#GV116601

Building

640 Wisconsin Ave N, Golden Valley

IssuedJul 17, 2024
StatusUnknown
Value$70,000,000
Inspections273
Scope of work

New, SENTINEL parking ramp and 303 unit apartment bldg

Location context
Parcel3111821140190
Coordinates44.98564, -93.38527
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$124,512.91
Total paid$124,512.91
Timeline
ApprovedJul 16, 2024
IssuedJul 17, 2024
Inspection record
Inspections273
Passed227
Failed0
  1. Jan 27, 2026

    Other - Letters of Substantial Completion

    Completed

    InspectorDan Anderson

  2. Jan 27, 2026

    Final

    Completed

    InspectorDan Anderson

  3. Jan 21, 2026

    Special Inspections

    Completed

    InspectorDan Anderson

    received final report 1/21/26
  4. Jan 21, 2026

    Special Inspections - Structural Engineer

    Completed

    InspectorDan Anderson

    received final report 1/21/26
  5. Jan 16, 2026

    Final

    Partial Approval

    InspectorMike Lockman

    Corridor inspections for 1st thru 4th floors. Re-check needed for the Low Voltage room on 3rd floor of Bldg B. ( doors wouldnt open / still need inspection. Glazing in the door for the dog wash was not etched for tempered glass - Adam to work on this. On-site with Garrett H.
  6. Jan 15, 2026

    Final

    Need Correction

    InspectorMike Lockman

    Inspection for parking structure. Several extinguisher cabinet not installed on center stitch wall. Fall protection not completed for snow chute on top level. Inspection completed w/ Bret E
  7. Jan 14, 2026

    Sanitarian Final

    Completed

    InspectorDan Anderson

    See letter dated from MDH 12/4/25 in Laserfiche.
  8. Jan 14, 2026

    Fire Stopping

    Completed

    InspectorBret Eggers

    Doors into garage level one and at garage door openings
  9. Jan 12, 2026

    Other - Verify Elevator Final

    Completed

    InspectorDan Anderson

    received Certificate of Approval letters 1/12/26 for all three cars
  10. Jan 12, 2026

    Verify Fire Final

    Completed

    InspectorDan Anderson

    Fire permits closed out 12/30/25
  11. Jan 12, 2026

    Verify Electrical Final

    Completed

    InspectorDan Anderson

    Final electrical close out 11/24/25
  12. Jan 10, 2026

    Final

    Partial Approval

    InspectorGarrett Heins

    With Mike Lockman - Inspection for the gas grills in all common areas of courtyard and sky lounge. Verified the E-stop in functioning as it should.
  13. Dec 30, 2025

    Final

    Partial Approval

    InspectorBret Eggers

    All unit finals have been completed with the exception off orsat test, unit door inspection, and fireplace finals
  14. Dec 29, 2025

    As-Built Survey

    Completed

    InspectorDan Anderson

  15. Dec 26, 2025

    Final

    Cancelled Appointment

    InspectorMike Lockman

    No inspections today per Bryan and Adam @ Big D
  16. Dec 19, 2025

    Final

    Cancelled Appointment

    InspectorMike Lockman

    No inspections today per Adam @ Big D
  17. Dec 18, 2025

    Final

    Partial Approval

    InspectorBret Eggers

    Elevator lobby smoke door closing with smoke alarm initiation
  18. Dec 17, 2025

    Fire Stopping

    Completed

    InspectorBret Eggers

    Final inspections approved
  19. Dec 17, 2025

    Final

    Partial Approval

    InspectorGarrett Heins

    With Bret Eggers - Power drop, including exterior lighting, interior lighting and rated corridor door mag lock release.
  20. Dec 16, 2025

    I & I Inspection

    Completed

    InspectorDan Anderson

    compliance certificate dated 12/10/25
  21. Dec 16, 2025

    Final

    Partial Approval

    InspectorGarrett Heins

    With Dan Anderson, Mike Lockman, Bret Eggers
  22. Dec 11, 2025

    Final

    Partial Approval

    InspectorBret Eggers

    2nd flooir units except 226 which is being used as storage
  23. Dec 10, 2025

    Final

    Cancelled Appointment

    InspectorMike Lockman

    No inspections today per Bryan @ Big D
  24. Dec 8, 2025

    Final

    Partial Approval

    InspectorGarrett Heins

    With Brett Eggers - All units except 326 which is being used as storage. Also need to double check glass panel railing on decks to make sure they are attached to base.
  25. Dec 5, 2025

    Final

    Cancelled Appointment

    InspectorMike Lockman

    No inspection needed today per Adam @ Big D
Show 248 earlier inspections
  1. Dec 3, 2025

    Final

    Partial Approval

    InspectorMike Lockman

    Unit finals for all units on 4th floor in both A & B buildings
  2. Dec 2, 2025

    Final

    Partial Approval

    InspectorBret Eggers

    All units on 5th floor except 526 which is being used as temp storage
  3. Nov 26, 2025

