IssuedAug 7, 2025
StatusUnknown
Value$522,478
Inspections19
Scope of work

New, New Dwelling

Location context
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedJul 18, 2025
IssuedAug 7, 2025
Inspection record
Inspections19
Passed17
Failed0
  1. Jan 29, 2026

    Final Building

    Pass

    InspectorDean Becker

    All corrections from 1/27/2026 are complete and verified via pictures. The driveway and landscaping were NOT complete at time of inspection.
  2. Jan 27, 2026

    Final Building

    Orders Issued

    InspectorDean Becker

    Corrections: (1) The egress window well exceeds the maximum 44" max height - the ladder must extend the full height of the well - R310.3.2.1. (2) Fireblocking is required in the mechanical room per R302.11 (ceiling & floor system). (3) Upper front entry posts must be protected from the elements. (4) Entry stoop either requires a guard or shall be a maximum of 30" to the ground - R312 & R312.1.1. The driveway and landscaping were NOT complete at the time of inspection. An escrow will be required.
  3. Jan 27, 2026

    Fireplace Final

    Pass

    InspectorDean Becker

    Both fireplaces.
  4. Jan 20, 2026

    Heating Final

    Pass

    InspectorDean Becker

    Included a manometer test.
  5. Jan 20, 2026

    Plumbing Final

    Pass

    InspectorDean Becker

    Verified hot/cold running water.
  6. Jan 8, 2026

    Plumbing Final

    Partial Pass

    InspectorDean Becker

    Included a manometer test. No running water at time of inspection. Verify hot/cold running water at the building final.
  7. Jan 8, 2026

    Backflow Preventer

    Pass

    InspectorDean Becker

  8. Dec 16, 2025

    Lath

    Pass

    InspectorDean Becker

  9. Nov 10, 2025

    Insulation

    Pass

    InspectorDave Rankin

    Per Josh Guin
  10. Nov 10, 2025

    Fireplace Rough In

    Pass

    InspectorJosh Guin

    Upper and lower fireplaces
  11. Nov 10, 2025

    Framing/Sheathing /Rim Joist

    Pass

    InspectorJosh Guin

    Girder nailed properly. Porch columns have been replaced.
  12. Nov 4, 2025

    Framing/Sheathing /Rim Joist

    Orders Issued

    InspectorDave Rankin

    3 ply girder truss nailing pattern required on both sides Covered porch columns need to be replaced. Cut too short and blocking will not work.
  13. Nov 4, 2025

    Rough Heating

    Pass

    InspectorDave Rankin

  14. Oct 16, 2025

    Rough Plumbing

    Pass

    InspectorDave Rankin

  15. Oct 9, 2025

    Floor Poly

    Pass

    InspectorDean Becker

    Radon pulled from the drain tile. Contractor responsible to wrap the clean out pipe as discussed while onsite.
  16. Oct 8, 2025

    Underground Rough In

    Pass

    InspectorJosh Guin

    Pressure test included.
  17. Sep 12, 2025

    Foundation

    Pass

    InspectorJosh Guin

    Contractor is responsible to ensure foundation and jumps at garage meet frost depth requirements.
  18. Sep 4, 2025

    Poured Wall

    Pass

    InspectorDean Becker

  19. Sep 2, 2025

    Footing

    Pass

    InspectorDean Becker