Building
640 Wisconsin Ave N, Golden Valley
New, SENTINEL parking ramp and 303 unit apartment bldg
- Jan 27, 2026
Other - Letters of Substantial Completion
CompletedInspectorDan Anderson
- Jan 27, 2026
Final
CompletedInspectorDan Anderson
- Jan 21, 2026
Special Inspections
CompletedInspectorDan Anderson
received final report 1/21/26
- Jan 21, 2026
Special Inspections - Structural Engineer
CompletedInspectorDan Anderson
received final report 1/21/26
- Jan 16, 2026
Final
Partial ApprovalInspectorMike Lockman
Corridor inspections for 1st thru 4th floors. Re-check needed for the Low Voltage room on 3rd floor of Bldg B. ( doors wouldnt open / still need inspection. Glazing in the door for the dog wash was not etched for tempered glass - Adam to work on this. On-site with Garrett H.
- Jan 15, 2026
Final
Need CorrectionInspectorMike Lockman
Inspection for parking structure. Several extinguisher cabinet not installed on center stitch wall. Fall protection not completed for snow chute on top level. Inspection completed w/ Bret E
- Jan 14, 2026
Sanitarian Final
CompletedInspectorDan Anderson
See letter dated from MDH 12/4/25 in Laserfiche.
- Jan 14, 2026
Fire Stopping
CompletedInspectorBret Eggers
Doors into garage level one and at garage door openings
- Jan 12, 2026
Other - Verify Elevator Final
CompletedInspectorDan Anderson
received Certificate of Approval letters 1/12/26 for all three cars
- Jan 12, 2026
Verify Fire Final
CompletedInspectorDan Anderson
Fire permits closed out 12/30/25
- Jan 12, 2026
Verify Electrical Final
CompletedInspectorDan Anderson
Final electrical close out 11/24/25
- Jan 10, 2026
Final
Partial ApprovalInspectorGarrett Heins
With Mike Lockman - Inspection for the gas grills in all common areas of courtyard and sky lounge. Verified the E-stop in functioning as it should.
- Dec 30, 2025
Final
Partial ApprovalInspectorBret Eggers
All unit finals have been completed with the exception off orsat test, unit door inspection, and fireplace finals
- Dec 29, 2025
As-Built Survey
CompletedInspectorDan Anderson
- Dec 26, 2025
Final
Cancelled AppointmentInspectorMike Lockman
No inspections today per Bryan and Adam @ Big D
- Dec 19, 2025
Final
Cancelled AppointmentInspectorMike Lockman
No inspections today per Adam @ Big D
- Dec 18, 2025
Final
Partial ApprovalInspectorBret Eggers
Elevator lobby smoke door closing with smoke alarm initiation
- Dec 17, 2025
Fire Stopping
CompletedInspectorBret Eggers
Final inspections approved
- Dec 17, 2025
Final
Partial ApprovalInspectorGarrett Heins
With Bret Eggers - Power drop, including exterior lighting, interior lighting and rated corridor door mag lock release.
- Dec 16, 2025
I & I Inspection
CompletedInspectorDan Anderson
compliance certificate dated 12/10/25
- Dec 16, 2025
Final
Partial ApprovalInspectorGarrett Heins
With Dan Anderson, Mike Lockman, Bret Eggers
- Dec 11, 2025
Final
Partial ApprovalInspectorBret Eggers
2nd flooir units except 226 which is being used as storage
- Dec 10, 2025
Final
Cancelled AppointmentInspectorMike Lockman
No inspections today per Bryan @ Big D
- Dec 8, 2025
Final
Partial ApprovalInspectorGarrett Heins
With Brett Eggers - All units except 326 which is being used as storage. Also need to double check glass panel railing on decks to make sure they are attached to base.
- Dec 5, 2025
Final
Cancelled AppointmentInspectorMike Lockman
No inspection needed today per Adam @ Big D
Show 248 earlier inspections
- Dec 3, 2025
Final
Partial ApprovalInspectorMike Lockman
Unit finals for all units on 4th floor in both A & B buildings
- Dec 2, 2025
Final
Partial ApprovalInspectorBret Eggers
All units on 5th floor except 526 which is being used as temp storage
- Nov 26, 2025
Floor Slab-Reinforcement
CompletedInspectorMike Lockman
- Nov 26, 2025
Framing
CompletedInspectorMike Lockman
- Nov 26, 2025
Footing
CompletedInspectorMike Lockman
- Nov 26, 2025
Insulation
CompletedInspectorMike Lockman
- Nov 26, 2025
Other - Reinforcing Before Applying Shopcrete
CompletedInspectorMike Lockman
- Nov 26, 2025
Other - Stoop Reinforcing
CompletedInspectorMike Lockman
- Nov 26, 2025
Wall Reinforcing - Lintel Locations
CompletedInspectorMike Lockman
- Nov 26, 2025
Rated Gypsum Assemblies
CompletedInspectorMike Lockman
- Nov 26, 2025
Radon Control
CompletedInspectorMike Lockman
Inspected during plumbing RI's
- Nov 26, 2025
Poured Wall
CompletedInspectorMike Lockman
- Nov 26, 2025
Final
Partial ApprovalInspectorGarrett Heins
With Mike Lockman - Unit finals completed for Bdlg A / W wing / floor 6. Corrections completed for floor 6 units in E wing.