    Floor Slab-Reinforcement

    Completed

    InspectorMike Lockman

  4. Nov 26, 2025

    Framing

    Completed

    InspectorMike Lockman

  5. Nov 26, 2025

    Footing

    Completed

    InspectorMike Lockman

  6. Nov 26, 2025

    Insulation

    Completed

    InspectorMike Lockman

  7. Nov 26, 2025

    Other - Reinforcing Before Applying Shopcrete

    Completed

    InspectorMike Lockman

  8. Nov 26, 2025

    Other - Stoop Reinforcing

    Completed

    InspectorMike Lockman

  9. Nov 26, 2025

    Wall Reinforcing - Lintel Locations

    Completed

    InspectorMike Lockman

  10. Nov 26, 2025

    Rated Gypsum Assemblies

    Completed

    InspectorMike Lockman

  11. Nov 26, 2025

    Radon Control

    Completed

    InspectorMike Lockman

    Inspected during plumbing RI's
  12. Nov 26, 2025

    Poured Wall

    Completed

    InspectorMike Lockman

  13. Nov 26, 2025

    Final

    Partial Approval

    InspectorGarrett Heins

    With Mike Lockman - Unit finals completed for Bdlg A / W wing / floor 6. Corrections completed for floor 6 units in E wing.
  14. Nov 24, 2025

    Final

    Partial Approval

    InspectorMike Lockman

    Unit finals only for 6th floor Bldg A / East wing completed up to elevators with the exception of units 626 (not ready), 630, 635 & 642 needing fire caulking in magic pack closet on rated ceilings. Many door seals need adjustment - Look at all door seals when doing corridor inspections
  15. Nov 14, 2025

    Final

    Cancelled Appointment

    InspectorMike Lockman

    No inspections today per Bryan @ Big D
  16. Nov 7, 2025

    Final

    Cancelled Appointment

    InspectorMike Lockman

    No inspections today per Bryan @ Big D
  17. Oct 24, 2025

    Other

    Cancelled Appointment

    InspectorMike Lockman

    No inspections today per Brian @ Big D
  18. Oct 17, 2025

    Other

    Cancelled Appointment

    InspectorMike Lockman

    No inspections needed today per text from Bryan @ Big-D
  19. Oct 10, 2025

    Other

    Cancelled Appointment

    InspectorMike Lockman

    Inspection cancelled by Bryan @ Big D
  20. Oct 3, 2025

    Framing-Above Ceiling

    Completed

    InspectorMike Lockman

    Inspected golf simulator room, Theater room, Bike storage, Dog wash and trash room. Should be last of the above-ceiling required
  21. Sep 26, 2025

    Framing

    Cancelled Appointment

    InspectorMike Lockman

    Inspection not needed today per Adam @ Bid D
  22. Sep 24, 2025

    Flat Roof/Tear-Off

    Completed

    InspectorBret Eggers

    Insulation as per approved plans
  23. Sep 24, 2025

    Framing-Above Ceiling

    Partial Approval

    InspectorBret Eggers

    All of 1st floor except dog was area and trash room
  24. Sep 19, 2025

    Framing

    Cancelled Appointment

    InspectorMike Lockman

    Cancelled by Bryan @ Big D
  25. Sep 18, 2025

    Footing

    Completed

    InspectorBret Eggers

    Stair reinforcing for pool and hot tub
  26. Sep 12, 2025

    Other

    Partial Approval

    InspectorMike Lockman

    UG pool piping for the hot tub/spa
  27. Sep 9, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorMike Lockman

    Rated ceiling inspection for the corridor on 1st floor / Bldg B
  28. Aug 29, 2025

    Other - Reinforcing Before Applying Shopcrete

    Partial Approval

    InspectorMike Lockman

    Re-inforcement for the pool and spa. Stairs to be completed after installation of the shotcrete application
  29. Aug 25, 2025

    Insulation

    Cancelled Appointment

    InspectorMike Lockman

    No inspection today per Bryan @ Big D
  30. Aug 22, 2025

    Insulation

    Partial Approval

    InspectorBrian Stemwedel

    1st floor liner wall at corridor. insulation and VB
  31. Aug 15, 2025

    Wall Reinforcing

    Completed

    InspectorMike Lockman

    Reinforcement for pool equipment bldg. #4 bar @ 12" OC horizontal and vertical
  32. Aug 15, 2025

    Other - Reinforcing Before Applying Shopcrete

    Partial Approval

    InspectorMike Lockman

    Reinforcement for hot tub/spa. #4 bar - 12" OC both ways for walls and floor
  33. Aug 14, 2025

    Rated Gypsum Assemblies

    Cancelled Appointment

    InspectorMike Lockman

    No inspections today per Bryan at Big-D
  34. Aug 13, 2025

    Rated Gypsum Assemblies

    Completed

    InspectorBret Eggers

    Building B floor 1
  35. Aug 8, 2025

    Footing

    Partial Approval

    InspectorMike Lockman

    8-12 Inches of river rock sub-base installed for the exterior pool and hot tub. Rigid foam insulation installed atop the aggregate for the hot tub.
  36. Aug 7, 2025

    Rated Gypsum Assemblies

    Cancelled Appointment

    InspectorMike Lockman

    No inspections today per Bryan @ Big-D
  37. Aug 6, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBret Eggers

    B 2 all units
  38. Aug 1, 2025

    Footing - Landing

    Completed

    InspectorBrian Stemwedel

    exterior landings ISCWAP
  39. Jul 31, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBret Eggers

