Permit / Golden Valley← Search
#GV128317Building
1045 Tyrol Tr, Golden Valley
IssuedOct 20, 2025
StatusUnknown
Value$250,000
Inspections8
Scope of work
Remodel/Alteration, First floor remodel includes new kitchen, mudroom/bathroom addition and dining room addition.
Location context
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$1,273.03
Total paid$1,273.03
Timeline
ApprovedOct 7, 2025
IssuedOct 20, 2025
Inspection record
Inspections8
Passed7
Failed0
- Feb 6, 2026
Framing
CompletedInspectorGarrett Heins
Point load carried to foundation with approved methods.
- Feb 6, 2026
Insulation
CompletedInspectorGarrett Heins
Closed cell spray foam used on all exterior walls, meeting or exceeding R value requirements. Fire blocking and draft stopping performed where required, fiberglass insulation installed in 2nd level floor joists for sound transmission.
- Jan 27, 2026
Framing
Need CorrectionInspectorGarrett Heins
Point load blocking for steel beam opposite of sliding patio door required. Engineering and HVAC alteration possible. Contractor approved to continue project as long as continued load pathway remains visible in basement. All other framing is substantially compliant with approved plan and engineering provided.
- Jan 27, 2026
Submit Pictures of House Wrap
Partial ApprovalInspectorGarrett Heins
House wrap and flashing of new windows on additions and anywhere siding was removed is approved.
- Nov 6, 2025
Foundation Waterproofing
CompletedInspectorBret Eggers
- Nov 6, 2025
Foundation Insulation
CompletedInspectorBret Eggers
R10 foam board with slip sheet
- Nov 4, 2025
Wall Reinforcing
CompletedInspectorMike Lockman
Reinforcement for CMU wall at mud room addition. SCWAP
- Oct 31, 2025
Footing
CompletedInspectorMike Lockman
20 x 10 strip footing. SCWAP w/ 2 #4 H bar. Pinned into existing footing