- Nov 24, 2025
Final
Partial ApprovalInspectorMike Lockman
Unit finals only for 6th floor Bldg A / East wing completed up to elevators with the exception of units 626 (not ready), 630, 635 & 642 needing fire caulking in magic pack closet on rated ceilings. Many door seals need adjustment - Look at all door seals when doing corridor inspections
- Nov 14, 2025
Final
Cancelled AppointmentInspectorMike Lockman
No inspections today per Bryan @ Big D
- Nov 7, 2025
Final
Cancelled AppointmentInspectorMike Lockman
No inspections today per Bryan @ Big D
- Oct 24, 2025
Other
Cancelled AppointmentInspectorMike Lockman
No inspections today per Brian @ Big D
- Oct 17, 2025
Other
Cancelled AppointmentInspectorMike Lockman
No inspections needed today per text from Bryan @ Big-D
- Oct 10, 2025
Other
Cancelled AppointmentInspectorMike Lockman
Inspection cancelled by Bryan @ Big D
- Oct 3, 2025
Framing-Above Ceiling
CompletedInspectorMike Lockman
Inspected golf simulator room, Theater room, Bike storage, Dog wash and trash room. Should be last of the above-ceiling required
- Sep 26, 2025
Framing
Cancelled AppointmentInspectorMike Lockman
Inspection not needed today per Adam @ Bid D
- Sep 24, 2025
Flat Roof/Tear-Off
CompletedInspectorBret Eggers
Insulation as per approved plans
- Sep 24, 2025
Framing-Above Ceiling
Partial ApprovalInspectorBret Eggers
All of 1st floor except dog was area and trash room
- Sep 19, 2025
Framing
Cancelled AppointmentInspectorMike Lockman
Cancelled by Bryan @ Big D
- Sep 18, 2025
Footing
CompletedInspectorBret Eggers
Stair reinforcing for pool and hot tub
- Sep 12, 2025
Other
Partial ApprovalInspectorMike Lockman
UG pool piping for the hot tub/spa
- Sep 9, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorMike Lockman
Rated ceiling inspection for the corridor on 1st floor / Bldg B
- Aug 29, 2025
Other - Reinforcing Before Applying Shopcrete
Partial ApprovalInspectorMike Lockman
Re-inforcement for the pool and spa. Stairs to be completed after installation of the shotcrete application
- Aug 25, 2025
Insulation
Cancelled AppointmentInspectorMike Lockman
No inspection today per Bryan @ Big D
- Aug 22, 2025
Insulation
Partial ApprovalInspectorBrian Stemwedel
1st floor liner wall at corridor. insulation and VB
- Aug 15, 2025
Wall Reinforcing
CompletedInspectorMike Lockman
Reinforcement for pool equipment bldg. #4 bar @ 12" OC horizontal and vertical
- Aug 15, 2025
Other - Reinforcing Before Applying Shopcrete
Partial ApprovalInspectorMike Lockman
Reinforcement for hot tub/spa. #4 bar - 12" OC both ways for walls and floor
- Aug 14, 2025
Rated Gypsum Assemblies
Cancelled AppointmentInspectorMike Lockman
No inspections today per Bryan at Big-D
- Aug 13, 2025
Rated Gypsum Assemblies
CompletedInspectorBret Eggers
Building B floor 1
- Aug 8, 2025
Footing
Partial ApprovalInspectorMike Lockman
8-12 Inches of river rock sub-base installed for the exterior pool and hot tub. Rigid foam insulation installed atop the aggregate for the hot tub.
- Aug 7, 2025
Rated Gypsum Assemblies
Cancelled AppointmentInspectorMike Lockman
No inspections today per Bryan @ Big-D
- Aug 6, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBret Eggers
B 2 all units
- Aug 1, 2025
Footing - Landing
CompletedInspectorBrian Stemwedel
exterior landings ISCWAP
- Jul 31, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBret Eggers
Building A all of floor 2 is completed
- Jul 30, 2025
Insulation
Partial ApprovalInspectorBret Eggers
Blown in ceiling complete building B floor 1 except for 3 units with water dammage
- Jul 29, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorMike Lockman
Drywall inspection for units on 2nd floor / W wing with the exception of unit 250 not being completed at time of inspection. Also looked at the storage closet area on 2nd floor / W wing
- Jul 28, 2025
Insulation
Need CorrectionInspectorMike Lockman
Failed inspection in 1B due to storm water saturating the lid insulation in the area of the Magic-Pac units. Felt on ceiling was holding water until a hole was made to let the water drain. Contractor to remove all wet insulation and install new insulation. Upper units will need to be spot checked for wet insulation above the drywall.