    Building A all of floor 2 is completed
  40. Jul 30, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    Blown in ceiling complete building B floor 1 except for 3 units with water dammage
  41. Jul 29, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorMike Lockman

    Drywall inspection for units on 2nd floor / W wing with the exception of unit 250 not being completed at time of inspection. Also looked at the storage closet area on 2nd floor / W wing
  42. Jul 28, 2025

    Insulation

    Need Correction

    InspectorMike Lockman

    Failed inspection in 1B due to storm water saturating the lid insulation in the area of the Magic-Pac units. Felt on ceiling was holding water until a hole was made to let the water drain. Contractor to remove all wet insulation and install new insulation. Upper units will need to be spot checked for wet insulation above the drywall.
  43. Jul 22, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBrian Stemwedel

    gyp @ shear walls in 2A
  44. Jul 21, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    All exterior walls and ceilings in building B floor 2 have been completed
  45. Jul 16, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBret Eggers

    3rd floor building A is complete
  46. Jul 15, 2025

    Final

    Partial Approval

    InspectorGarrett Heins

    Corridor inspection Levels 6 and 5 with Bret Eggers. Units 649, 533, & 527 require adjustment. Southwest fire door level 5 also requires adjustment.
  47. Jul 14, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    2 B ceiling and wall insulation complete
  48. Jul 11, 2025

    Drain Tile

    Completed

    InspectorBrian Stemwedel

  49. Jul 11, 2025

    Foundation Insulation

    Completed

    InspectorBrian Stemwedel

  50. Jul 11, 2025

    Foundation Waterproofing

    Completed

    InspectorBrian Stemwedel

  51. Jul 11, 2025

    Other - Concrete Piers

    Completed

    InspectorBrian Stemwedel

  52. Jul 11, 2025

    Other - Grout Lintels

    Completed

    InspectorBrian Stemwedel

  53. Jul 11, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBrian Stemwedel

    Looked at shaft liner at elevator doorways. ok to proceed on levels 1-6
  54. Jul 10, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBrian Stemwedel

    3A west 301-304 and 344 and 345
  55. Jul 9, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    Exterior walls all units B3
  56. Jul 7, 2025

    Insulation

    Cancelled Appointment

    InspectorMike Lockman

    No inspection today per Bryan @ Big D
  57. Jul 3, 2025

    Submit Pictures of House Wrap

    Completed

    InspectorBret Eggers

  58. Jul 3, 2025

    Final

    Partial Approval

    InspectorBret Eggers

    3rd floor units only both buildings
  59. Jul 3, 2025

    Insulation

    Partial Approval

    InspectorBrian Stemwedel

    exterior walls 2 West
  60. Jul 1, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    Building A east wing. South 4 units
  61. Jun 30, 2025

    Footing

    Partial Approval

    InspectorBret Eggers

    Pool house
  62. Jun 30, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    Bldg A east to elevators
  63. Jun 27, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBrian Stemwedel

    3 west Shear wall gyp
  64. Jun 26, 2025

    Framing

    Partial Approval

    InspectorBrian Stemwedel

    1B with B.E.
  65. Jun 24, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Wall & sound insulation on 2nd floor / Bldg A / E wing with Brian S
  66. Jun 23, 2025

    Foundation Insulation

    Partial Approval

    InspectorMike Lockman

    Lid insulation on 3rd floor / Bldg A / W wing
  67. Jun 23, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    Building 1 east side, both exterior and interior walls
  68. Jun 20, 2025

    Framing

    Partial Approval

    InspectorMike Lockman

    Per Bryan @ Big D - he will have stuff to look at on monday when the insulator is done in that area.
  69. Jun 18, 2025

    Insulation

    Partial Approval

    InspectorBrian Stemwedel

    lids on 3B with B.E.
  70. Jun 18, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBrian Stemwedel

    shear walls in 4B
  71. Jun 13, 2025

    Framing

    Cancelled Appointment

    InspectorMike Lockman

    Inspection cancelled by Bryan @ B-D
  72. Jun 12, 2025

    Framing

    Partial Approval

    InspectorBret Eggers

    Units 127, 128, 130,131, 132 ,133,134, 135,136, 137, 138,139, 140, 141
  73. Jun 11, 2025

    Insulation

    Partial Approval

    InspectorBrian Stemwedel

    3B bldg. ex. wall insulation and VB with B.E.
  74. Jun 10, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Lid insulation for floor 3A is complete
  75. Jun 10, 2025

    Framing

    Partial Approval

    InspectorMike Lockman

    2nd floor / E wing completed
  76. Jun 10, 2025

    Fire Stopping

    Partial Approval

    InspectorMike Lockman

    2nd floor / E wing completed
  77. Jun 9, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Lid insulation for units on 3rd floor / E wing / Bldg A except for units 329 thru 333 that have not been completed yet.
  78. Jun 5, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorMike Lockman

    Drywall in units. 4th floor / Bldg A
  79. Jun 4, 2025

    Insulation

    Partial Approval

    InspectorBrian Stemwedel

    With Bret Eggers 3rd floor Building A, East finger- Exterior wall insulation and Vapor Barrier
  80. Jun 3, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Ceiling insulation completed for all units on 4th floor / Bldg B
  81. Jun 2, 2025

