Location context
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$342.71
Total paid$342.71
Timeline
ApprovedNov 14, 2025
IssuedNov 17, 2025
Inspection record
Inspections3
Passed3
Failed0
- Dec 2, 2025
Other - Core Fill
CompletedInspectorGarrett Heins
Core filled with reinforcement #4 bar in corners, even backfill. Additional Simpson strong tie EPB wet set for future post connections.
- Nov 25, 2025
Footing
CompletedInspectorMike Lockman
10 x 20 Strip footings installed in lieu of the 8 x 20 footings shown on plans
- Nov 25, 2025
Footing - Reinforcing
CompletedInspectorMike Lockman
2 Horizontal bar reinforcement in lower 1/3 of footing. Pinned into existing foundation. SCWAP