- Jul 22, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBrian Stemwedel
gyp @ shear walls in 2A
- Jul 21, 2025
Insulation
Partial ApprovalInspectorBret Eggers
All exterior walls and ceilings in building B floor 2 have been completed
- Jul 16, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBret Eggers
3rd floor building A is complete
- Jul 15, 2025
Final
Partial ApprovalInspectorGarrett Heins
Corridor inspection Levels 6 and 5 with Bret Eggers. Units 649, 533, & 527 require adjustment. Southwest fire door level 5 also requires adjustment.
- Jul 14, 2025
Insulation
Partial ApprovalInspectorBret Eggers
2 B ceiling and wall insulation complete
- Jul 11, 2025
Drain Tile
CompletedInspectorBrian Stemwedel
- Jul 11, 2025
Foundation Insulation
CompletedInspectorBrian Stemwedel
- Jul 11, 2025
Foundation Waterproofing
CompletedInspectorBrian Stemwedel
- Jul 11, 2025
Other - Concrete Piers
CompletedInspectorBrian Stemwedel
- Jul 11, 2025
Other - Grout Lintels
CompletedInspectorBrian Stemwedel
- Jul 11, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBrian Stemwedel
Looked at shaft liner at elevator doorways. ok to proceed on levels 1-6
- Jul 10, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBrian Stemwedel
3A west 301-304 and 344 and 345
- Jul 9, 2025
Insulation
Partial ApprovalInspectorBret Eggers
Exterior walls all units B3
- Jul 7, 2025
Insulation
Cancelled AppointmentInspectorMike Lockman
No inspection today per Bryan @ Big D
- Jul 3, 2025
Submit Pictures of House Wrap
CompletedInspectorBret Eggers
- Jul 3, 2025
Final
Partial ApprovalInspectorBret Eggers
3rd floor units only both buildings
- Jul 3, 2025
Insulation
Partial ApprovalInspectorBrian Stemwedel
exterior walls 2 West
- Jul 1, 2025
Insulation
Partial ApprovalInspectorBret Eggers
Building A east wing. South 4 units
- Jun 30, 2025
Footing
Partial ApprovalInspectorBret Eggers
Pool house
- Jun 30, 2025
Insulation
Partial ApprovalInspectorBret Eggers
Bldg A east to elevators
- Jun 27, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBrian Stemwedel
3 west Shear wall gyp
- Jun 26, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
1B with B.E.
- Jun 24, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Wall & sound insulation on 2nd floor / Bldg A / E wing with Brian S
- Jun 23, 2025
Foundation Insulation
Partial ApprovalInspectorMike Lockman
Lid insulation on 3rd floor / Bldg A / W wing
- Jun 23, 2025
Insulation
Partial ApprovalInspectorBret Eggers
Building 1 east side, both exterior and interior walls
- Jun 20, 2025
Framing
Partial ApprovalInspectorMike Lockman
Per Bryan @ Big D - he will have stuff to look at on monday when the insulator is done in that area.
- Jun 18, 2025
Insulation
Partial ApprovalInspectorBrian Stemwedel
lids on 3B with B.E.
- Jun 18, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBrian Stemwedel
shear walls in 4B
- Jun 13, 2025
Framing
Cancelled AppointmentInspectorMike Lockman
Inspection cancelled by Bryan @ B-D
- Jun 12, 2025
Framing
Partial ApprovalInspectorBret Eggers
Units 127, 128, 130,131, 132 ,133,134, 135,136, 137, 138,139, 140, 141
- Jun 11, 2025
Insulation
Partial ApprovalInspectorBrian Stemwedel
3B bldg. ex. wall insulation and VB with B.E.
- Jun 10, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Lid insulation for floor 3A is complete
- Jun 10, 2025
Framing
Partial ApprovalInspectorMike Lockman
2nd floor / E wing completed
- Jun 10, 2025
Fire Stopping
Partial ApprovalInspectorMike Lockman
2nd floor / E wing completed
- Jun 9, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Lid insulation for units on 3rd floor / E wing / Bldg A except for units 329 thru 333 that have not been completed yet.