    Fire Stopping

    Partial Approval

    InspectorMike Lockman

    Bldg A / E wing / 2nd floor completed w/ Bret E
  82. Jun 2, 2025

    Framing

    Partial Approval

    InspectorMike Lockman

    Bldg A / E wing / 2nd floor completed w/ Bret E
  83. May 29, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    Exterior walls B 5 whole floor
  84. May 28, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBrian Stemwedel

    Gyp in shear walls on 4B
  85. May 27, 2025

    Insulation

    Partial Approval

    InspectorBrian Stemwedel

    lid insulation on floor 4
  86. May 23, 2025

    Framing

    Partial Approval

    InspectorMike Lockman

    Framing & firestopping 3rd floor / Bldg B
  87. May 21, 2025

    Insulation

    Partial Approval

    InspectorBrian Stemwedel

    insulation on 4th floor. signed inspection records on site (per room)
  88. May 20, 2025

    Framing

    Partial Approval

    InspectorMike Lockman

    No inspections today. Small consult with Big D. On site with Brian S.
  89. May 15, 2025

    Framing

    Partial Approval

    InspectorBrian Stemwedel

    3rd floor area A
  90. May 12, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Ceiling insulation completed in all units and hallways in E wing of Bldg A up to the elevators.
  91. May 6, 2025

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBret Eggers

    All 5th floor except 547 - 558 and 501 - 504
  92. May 6, 2025

    Fire Stopping

    Partial Approval

    InspectorBret Eggers

    All units and hallways 4B
  93. May 6, 2025

    Framing

    Partial Approval

    InspectorBret Eggers

    All units and hallways 4B
  94. May 2, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Exterior wall insulation completed on 4th floor / Bldg A / E wing up to elevators.
  95. Apr 30, 2025

    Framing

    Partial Approval

    InspectorBrian Stemwedel

    Completed framing firestop on 5th floor building B. noted that on the 05 stack (unit 505) and on the 18 stack (unit 518) floor openings around shaft(s) were open from foundation to roof. need to be fireblocked with 1 hour rated material. (required floor rating)
  96. Apr 29, 2025

    Framing

    Partial Approval

    InspectorMike Lockman

    Framing for W wing / 4th floor / Bldg A. Units and corridor completed along with the Sky Lounge on 6th floor
  97. Apr 29, 2025

    Fire Stopping

    Partial Approval

    InspectorMike Lockman

    W wing / 4th. floor / Bldg A. Units and corridor
  98. Apr 28, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Remainder of blown cellulose in unit ceilings on 5th flloor / Bldg A
  99. Apr 23, 2025

    Framing

    Completed in Future.

    InspectorBrian Stemwedel

    verify blue elec. boxes installed in corridor walls are rated
  100. Apr 21, 2025

    Fire Stopping

    Partial Approval

    InspectorMike Lockman

    Bldg A / 4th Floor. Fire stopping for E wing up to elevators. Completed w/ Bret E.
  101. Apr 21, 2025

    Framing

    Partial Approval

    InspectorMike Lockman

    Bldg A / 4 th floor. Framing for all units and corridors in the E wing up to elevators. Completed w/ Bret E
  102. Apr 21, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Bldg A / 5th floor. Ceiling insulation completed in E wing of all units up to elevators
  103. Apr 18, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Bldg A / 5th floor - Blown insulation in ceiling space of units from S end on E wing up to trash chute. Batt insulation in ceiling space of corridors and common areas up to trash chute. Exterior wall insulation and VB in the W wing units.
  104. Apr 15, 2025

    Fire Stopping

    Partial Approval

    InspectorBret Eggers

    With ML see his notes
  105. Apr 15, 2025

    Framing

    Partial Approval

    InspectorBret Eggers

    All of 5th floor building 1 is complete. Units and corridors
  106. Apr 14, 2025

    Insulation

    Partial Approval

    InspectorMike Lockman

    Insulation for units on 5th floor / Bldg A / E wing.
  107. Apr 14, 2025

    Fire Stopping

    Partial Approval

    InspectorMike Lockman

    Framing & fire stopping for 5th and 6th floor stair wells on E and W wings
  108. Apr 7, 2025

    Framing

    Partial Approval

    InspectorBret Eggers

    All framing for units on 5th floor completed 557
  109. Apr 7, 2025

    Fire Stopping

    Partial Approval

    InspectorBret Eggers

    All units on 5th floor except 557 are completed
  110. Apr 4, 2025

    Fire Stopping

    Partial Approval

    InspectorMike Lockman

    5th floor E wing completed up to elevator lobby
  111. Apr 4, 2025

    Framing

    Partial Approval

    InspectorBrian Stemwedel

    5th floor on east wing to elevator lobby
  112. Apr 2, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    6th floor unit insulation is complete
  113. Mar 27, 2025

