
Included a manometer test. Items to verify at the building final: (1) Water meter not installed at time of inspection - verify Hot/cold running water. (2) Fixtures being sealed at time of inspection - verify.
- Sep 30, 2025
Heating Final
Partial PassInspectorDean Becker
Included a manometer test. Items to verify at the building final: (1) Diffusers not installed at time of inspection - verify.
- Sep 30, 2025
Backflow Preventer
PassInspectorDean Becker
- Aug 19, 2025
Framing/Sheathing /Rim Joist
PassInspectorDean Becker
All corrections are complete and verified via pictures.
- Aug 15, 2025
Insulation
PassInspectorJosh Guin
- Aug 12, 2025
Framing/Sheathing /Rim Joist
Orders IssuedInspectorDean Becker
Corrections: (1) Add uplift screws or hurricane clips to trusses spanning over porch area - both sides. (2) Gable end blocking shall be 24" O.C. for overhangs 9" and over per Table R503.2.1.1(1). (3) Overhead door headers can not be continuous for multiple portal frame openings. Good Pictures are okay for re-inspection - dean@rumrivercc.com.
- Aug 12, 2025
Lath
PassInspectorJosh Guin
- Aug 8, 2025
Fireplace Rough In
Partial PassInspectorDean Becker
The gas line shall be protected where it enters the fireplace. Fuel Gas code, 403.8 - Protective coating. To be verified at the final inspection.
- Aug 6, 2025
Rough Heating
PassInspectorDean Becker
Air pressure test included. Includes garage heater gas line & venting rough-in.
- Aug 6, 2025
Rough Plumbing
PassInspectorDean Becker
Included air test. Radon pipe is insulated in the attic.
- Jul 18, 2025
Floor Poly
PassInspectorJosh Guin
- Jul 17, 2025
Underground Rough In
PassInspectorDave Rankin
- Jul 17, 2025
Sewer/Water
PassInspectorJordan Evans
- Jul 16, 2025
Foundation
PassInspectorDean Becker
- Jul 14, 2025
Poured Wall
PassInspectorDean Becker
Show 1 earlier inspection
- Jul 10, 2025
Footing
PassInspectorDean Becker
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.