- Jun 5, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorMike Lockman
Drywall in units. 4th floor / Bldg A
- Jun 4, 2025
Insulation
Partial ApprovalInspectorBrian Stemwedel
With Bret Eggers 3rd floor Building A, East finger- Exterior wall insulation and Vapor Barrier
- Jun 3, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Ceiling insulation completed for all units on 4th floor / Bldg B
- Jun 2, 2025
Fire Stopping
Partial ApprovalInspectorMike Lockman
Bldg A / E wing / 2nd floor completed w/ Bret E
- Jun 2, 2025
Framing
Partial ApprovalInspectorMike Lockman
Bldg A / E wing / 2nd floor completed w/ Bret E
- May 29, 2025
Insulation
Partial ApprovalInspectorBret Eggers
Exterior walls B 5 whole floor
- May 28, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBrian Stemwedel
Gyp in shear walls on 4B
- May 27, 2025
Insulation
Partial ApprovalInspectorBrian Stemwedel
lid insulation on floor 4
- May 23, 2025
Framing
Partial ApprovalInspectorMike Lockman
Framing & firestopping 3rd floor / Bldg B
- May 21, 2025
Insulation
Partial ApprovalInspectorBrian Stemwedel
insulation on 4th floor. signed inspection records on site (per room)
- May 20, 2025
Framing
Partial ApprovalInspectorMike Lockman
No inspections today. Small consult with Big D. On site with Brian S.
- May 15, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
3rd floor area A
- May 12, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Ceiling insulation completed in all units and hallways in E wing of Bldg A up to the elevators.
- May 6, 2025
Rated Gypsum Assemblies
Partial ApprovalInspectorBret Eggers
All 5th floor except 547 - 558 and 501 - 504
- May 6, 2025
Fire Stopping
Partial ApprovalInspectorBret Eggers
All units and hallways 4B
- May 6, 2025
Framing
Partial ApprovalInspectorBret Eggers
All units and hallways 4B
- May 2, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Exterior wall insulation completed on 4th floor / Bldg A / E wing up to elevators.
- Apr 30, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
Completed framing firestop on 5th floor building B. noted that on the 05 stack (unit 505) and on the 18 stack (unit 518) floor openings around shaft(s) were open from foundation to roof. need to be fireblocked with 1 hour rated material. (required floor rating)
- Apr 29, 2025
Framing
Partial ApprovalInspectorMike Lockman
Framing for W wing / 4th floor / Bldg A. Units and corridor completed along with the Sky Lounge on 6th floor
- Apr 29, 2025
Fire Stopping
Partial ApprovalInspectorMike Lockman
W wing / 4th. floor / Bldg A. Units and corridor
- Apr 28, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Remainder of blown cellulose in unit ceilings on 5th flloor / Bldg A
- Apr 23, 2025
Framing
Completed in Future.InspectorBrian Stemwedel
verify blue elec. boxes installed in corridor walls are rated
- Apr 21, 2025
Fire Stopping
Partial ApprovalInspectorMike Lockman
Bldg A / 4th Floor. Fire stopping for E wing up to elevators. Completed w/ Bret E.
- Apr 21, 2025
Framing
Partial ApprovalInspectorMike Lockman
Bldg A / 4 th floor. Framing for all units and corridors in the E wing up to elevators. Completed w/ Bret E
- Apr 21, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Bldg A / 5th floor. Ceiling insulation completed in E wing of all units up to elevators
- Apr 18, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Bldg A / 5th floor - Blown insulation in ceiling space of units from S end on E wing up to trash chute. Batt insulation in ceiling space of corridors and common areas up to trash chute. Exterior wall insulation and VB in the W wing units.
- Apr 15, 2025
Fire Stopping
Partial ApprovalInspectorBret Eggers
With ML see his notes
- Apr 15, 2025
Framing
Partial ApprovalInspectorBret Eggers
All of 5th floor building 1 is complete. Units and corridors
- Apr 14, 2025
Insulation
Partial ApprovalInspectorMike Lockman
Insulation for units on 5th floor / Bldg A / E wing.
- Apr 14, 2025
Fire Stopping
Partial ApprovalInspectorMike Lockman
Framing & fire stopping for 5th and 6th floor stair wells on E and W wings
- Apr 7, 2025
Framing
Partial ApprovalInspectorBret Eggers
All framing for units on 5th floor completed 557
- Apr 7, 2025
Fire Stopping
Partial ApprovalInspectorBret Eggers
All units on 5th floor except 557 are completed
- Apr 4, 2025
Fire Stopping
Partial ApprovalInspectorMike Lockman
5th floor E wing completed up to elevator lobby
- Apr 4, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
5th floor on east wing to elevator lobby
- Apr 2, 2025
Insulation
Partial ApprovalInspectorBret Eggers
6th floor unit insulation is complete
- Mar 27, 2025
Framing
Partial ApprovalInspectorBret Eggers
6th floor units have all been inspected.
- Mar 27, 2025
Insulation
Partial ApprovalInspectorBret Eggers
6th floor east wing to elevator completed.