    Framing

    Partial Approval

    InspectorBret Eggers

    6th floor units have all been inspected.
  114. Mar 27, 2025

    Insulation

    Partial Approval

    InspectorBret Eggers

    6th floor east wing to elevator completed.
  115. Mar 27, 2025

    Fire Stopping

    Partial Approval

    InspectorBret Eggers

    6th floor units have been completed
  116. Mar 21, 2025

    Framing

    Partial Approval

    InspectorMike Lockman

    Framing & firecaulking for units 624-630, 632, 640 & 641
  117. Mar 20, 2025

    Framing

    Partial Approval

    InspectorBret Eggers

    Framing for units 631-639
  118. Mar 12, 2025

    Framing

    Partial Approval

    InspectorBrian Stemwedel

    spoke with Brian re: unit finals next week. will schedule (2) inspectors starting March 17 and come up with a list to post on unit doors to track inspections per unit
  119. Mar 10, 2025

    Framing

    Cancelled Appointment

    InspectorMike Lockman

    Cancelled by Bryan @ Big D
  120. Mar 7, 2025

    Framing

    Completed in Future.

    InspectorBrian Stemwedel

    talked with Brian and Adam re: F/S dampers and duct detector locations.
  121. Mar 6, 2025

    Framing

    Completed in Future.

    InspectorBrian Stemwedel

    met with Adam to discuss ceiling condition over units on 5th floor. identified approved plans were not accurate (show detail R1, detail R2 is what is planned) informed them revised plans would need to be approved by Jake and Building insp. but the R2 detail appeared to comply with NFPA 13 for concealed space(s) exception. also verified standpipe locations (new) would be in a concealed space with a area of less than 10 sq. ft.. this will also require revised plans as a 2 hour shaft is being eliminated
  122. Feb 26, 2025

    Framing

    Partial Approval

    InspectorBrian Stemwedel

    looked at parapet on roof. attachment per approved details. also talked with Adam re: eliminating 2 hour shaft for standpipe chase and continuing rated floor through deadspace at every level and firestopping around penetrations following details per NFPA 13-16 Section 8.15.1.2.14 (no sprinkler required in comb. deadspace detail)
  123. Feb 21, 2025

    Radon Control

    Partial Approval

    InspectorBrian Stemwedel

    Rock under slab (units in garage area)
  124. Feb 20, 2025

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    little work ready for inspection
  125. Feb 12, 2025

    Framing

    Not Ready

    InspectorMike Lockman

    Contractors didn't have anything to look at today
  126. Feb 3, 2025

    Framing

    Not Ready

    InspectorMike Lockman

    No inspections on building permit today, only plumbing
  127. Jan 17, 2025

    Framing

    Completed in Future.

    InspectorBrian Stemwedel

    Met to go over changes to original plans and discussed control locations for showers in type B units. wil need to research more to answer questions
  128. Jan 16, 2025

    Framing

    Met for Consultation

    InspectorBret Eggers

    Met to discuss Type B unit plumbing requirements. The shower valve in some type B units is off set from the shower head. They wanted to install the valve in line with the shower head. I told them that it must comply with Minnesota 2020 Plumbing Code section 408.9
  129. Jan 15, 2025

    Floor Slab-Reinforcement

    Partial Approval

    InspectorBrian Stemwedel

    looked at floor slab section on LL apartment slab on grade
  130. Jan 13, 2025

    Radon Control

    Partial Approval

    InspectorMike Lockman

    Vapor barrier installed on 1st floor of the E wing from GL9.2 to GL10
  131. Dec 30, 2024

    Framing

    Not Ready

    InspectorMike Lockman

    Per Bryan @ Big D - Pause inspections the week of 12/30 - 1/3
  132. Dec 27, 2024

    Footing

    Not Ready

    InspectorBrian Stemwedel

    NO WORK READY FOR INSPECTION (HOLIDAY WEEK)
  133. Dec 23, 2024

    Framing

    Not Ready

    InspectorMike Lockman

    Nothing ready for inspection today
  134. Dec 20, 2024

    Fire Stopping

    Not Ready

    InspectorBrian Stemwedel

    contractor did not have anything to inspect
  135. Dec 16, 2024

    Framing

    Cancelled Appointment

    InspectorMike Lockman

    Cancelled by contractor
  136. Dec 13, 2024

    Footing

    Not Ready

    InspectorBrian Stemwedel

    sub zero temps. no work due to temp.
  137. Dec 12, 2024

    Framing

    Cancelled Appointment

    InspectorMike Lockman

    Cancelled due to sub-zero temps. Crews not on site
  138. Dec 5, 2024

    Footing

    Cancelled Appointment

    InspectorMike Lockman

  139. Dec 5, 2024

    Fire Stopping

    Completed in Future.

