Permit / Ramsey← Search
#RA062167Building
6798 153rd La NW, Ramsey
IssuedAug 7, 2025
StatusUnknown
Value$522,478
Inspections19
Scope of work
New, New Dwelling
Location context
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedJul 18, 2025
IssuedAug 7, 2025
Inspection record
Inspections19
Passed17
Failed0
- Jan 29, 2026
Final Building
PassInspectorDean Becker
All corrections from 1/27/2026 are complete and verified via pictures. The driveway and landscaping were NOT complete at time of inspection.
- Jan 27, 2026
Final Building
Orders IssuedInspectorDean Becker
Corrections: (1) The egress window well exceeds the maximum 44" max height - the ladder must extend the full height of the well - R310.3.2.1. (2) Fireblocking is required in the mechanical room per R302.11 (ceiling & floor system). (3) Upper front entry posts must be protected from the elements. (4) Entry stoop either requires a guard or shall be a maximum of 30" to the ground - R312 & R312.1.1. The driveway and landscaping were NOT complete at the time of inspection. An escrow will be required.
- Jan 27, 2026
Fireplace Final
PassInspectorDean Becker
Both fireplaces.
- Jan 20, 2026
Heating Final
PassInspectorDean Becker
Included a manometer test.
- Jan 20, 2026
Plumbing Final
PassInspectorDean Becker
Verified hot/cold running water.
- Jan 8, 2026
Plumbing Final
Partial PassInspectorDean Becker
Included a manometer test. No running water at time of inspection. Verify hot/cold running water at the building final.
- Jan 8, 2026
Backflow Preventer
PassInspectorDean Becker
- Dec 16, 2025
Lath
PassInspectorDean Becker
- Nov 10, 2025
Insulation
PassInspectorDave Rankin
Per Josh Guin
- Nov 10, 2025
Fireplace Rough In
PassInspectorJosh Guin
Upper and lower fireplaces
- Nov 10, 2025
Framing/Sheathing /Rim Joist
PassInspectorJosh Guin
Girder nailed properly. Porch columns have been replaced.
- Nov 4, 2025
Framing/Sheathing /Rim Joist
Orders IssuedInspectorDave Rankin
3 ply girder truss nailing pattern required on both sides Covered porch columns need to be replaced. Cut too short and blocking will not work.
- Nov 4, 2025
Rough Heating
PassInspectorDave Rankin
- Oct 16, 2025
Rough Plumbing
PassInspectorDave Rankin
- Oct 9, 2025
Floor Poly
PassInspectorDean Becker
Radon pulled from the drain tile. Contractor responsible to wrap the clean out pipe as discussed while onsite.
- Oct 8, 2025
Underground Rough In
PassInspectorJosh Guin
Pressure test included.
- Sep 12, 2025
Foundation
PassInspectorJosh Guin
Contractor is responsible to ensure foundation and jumps at garage meet frost depth requirements.
- Sep 4, 2025
Poured Wall
PassInspectorDean Becker
- Sep 2, 2025
Footing
PassInspectorDean Becker