- Mar 27, 2025
Fire Stopping
Partial ApprovalInspectorBret Eggers
6th floor units have been completed
- Mar 21, 2025
Framing
Partial ApprovalInspectorMike Lockman
Framing & firecaulking for units 624-630, 632, 640 & 641
- Mar 20, 2025
Framing
Partial ApprovalInspectorBret Eggers
Framing for units 631-639
- Mar 12, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
spoke with Brian re: unit finals next week. will schedule (2) inspectors starting March 17 and come up with a list to post on unit doors to track inspections per unit
- Mar 10, 2025
Framing
Cancelled AppointmentInspectorMike Lockman
Cancelled by Bryan @ Big D
- Mar 7, 2025
Framing
Completed in Future.InspectorBrian Stemwedel
talked with Brian and Adam re: F/S dampers and duct detector locations.
- Mar 6, 2025
Framing
Completed in Future.InspectorBrian Stemwedel
met with Adam to discuss ceiling condition over units on 5th floor. identified approved plans were not accurate (show detail R1, detail R2 is what is planned) informed them revised plans would need to be approved by Jake and Building insp. but the R2 detail appeared to comply with NFPA 13 for concealed space(s) exception. also verified standpipe locations (new) would be in a concealed space with a area of less than 10 sq. ft.. this will also require revised plans as a 2 hour shaft is being eliminated
- Feb 26, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
looked at parapet on roof. attachment per approved details. also talked with Adam re: eliminating 2 hour shaft for standpipe chase and continuing rated floor through deadspace at every level and firestopping around penetrations following details per NFPA 13-16 Section 8.15.1.2.14 (no sprinkler required in comb. deadspace detail)
- Feb 21, 2025
Radon Control
Partial ApprovalInspectorBrian Stemwedel
Rock under slab (units in garage area)
- Feb 20, 2025
Footing
Partial ApprovalInspectorBrian Stemwedel
little work ready for inspection
- Feb 12, 2025
Framing
Not ReadyInspectorMike Lockman
Contractors didn't have anything to look at today
- Feb 3, 2025
Framing
Not ReadyInspectorMike Lockman
No inspections on building permit today, only plumbing
- Jan 17, 2025
Framing
Completed in Future.InspectorBrian Stemwedel
Met to go over changes to original plans and discussed control locations for showers in type B units. wil need to research more to answer questions
- Jan 16, 2025
Framing
Met for ConsultationInspectorBret Eggers
Met to discuss Type B unit plumbing requirements. The shower valve in some type B units is off set from the shower head. They wanted to install the valve in line with the shower head. I told them that it must comply with Minnesota 2020 Plumbing Code section 408.9
- Jan 15, 2025
Floor Slab-Reinforcement
Partial ApprovalInspectorBrian Stemwedel
looked at floor slab section on LL apartment slab on grade
- Jan 13, 2025
Radon Control
Partial ApprovalInspectorMike Lockman
Vapor barrier installed on 1st floor of the E wing from GL9.2 to GL10
- Dec 30, 2024
Framing
Not ReadyInspectorMike Lockman
Per Bryan @ Big D - Pause inspections the week of 12/30 - 1/3
- Dec 27, 2024
Footing
Not ReadyInspectorBrian Stemwedel
NO WORK READY FOR INSPECTION (HOLIDAY WEEK)
- Dec 23, 2024
Framing
Not ReadyInspectorMike Lockman
Nothing ready for inspection today
- Dec 20, 2024
Fire Stopping
Not ReadyInspectorBrian Stemwedel
contractor did not have anything to inspect
- Dec 16, 2024
Framing
Cancelled AppointmentInspectorMike Lockman
Cancelled by contractor
- Dec 13, 2024
Footing
Not ReadyInspectorBrian Stemwedel
sub zero temps. no work due to temp.
- Dec 12, 2024
Framing
Cancelled AppointmentInspectorMike Lockman
Cancelled due to sub-zero temps. Crews not on site
- Dec 5, 2024
Footing
Cancelled AppointmentInspectorMike Lockman
- Dec 5, 2024
Fire Stopping
Completed in Future.InspectorBrian Stemwedel
Met with contractor to discuss FS in airspace between IIIA and IIA parking garage
- Dec 4, 2024
Floor Slab-Reinforcement
Not ReadyInspectorBrian Stemwedel
- Nov 25, 2024
Rated Gypsum Assemblies
Partial ApprovalInspectorMike Lockman
First and second layer - Joints stagered 16" . for the mechanical and stair shafts on the 3rd floor/East wing
- Nov 22, 2024
Rated Gypsum Assemblies
Partial ApprovalInspectorMike Lockman
Second gypsum layer on the S stairwell of the W wing. Second layer of gypsum on the S mechanical shaft of the W wing. Seems have been staggered approximately 18"
- Nov 18, 2024
Footing
CompletedInspectorBret Eggers
- Nov 18, 2024
Footing - Reinforcing
CompletedInspectorBret Eggers
- Nov 18, 2024
Wall Reinforcing
CompletedInspectorBret Eggers
- Nov 13, 2024
Floor Slab-Reinforcement
Partial ApprovalInspectorMike Lockman
Re-inforcement at thickend slab and shallow footings for Area B on the W side of the parking structure.