    InspectorBrian Stemwedel

    Met with contractor to discuss FS in airspace between IIIA and IIA parking garage
  140. Dec 4, 2024

    Floor Slab-Reinforcement

    Not Ready

    InspectorBrian Stemwedel

  141. Nov 25, 2024

    Rated Gypsum Assemblies

    Partial Approval

    InspectorMike Lockman

    First and second layer - Joints stagered 16" . for the mechanical and stair shafts on the 3rd floor/East wing
  142. Nov 22, 2024

    Rated Gypsum Assemblies

    Partial Approval

    InspectorMike Lockman

    Second gypsum layer on the S stairwell of the W wing. Second layer of gypsum on the S mechanical shaft of the W wing. Seems have been staggered approximately 18"
  143. Nov 18, 2024

    Footing

    Completed

    InspectorBret Eggers

  144. Nov 18, 2024

    Footing - Reinforcing

    Completed

    InspectorBret Eggers

  145. Nov 18, 2024

    Wall Reinforcing

    Completed

    InspectorBret Eggers

  146. Nov 13, 2024

    Floor Slab-Reinforcement

    Partial Approval

    InspectorMike Lockman

    Re-inforcement at thickend slab and shallow footings for Area B on the W side of the parking structure.
  147. Nov 12, 2024

    Rated Gypsum Assemblies

    Partial Approval

    InspectorMike Lockman

    3 Hr fire wall on E side of parking structure. SCWAP. Detail work at the corridor horizontal exit has not been completed at time of inspection.
  148. Nov 7, 2024

    Poured Wall

    Partial Approval

    InspectorBret Eggers

    GL 1 thru 2 Between D2 and F8
  149. Nov 7, 2024

    Radon Control

    Partial Approval

    InspectorBret Eggers

    UG East elevation of garage
  150. Nov 6, 2024

    Footing

    Partial Approval

    InspectorBret Eggers

    D thru F between D2 and F
  151. Nov 6, 2024

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBret Eggers

    Trash shoot 1st floor Rated assembly
  152. Nov 5, 2024

    Footing

    Cancelled Appointment

    InspectorBret Eggers

    Due to rain
  153. Nov 4, 2024

    Rated Gypsum Assemblies

    Partial Approval

    InspectorMike Lockman

    Layer 1 of gypsum for trash chute on SE corner of parking structure
  154. Nov 1, 2024

    Footing

    Cancelled Appointment

    InspectorMike Lockman

  155. Oct 31, 2024

    Footing

    Cancelled Appointment

    InspectorMike Lockman

    Cancelled by Brian @ Big D
  156. Oct 30, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Poured wall along GL-1 from B.3 to D.2
  157. Oct 30, 2024

    Wall Reinforcing

    Partial Approval

    InspectorMike Lockman

    Wall along GL-1 from B3 to D2
  158. Oct 29, 2024

    Rated Gypsum Assemblies

    Partial Approval

    InspectorMike Lockman

    Gypsum install. Second floor. Section A - East staircase. Minimum of 1 foot lap on gypsum panels seams
  159. Oct 29, 2024

    Floor Slab-Reinforcement

    Partial Approval

    InspectorMike Lockman

    Curb pour for half of 6th floor on parking structure.
  160. Oct 28, 2024

    Footing

    Partial Approval

    InspectorBret Eggers

    GL B 3 thru D.2
  161. Oct 28, 2024

    Rated Gypsum Assemblies

    Partial Approval

    InspectorBret Eggers

    Mechanical shaft second floor SE corner
  162. Oct 25, 2024

    Footing

    Completed

    InspectorMike Lockman

    Footing along Grid 1 from B.2 to C
  163. Oct 25, 2024

    Footing - Reinforcing

    Partial Approval

    InspectorMike Lockman

    Grid 1 from B.2 to C
  164. Oct 25, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Poured wall along Grid 1 from A to B.2
  165. Oct 25, 2024

    Wall Reinforcing

    Partial Approval

    InspectorMike Lockman

    Wall along Grid 1 from A to B.2
  166. Oct 23, 2024

    Footing

    Partial Approval

    InspectorBret Eggers

    gl1 from A1 to A3
  167. Oct 23, 2024

    Poured Wall

    Partial Approval

    InspectorBret Eggers

    GL D from 8 thru 8.8
  168. Oct 22, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorMike Lockman

    Final 5 concrete piers for W wing of Section A
  169. Oct 22, 2024

    Footing

    Partial Approval

    InspectorMike Lockman

    Column pads along C9 @ 8.0, 8.1, 8.2
  170. Oct 22, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Wall along GL-A between 3 & 5
  171. Oct 22, 2024

    Wall Reinforcing

    Partial Approval

    InspectorMike Lockman

    Wall along GL-A between 3 & 5
  172. Oct 21, 2024

    Footing

    Not Ready

    InspectorBret Eggers

  173. Oct 18, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    columns on C.4 from 8.5 to 8.9
  174. Oct 17, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    Spread footings for columns on C.4 from 8.5 to 8.9
  175. Oct 16, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    looked at footings and poured walls. updated plan set on jobsite (highlight) Plans are current with work completed
  176. Oct 10, 2024

    Footing - Reinforcing

    Partial Approval

    InspectorBret Eggers

    2 areas 1) GL 6.8 -and 7 Between A and B A between 7 and 4 2) C1 thru C at 8.9
  177. Oct 10, 2024

