PULLFIRST[THE RECORD]
Permit / Ramsey← Search
#RA061526

Building

14047 Azurite St NW, Ramsey

IssuedSep 15, 2025
StatusUnknown
Value$50,000
Inspections13
Scope of work

Alteration, Building

Location context
Parcel343225110008
Coordinates45.22472, -93.43285
Loading map…
198 nearby
This permitNearby
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedSep 10, 2025
IssuedSep 15, 2025
Inspection record
Inspections13
Passed9
Failed0
  1. Jan 6, 2026

    Final Building

    Partial Pass

    InspectorDave Rankin

    Unit 5 - Not complete. Mechanical permits still required for unit heaters and added gas lines.
  2. Dec 31, 2025

    Final Building

    Orders Issued

    InspectorDave Rankin

    Unit 1 - ok Unit 2 - Move camper out of accessible parking Unit 3 - OK Unit 4 - Insulation required above heater @ entrance. Seal all penetrations Unit 5 - Not ready, mechanical permit required, electrical not ready, Sheet rock still needs to be installed. unit 6 - Mechanical permit required for heater
  3. Dec 31, 2025

    Fire Wall

    Pass

    InspectorDave Rankin

  4. Dec 31, 2025

    Framing

    Pass

    InspectorDave Rankin

  5. Dec 31, 2025

    Siding Final

    Pass

    InspectorDave Rankin

  6. Nov 18, 2025

    Fire Wall

    Orders Issued

    InspectorDave Rankin

    North building has 2 hour wall. Updated plans changes to 3 hour wall.
  7. Nov 4, 2025

    Siding Final

    Orders Issued

    InspectorDave Rankin

    Flashing required at corners of OHD's. Seal all penetrations
  8. Nov 4, 2025

    Fire Wall

    Partial Pass

    InspectorDave Rankin

    NE unit below ceiling firewall ok. Must inspect above ceiling
  9. Oct 21, 2025

    Fire Wall

    Partial Pass

    InspectorDave Rankin

    Unit 32 only
  10. Oct 16, 2025

    Fire Wall

    Orders Issued

    InspectorDave Rankin

    Orange spray foam not allowed. Electrical boxes not covered. Contractor states the engineer is drawing up plans for 2 hour fire wall by electrical boxes. 4' section from concrete to roof line.
  11. Oct 6, 2025

    Fire Wall

    Partial Pass

    InspectorDave Rankin

    Unit 32 only
  12. Sep 25, 2025

    Insulation

    Partial Pass

    InspectorDave Rankin

    1st unit on south end of pole barn
  13. Sep 25, 2025

    Water-Resistive Barrier

    Pass

    InspectorDave Rankin

    Pole barn on only

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.