Building
1300 Hidden Lakes Pkwy, Golden Valley
Remodel/Alteration, HOSPITAL/Tenant Remodel/Alteration,
- Mar 31, 2026
Framing
Need CorrectionInspectorDan Anderson
Hallway alcoves near rooms 230,231,232. Sidewalls need to be framed to bottom of deck to complete smoke barrier in corridor.
- Mar 31, 2026
Framing-Above Ceiling
Partial ApprovalInspectorDan Anderson
Wound Care, CR200 clean room, S201 Soil linen, and TH200 Therapy Room above ceiling completed.
- Feb 6, 2026
Final
Partial ApprovalInspectorDan Anderson
Rooms completed: 234, 236, 238, Staff Lounge 201.
- Jan 26, 2026
Framing-Above Ceiling
Partial ApprovalInspectorDan Anderson
Above ceiling in rooms: Private room 234, 236, 238, Staff Lounge 201,
- Jan 26, 2026
Final
Partial ApprovalInspectorDan Anderson
Nurse office areas completed: 206,205, Waiting room 200, Bathroom 200T, 204,203
- Jan 5, 2026
Framing
Partial ApprovalInspectorBret Eggers
Above ceiling rooms 200, 202, 204, 205 and 206. With Dan Anderson.
- Dec 9, 2025
Final
Partial ApprovalInspectorDan Anderson
Both items from 12/8/25 have been corrected.
- Dec 8, 2025
Final
Need CorrectionInspectorDan Anderson
-Missing exit signage at the end of Corridor 207. -Missing exit sign at hallway smoke control door, Corridor 205 (will be installed when new smoke doors get replaced)
- Dec 1, 2025
Framing-Above Ceiling
Partial ApprovalInspectorDan Anderson
Rooms 244, 243, 242, 241, 240, Storage riin ST201, Linen room 202, 207, 237, 235, 233, Corridor C207, Partial C206
- Nov 14, 2025
Final
Partial ApprovalInspectorDan Anderson
Okay to occupy HR area and Main entrance and main vestibule area.
- Nov 6, 2025
Framing-Above Ceiling
Partial ApprovalInspectorDan Anderson
above ceiling main floor entry area. Waiting room 184, Interview room 193, Bereavement room 191 Vestibule E183, Reception 185, and Corridor 186
- Nov 3, 2025
Framing-Above Ceiling
Need CorrectionInspectorDan Anderson
HR area all VAV lines need to be labeled above ceiling
- Nov 3, 2025
Framing
Partial ApprovalInspectorDan Anderson
Correction of smoke partition wall from 10/22/25 completed. framed to deck, penetrations sealed from one side and wall labeled "SMOKE PARTITION""
- Oct 22, 2025
Framing
Need CorrectionInspectorDan Anderson
newly created corridor wall needs to be a smoke parttion and walls need to go from floor to bottom of the deck and sealed. Smoke dampers are not required in ducts but any air transfer openings need to have one. Top of wall and all penetrations need to be sealed.
- Oct 15, 2025
Framing
Not ReadyInspectorDan Anderson
1st floor main entrance, east smoke wall soffit around duct not completed, interior bulk head for interior aluminum clad window not completed.
- Oct 6, 2025
Framing
Partial ApprovalInspectorDan Anderson
2nd Floor North Alcoves: Above ceiling smoked sealed.along corridor side. 241,243,244,242,240, St.201,202,207,237,235,233
- Sep 24, 2025
Framing
Partial ApprovalInspectorDan Anderson
SE corner of hospital, east of canopy. Framing of areas 179 B, 179 C, 179 D, 179 G 179 H, 179 J, 179 N, 179 M, 179 L, 179 K, Open Office area 179
- Sep 5, 2025
Final
Partial ApprovalInspectorDan Anderson
Rooms 245,246,247,248,249,250, Corridor C208 and day room
- Aug 28, 2025
Framing-Above Ceiling
Partial ApprovalInspectorBrian Stemwedel
Rooms E201 (electrical), 245, 246, 247, 248, 249, 250, and C208 (corridor) no combustibles above grid (plenum) and corridor penetrations smoke sealed as required
- Jul 15, 2025
Special Inspections
Partial ApprovalInspectorBrian Stemwedel
Firestopping in I-2 Occupancy. report archived into City records
- Jul 11, 2025
Final
Partial ApprovalInspectorBrian Stemwedel
care rooms 258, 260, 262, and 265
- Jul 11, 2025
Fire Stopping
CompletedInspectorBrian Stemwedel
Where required in rated assemblies. SI inspection report required prior to final approval
- Jul 11, 2025
Insulation
CompletedInspectorBrian Stemwedel
for sound where required
- Jun 25, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
contractor called for a site visit to check on progress. all work ISCWAP to date. also met with John (Mech. contractor) confirmed a smoke damper was not needed in electrical room (Incidental use) which is sprinklered and HVAC is ducted all the way to air handler. (DLI Plan Review Policy PR-01 condition 3)
- Jun 20, 2025
Framing-Above Ceiling
Partial ApprovalInspectorDan Anderson
Rooms 258, 260,262, 265. Includes hallway smoke barrier
Show 9 earlier inspections
- May 28, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
in loading dock area. rated wall 127A. care suite rooms 262, 260, and 258- ISCWAP Conversion of room 265 (materials handling) to care room
- May 13, 2025
Final
Partial ApprovalInspectorBrian Stemwedel
Loading dock- RM 125B/ 125C/ 125D J202, M202, ST203, MM265
- May 13, 2025
Fire Stopping
Partial ApprovalInspectorBrian Stemwedel
Loading dock- RM 125B/ 125C/ 125D and ST 203
- May 6, 2025
Framing-Above Ceiling
Partial ApprovalInspectorBrian Stemwedel
In loading dock- Rm 125B/125C/125E 2nd floor MM265, ST203, N202, J202
- Apr 17, 2025
Framing
Partial ApprovalInspectorBrian Stemwedel
Rated (2) hour assembly in loading dock area and (1) hour assembly is MM201. also framing N202 (removal of dumbwaiter)
- Mar 14, 2025
Framing-Above Ceiling
Partial ApprovalInspectorBrian Stemwedel
Rm's 251, 253, 255, 257, 259, 261 and public restroom and room 202(isolation)
- Mar 14, 2025
Final
Partial ApprovalInspectorBrian Stemwedel
Rm's 251, 253, 255, 257, 259, 261 and public restroom and room 202(isolation) This is also a SI inspection. so prior to final approval for this permit. SI reports are required
- Mar 14, 2025
Special Inspections
Completed in Future.InspectorBrian Stemwedel
as identified on SI agreement. includes firestopping in I-2 Occ.
- Dec 26, 2024
Framing
Partial ApprovalInspectorBrian Stemwedel
Rm's 251, 253, 255, 257, 259, 261
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.