    Wall Reinforcing

    Partial Approval

    InspectorBret Eggers

    GL 9 between C1 and C4
  178. Oct 9, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorBret Eggers

    last 4 columns SW corner
  179. Oct 7, 2024

    Footing

    Not Ready

    InspectorMike Lockman

  180. Oct 4, 2024

    Footing - Reinforcing

    Partial Approval

    InspectorBret Eggers

    GL 8.4 - 9 and c - c.4
  181. Oct 3, 2024

    Footing

    Cancelled Appointment

    InspectorMike Lockman

    Cancelled by job sup
  182. Oct 3, 2024

    Footing - Reinforcing

    Cancelled Appointment

    InspectorMike Lockman

    Cancelled by job sup
  183. Oct 1, 2024

    Footing

    Cancelled Appointment

    InspectorBret Eggers

  184. Sep 30, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorMike Lockman

    4 Piers along GL-6.8 at intersections B, B1, B3 & B7
  185. Sep 30, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Wall along GL-C from 6.8 south to 8.1 Wall at SW corner of parking structure from GL-B to C
  186. Sep 27, 2024

    Footing

    Cancelled Appointment

    InspectorBrian Stemwedel

    additional footings not ready. will cast footings identified previously on Monday Sept 30
  187. Sep 26, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    8.1 to 6.8 on C line, B3 to C on 7
  188. Sep 25, 2024

    Footing

    Partial Approval

    InspectorBret Eggers

    GL B thru B7 and 5 thru 7.5 Brian to see completed reinforcement photos 9/26/24
  189. Sep 23, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorMike Lockman

    (3) Concrete piers on Grid Line C.1 at GL's 8.2 / 8.3 & 8.4
  190. Sep 20, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    Columns on B7 to E on 6.2
  191. Sep 20, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    footings on C line from 8.5 to 8.1
  192. Sep 19, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Poured wall from D/8 south to D/8.4. SCWAP
  193. Sep 19, 2024

    Footing

    Partial Approval

    InspectorMike Lockman

    (4) Pad footings. (1) at Grid Line D.9 between 6.2 and 6.8. (2) at Grid Line D.4 between 6.2 and 6.8. (1) at Grid Line D between 6.2 and 6.8.
  194. Sep 18, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    grid 8 from D to G.3
  195. Sep 17, 2024

    Footing

    Partial Approval

    InspectorMike Lockman

    (3) Column pad footings along GL-H.9 from 9.2 to G.9, (1) pad footing at GL-6.2 just E of GL-G.9. (2) pad footings just N of GL-6.8 at F.8 and g.3. (2) pad footings at F/4.7 & F/6.
  196. Sep 17, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorMike Lockman

    (4) Columns along GL-D from GL-8.1 to GL-8.4. SCWAP
  197. Sep 16, 2024

    Footing

    Partial Approval

    InspectorMike Lockman

    Strip footing along Grid Line D from GL-8 to GL-8.4 as well as 3 pad footing in same location. All are SCWAP
  198. Sep 16, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorMike Lockman

    (7) Concrete columns along Grid Line H.9 intersecting at 9.3 / 9.4 / 9.6 / 9.7 / 9.8 and halfway between 9.8 and 9.9
  199. Sep 16, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Poured wall running E to W just north of GL-3.7 on the E side of the parking structure and the wall running E to W just S of GL-4.2.
  200. Sep 13, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    marked on plans in job trailer
  201. Sep 12, 2024

    Footing

    Partial Approval

    InspectorMike Lockman

    Strip footing E side of parking structure just N of Grid Line 3.7 from GL-E to GL-G. Strip footing just E of Grid Line F from GL-3.7 to GL-4.2
  202. Sep 12, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorMike Lockman

    Columns at the following intercections... D.4/7.5, E/7.5, F.8/7.5, F.8/5 and F.8/4.5. All SCWAP
  203. Sep 12, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Anchor slabs along E wall per engineering for securing the E wall along Grid Line I at the following locations... GL9.3, from GL9.6 to 9.7, from GL9.8 to 9.9. Contractor (Brian) to provide engineering documents and SI reports to our office.
  204. Sep 11, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorBret Eggers

    4 columns (of 5) North side area A. Only remaining column the one furthest North
  205. Sep 11, 2024

    Poured Wall

    Partial Approval

    InspectorBret Eggers

    North Side Area A
  206. Sep 10, 2024

    Footing

    Completed

    InspectorBrian Stemwedel

    Remaining columns Grid I. Footings On Grid 8 (run east and west from D to G.3. marked on plans on site
  207. Sep 10, 2024

    Footing - Reinforcing

    Partial Approval

    InspectorBrian Stemwedel

    All footings through 9/4 (Verified via SI reports)
  208. Sep 9, 2024

    Footing

    Partial Approval

    InspectorBret Eggers

    Grid line 5 (turns North on Grid line G) on F8 4.1 thru 5 6 Piers GL J8 9.1 thru 9.7
  209. Sep 9, 2024

    Poured Wall

    Partial Approval

    InspectorBret Eggers

    GL5 G3 thru I
  210. Sep 6, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorMike Lockman

    (4) Piers along GL 9.9 & 10 from grid line H to grid line I and (1) pier at J.8 - 9.8 and (1) pier at I - 9.8. All SCWAP
  211. Sep 5, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Poured wall along GL - I from grid 9.2 north to grid 5. SCWAP
  212. Sep 5, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorMike Lockman

    Columns along GL - H from grid 9.7 north to grid 9.2. Total of 5 columns. SCWAP
  213. Sep 4, 2024