- Nov 12, 2024
Rated Gypsum Assemblies
Partial ApprovalInspectorMike Lockman
3 Hr fire wall on E side of parking structure. SCWAP. Detail work at the corridor horizontal exit has not been completed at time of inspection.
- Nov 7, 2024
Poured Wall
Partial ApprovalInspectorBret Eggers
GL 1 thru 2 Between D2 and F8
- Nov 7, 2024
Radon Control
Partial ApprovalInspectorBret Eggers
UG East elevation of garage
- Nov 6, 2024
Footing
Partial ApprovalInspectorBret Eggers
D thru F between D2 and F
- Nov 6, 2024
Rated Gypsum Assemblies
Partial ApprovalInspectorBret Eggers
Trash shoot 1st floor Rated assembly
- Nov 5, 2024
Footing
Cancelled AppointmentInspectorBret Eggers
Due to rain
- Nov 4, 2024
Rated Gypsum Assemblies
Partial ApprovalInspectorMike Lockman
Layer 1 of gypsum for trash chute on SE corner of parking structure
- Nov 1, 2024
Footing
Cancelled AppointmentInspectorMike Lockman
- Oct 31, 2024
Footing
Cancelled AppointmentInspectorMike Lockman
Cancelled by Brian @ Big D
- Oct 30, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Poured wall along GL-1 from B.3 to D.2
- Oct 30, 2024
Wall Reinforcing
Partial ApprovalInspectorMike Lockman
Wall along GL-1 from B3 to D2
- Oct 29, 2024
Rated Gypsum Assemblies
Partial ApprovalInspectorMike Lockman
Gypsum install. Second floor. Section A - East staircase. Minimum of 1 foot lap on gypsum panels seams
- Oct 29, 2024
Floor Slab-Reinforcement
Partial ApprovalInspectorMike Lockman
Curb pour for half of 6th floor on parking structure.
- Oct 28, 2024
Footing
Partial ApprovalInspectorBret Eggers
GL B 3 thru D.2
- Oct 28, 2024
Rated Gypsum Assemblies
Partial ApprovalInspectorBret Eggers
Mechanical shaft second floor SE corner
- Oct 25, 2024
Footing
CompletedInspectorMike Lockman
Footing along Grid 1 from B.2 to C
- Oct 25, 2024
Footing - Reinforcing
Partial ApprovalInspectorMike Lockman
Grid 1 from B.2 to C
- Oct 25, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Poured wall along Grid 1 from A to B.2
- Oct 25, 2024
Wall Reinforcing
Partial ApprovalInspectorMike Lockman
Wall along Grid 1 from A to B.2
- Oct 23, 2024
Footing
Partial ApprovalInspectorBret Eggers
gl1 from A1 to A3
- Oct 23, 2024
Poured Wall
Partial ApprovalInspectorBret Eggers
GL D from 8 thru 8.8
- Oct 22, 2024
Other - Concrete Piers
Partial ApprovalInspectorMike Lockman
Final 5 concrete piers for W wing of Section A
- Oct 22, 2024
Footing
Partial ApprovalInspectorMike Lockman
Column pads along C9 @ 8.0, 8.1, 8.2
- Oct 22, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Wall along GL-A between 3 & 5
- Oct 22, 2024
Wall Reinforcing
Partial ApprovalInspectorMike Lockman
Wall along GL-A between 3 & 5
- Oct 21, 2024
Footing
Not ReadyInspectorBret Eggers
- Oct 18, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
columns on C.4 from 8.5 to 8.9
- Oct 17, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
Spread footings for columns on C.4 from 8.5 to 8.9
- Oct 16, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
looked at footings and poured walls. updated plan set on jobsite (highlight) Plans are current with work completed
- Oct 10, 2024
Footing - Reinforcing
Partial ApprovalInspectorBret Eggers
2 areas 1) GL 6.8 -and 7 Between A and B A between 7 and 4 2) C1 thru C at 8.9
- Oct 10, 2024
Wall Reinforcing
Partial ApprovalInspectorBret Eggers
GL 9 between C1 and C4
- Oct 9, 2024
Other - Concrete Piers
Partial ApprovalInspectorBret Eggers
last 4 columns SW corner
- Oct 7, 2024
Footing
Not ReadyInspectorMike Lockman
- Oct 4, 2024
Footing - Reinforcing
Partial ApprovalInspectorBret Eggers
GL 8.4 - 9 and c - c.4
- Oct 3, 2024
Footing
Cancelled AppointmentInspectorMike Lockman
Cancelled by job sup
- Oct 3, 2024
Footing - Reinforcing
Cancelled AppointmentInspectorMike Lockman
Cancelled by job sup
- Oct 1, 2024
Footing
Cancelled AppointmentInspectorBret Eggers
- Sep 30, 2024
Other - Concrete Piers
Partial ApprovalInspectorMike Lockman
4 Piers along GL-6.8 at intersections B, B1, B3 & B7
- Sep 30, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Wall along GL-C from 6.8 south to 8.1 Wall at SW corner of parking structure from GL-B to C
- Sep 27, 2024
Footing
Cancelled AppointmentInspectorBrian Stemwedel
additional footings not ready. will cast footings identified previously on Monday Sept 30
- Sep 26, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
8.1 to 6.8 on C line, B3 to C on 7
- Sep 25, 2024
Footing
Partial ApprovalInspectorBret Eggers
GL B thru B7 and 5 thru 7.5 Brian to see completed reinforcement photos 9/26/24
- Sep 23, 2024
Other - Concrete Piers
Partial ApprovalInspectorMike Lockman
(3) Concrete piers on Grid Line C.1 at GL's 8.2 / 8.3 & 8.4
- Sep 20, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
Columns on B7 to E on 6.2
- Sep 20, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
footings on C line from 8.5 to 8.1
- Sep 19, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Poured wall from D/8 south to D/8.4. SCWAP
- Sep 19, 2024
Footing
Partial ApprovalInspectorMike Lockman
(4) Pad footings. (1) at Grid Line D.9 between 6.2 and 6.8. (2) at Grid Line D.4 between 6.2 and 6.8. (1) at Grid Line D between 6.2 and 6.8.
- Sep 18, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
grid 8 from D to G.3
- Sep 17, 2024
Footing
Partial ApprovalInspectorMike Lockman
(3) Column pad footings along GL-H.9 from 9.2 to G.9, (1) pad footing at GL-6.2 just E of GL-G.9. (2) pad footings just N of GL-6.8 at F.8 and g.3. (2) pad footings at F/4.7 & F/6.
- Sep 17, 2024
Other - Concrete Piers
Partial ApprovalInspectorMike Lockman
(4) Columns along GL-D from GL-8.1 to GL-8.4. SCWAP
- Sep 16, 2024
Footing
Partial ApprovalInspectorMike Lockman
Strip footing along Grid Line D from GL-8 to GL-8.4 as well as 3 pad footing in same location. All are SCWAP
- Sep 16, 2024
Other - Concrete Piers
Partial ApprovalInspectorMike Lockman
(7) Concrete columns along Grid Line H.9 intersecting at 9.3 / 9.4 / 9.6 / 9.7 / 9.8 and halfway between 9.8 and 9.9
- Sep 16, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Poured wall running E to W just north of GL-3.7 on the E side of the parking structure and the wall running E to W just S of GL-4.2.
- Sep 13, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
marked on plans in job trailer
- Sep 12, 2024
Footing
Partial ApprovalInspectorMike Lockman
Strip footing E side of parking structure just N of Grid Line 3.7 from GL-E to GL-G. Strip footing just E of Grid Line F from GL-3.7 to GL-4.2
- Sep 12, 2024
Other - Concrete Piers
Partial ApprovalInspectorMike Lockman
Columns at the following intercections... D.4/7.5, E/7.5, F.8/7.5, F.8/5 and F.8/4.5. All SCWAP
- Sep 12, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Anchor slabs along E wall per engineering for securing the E wall along Grid Line I at the following locations... GL9.3, from GL9.6 to 9.7, from GL9.8 to 9.9. Contractor (Brian) to provide engineering documents and SI reports to our office.
- Sep 11, 2024
Other - Concrete Piers
Partial ApprovalInspectorBret Eggers
4 columns (of 5) North side area A. Only remaining column the one furthest North
- Sep 11, 2024
Poured Wall
Partial ApprovalInspectorBret Eggers
North Side Area A
- Sep 10, 2024
Footing
CompletedInspectorBrian Stemwedel
Remaining columns Grid I. Footings On Grid 8 (run east and west from D to G.3. marked on plans on site
- Sep 10, 2024
Footing - Reinforcing
Partial ApprovalInspectorBrian Stemwedel
All footings through 9/4 (Verified via SI reports)
- Sep 9, 2024
Footing
Partial ApprovalInspectorBret Eggers
Grid line 5 (turns North on Grid line G) on F8 4.1 thru 5 6 Piers GL J8 9.1 thru 9.7
- Sep 9, 2024
Poured Wall
Partial ApprovalInspectorBret Eggers
GL5 G3 thru I
- Sep 6, 2024
Other - Concrete Piers
Partial ApprovalInspectorMike Lockman
(4) Piers along GL 9.9 & 10 from grid line H to grid line I and (1) pier at J.8 - 9.8 and (1) pier at I - 9.8. All SCWAP
- Sep 5, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Poured wall along GL - I from grid 9.2 north to grid 5. SCWAP
- Sep 5, 2024
Other - Concrete Piers
Partial ApprovalInspectorMike Lockman
Columns along GL - H from grid 9.7 north to grid 9.2. Total of 5 columns. SCWAP
- Sep 4, 2024
Footing - Reinforcing
Cancelled AppointmentInspectorDan Anderson
- Sep 4, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
remaining footings on gridline I
- Sep 4, 2024
Other - Concrete Piers
Partial ApprovalInspectorBrian Stemwedel
Columns along gridline I
- Sep 3, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
along gridline I and columns from 9.9 to 9.3
- Aug 30, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
Footings along gridline I and columns from 9.9 to 9.3. includes column pads
- Aug 29, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
Poured wall along gridline I and columns from 9.9 to 9.3
- Aug 28, 2024
Footing
Not ReadyInspectorBrian Stemwedel
work will be inspected on 8/28 prior to casting poured wall/ columns
- Aug 26, 2024
Footing
Partial ApprovalInspectorMike Lockman
Piers/post footing at the following intersections. J8 @ 9.8 / J8 @9.7 and J8 @ 9.6. SCWAP w/ reinforcement
- Aug 26, 2024
Footing - Reinforcing
Partial ApprovalInspectorMike Lockman
See footing notes for location details.