    Footing - Reinforcing

    Cancelled Appointment

    InspectorDan Anderson

  214. Sep 4, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    remaining footings on gridline I
  215. Sep 4, 2024

    Other - Concrete Piers

    Partial Approval

    InspectorBrian Stemwedel

    Columns along gridline I
  216. Sep 3, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    along gridline I and columns from 9.9 to 9.3
  217. Aug 30, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    Footings along gridline I and columns from 9.9 to 9.3. includes column pads
  218. Aug 29, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    Poured wall along gridline I and columns from 9.9 to 9.3
  219. Aug 28, 2024

    Footing

    Not Ready

    InspectorBrian Stemwedel

    work will be inspected on 8/28 prior to casting poured wall/ columns
  220. Aug 26, 2024

    Footing

    Partial Approval

    InspectorMike Lockman

    Piers/post footing at the following intersections. J8 @ 9.8 / J8 @9.7 and J8 @ 9.6. SCWAP w/ reinforcement
  221. Aug 26, 2024

    Footing - Reinforcing

    Partial Approval

    InspectorMike Lockman

    See footing notes for location details.
  222. Aug 23, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    Remaining poured wall S side Gridlines 10-9.9 from H to I
  223. Aug 23, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    Spread footings S.E. corner along gridline I from 9.9 to column just N of 9.8. includes column and area NW of 9.8 on J.8
  224. Aug 22, 2024

    Footing

    Cancelled Appointment

    InspectorBrian Stemwedel

    no work ready
  225. Aug 21, 2024

    Poured Wall

    Partial Approval

    InspectorBret Eggers

    G9 and 9.55 - 10 4 columns on grid line 9.9 thru 10
  226. Aug 20, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    Spread footings on east apt building's south side from H to I on gridline(s) 10-9.9
  227. Aug 19, 2024

    Footing

    Partial Approval

    InspectorMike Lockman

    Area A footings along Grild Line H from GL7.5 to GL10. SCWAP. Highlighted and signed on job site plans.
  228. Aug 19, 2024

    Footing - Reinforcing

    Partial Approval

    InspectorMike Lockman

  229. Aug 14, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    remaining footings for parking structure. all footings for parking structure complete
  230. Aug 13, 2024

    Wall Reinforcing

    Partial Approval

    InspectorBret Eggers

    Elevator pit and B4 - B6 and stairway wall
  231. Aug 12, 2024

    Footing

    Partial Approval

    InspectorBret Eggers

    Grid line E and 3-5
  232. Aug 12, 2024

    Poured Wall

    Partial Approval

    InspectorBret Eggers

    Grid line B and 3-6
  233. Aug 9, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    Elevator pit floor. noted (3) 4" PVC drains. and reinforcement ISCWAP. Also remaining spread footings on east side of parking structure. highlighted plans on site
  234. Aug 8, 2024

    Footing

    Not Ready

    InspectorBrian Stemwedel

    no additional work ready at time of inspection
  235. Aug 7, 2024

    Poured Wall

    Not Ready

    InspectorBrian Stemwedel

    contractor did not have additional work ready. was casting poured wall approved on 8/6
  236. Aug 6, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    Along grid 4 from b to c9
  237. Aug 5, 2024

    Footing

    Cancelled Appointment

    InspectorBret Eggers

    Due to rain
  238. Aug 2, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    Center spread footings on 4 from C to D2 ISCWAP
  239. Aug 2, 2024

    Footing - Reinforcing

    Partial Approval

    InspectorBrian Stemwedel

    Reinforcing for all footings inspected through 7/29/24 (verified via SI daily reports)
  240. Aug 1, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    Center footings parking structure. Along grid 4 from B to C ISCWAP
  241. Jul 31, 2024

    Footing

    Partial Approval

    InspectorBret Eggers

    lines B = B3 and 4 -5
  242. Jul 31, 2024

    Poured Wall

    Partial Approval

    InspectorBret Eggers

    Beteen B - B3 north wall
  243. Jul 29, 2024

    Footing

    Partial Approval

    InspectorMike Lockman

    Grid line 3 from C.4 to E. Grid line E from B to 3.5 Reinforcement SCWAP. On site with B Eggers.
  244. Jul 29, 2024

    Foundation Waterproofing

    Partial Approval

    InspectorMike Lockman

    60 Mil adhesive applied WP on Grid B from 3 to 4 (center of ramp) and Grid 3 from B to C. Water proofing install 6 feet above footing and 1 foot onto top of footing. Remainder of wall to be completed in future after some backfilling is completed..
  245. Jul 29, 2024

    Poured Wall

    Partial Approval

    InspectorMike Lockman

    Grid 3 from C to C.4 Reinforcement is SCWAP
  246. Jul 25, 2024

    Poured Wall

    Partial Approval

    InspectorBrian Stemwedel

    Contractor had to add chairs at top of wall (clearance to face) approved poured wass section(s) Grid B from 3 to 3.3 and Grid 3 from B to B.3
  247. Jul 23, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    Continuing from NW corner- South on B from 3.3 to 4.7, East on 3 from B.3 to C.4
  248. Jul 19, 2024

    Footing

    Partial Approval

    InspectorBrian Stemwedel

    far NW corner of parking structure. Grid B from 3 to 3.3, Grid 3 from B to B.3