- Aug 23, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
Remaining poured wall S side Gridlines 10-9.9 from H to I
- Aug 23, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
Spread footings S.E. corner along gridline I from 9.9 to column just N of 9.8. includes column and area NW of 9.8 on J.8
- Aug 22, 2024
Footing
Cancelled AppointmentInspectorBrian Stemwedel
no work ready
- Aug 21, 2024
Poured Wall
Partial ApprovalInspectorBret Eggers
G9 and 9.55 - 10 4 columns on grid line 9.9 thru 10
- Aug 20, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
Spread footings on east apt building's south side from H to I on gridline(s) 10-9.9
- Aug 19, 2024
Footing
Partial ApprovalInspectorMike Lockman
Area A footings along Grild Line H from GL7.5 to GL10. SCWAP. Highlighted and signed on job site plans.
- Aug 19, 2024
Footing - Reinforcing
Partial ApprovalInspectorMike Lockman
- Aug 14, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
remaining footings for parking structure. all footings for parking structure complete
- Aug 13, 2024
Wall Reinforcing
Partial ApprovalInspectorBret Eggers
Elevator pit and B4 - B6 and stairway wall
- Aug 12, 2024
Footing
Partial ApprovalInspectorBret Eggers
Grid line E and 3-5
- Aug 12, 2024
Poured Wall
Partial ApprovalInspectorBret Eggers
Grid line B and 3-6
- Aug 9, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
Elevator pit floor. noted (3) 4" PVC drains. and reinforcement ISCWAP. Also remaining spread footings on east side of parking structure. highlighted plans on site
- Aug 8, 2024
Footing
Not ReadyInspectorBrian Stemwedel
no additional work ready at time of inspection
- Aug 7, 2024
Poured Wall
Not ReadyInspectorBrian Stemwedel
contractor did not have additional work ready. was casting poured wall approved on 8/6
- Aug 6, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
Along grid 4 from b to c9
- Aug 5, 2024
Footing
Cancelled AppointmentInspectorBret Eggers
Due to rain
- Aug 2, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
Center spread footings on 4 from C to D2 ISCWAP
- Aug 2, 2024
Footing - Reinforcing
Partial ApprovalInspectorBrian Stemwedel
Reinforcing for all footings inspected through 7/29/24 (verified via SI daily reports)
- Aug 1, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
Center footings parking structure. Along grid 4 from B to C ISCWAP
- Jul 31, 2024
Footing
Partial ApprovalInspectorBret Eggers
lines B = B3 and 4 -5
- Jul 31, 2024
Poured Wall
Partial ApprovalInspectorBret Eggers
Beteen B - B3 north wall
- Jul 29, 2024
Footing
Partial ApprovalInspectorMike Lockman
Grid line 3 from C.4 to E. Grid line E from B to 3.5 Reinforcement SCWAP. On site with B Eggers.
- Jul 29, 2024
Foundation Waterproofing
Partial ApprovalInspectorMike Lockman
60 Mil adhesive applied WP on Grid B from 3 to 4 (center of ramp) and Grid 3 from B to C. Water proofing install 6 feet above footing and 1 foot onto top of footing. Remainder of wall to be completed in future after some backfilling is completed..
- Jul 29, 2024
Poured Wall
Partial ApprovalInspectorMike Lockman
Grid 3 from C to C.4 Reinforcement is SCWAP
- Jul 25, 2024
Poured Wall
Partial ApprovalInspectorBrian Stemwedel
Contractor had to add chairs at top of wall (clearance to face) approved poured wass section(s) Grid B from 3 to 3.3 and Grid 3 from B to B.3
- Jul 23, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
Continuing from NW corner- South on B from 3.3 to 4.7, East on 3 from B.3 to C.4
- Jul 19, 2024
Footing
Partial ApprovalInspectorBrian Stemwedel
far NW corner of parking structure. Grid B from 3 to 3.3, Grid 3 from B to B.3