Permit / Golden Valley← Search
#GV129021Building
124 Paisley La, Golden Valley
IssuedDec 23, 2025
StatusUnknown
Value$102,000
Inspections11
Scope of work
Addition, Add mud/office addition on rear of exist. garage •Add garage stall and remodel MBR suite
Location context
Parcel3311821330041
Coordinates44.97971, -93.35851
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$695.83
Total paid$695.83
Timeline
ApprovedDec 23, 2025
IssuedDec 23, 2025
Inspection record
Inspections11
Passed9
Failed0
- Feb 19, 2026
Framing
CompletedInspectorGarrett Heins
Signed copy of engineering for entry wall received, all items approved.
- Feb 18, 2026
Framing
Partial ApprovalInspectorGarrett Heins
Portal framing correction completed. Outstanding item left is signed copy of engineer repair for bearing wall in front entry. All other items approved.
- Feb 17, 2026
Insulation
Partial ApprovalInspectorMike Lockman
Un-faced FG batt insulation R13 installed in existing 2x4 exterior walls of the bathroom w/ VP and CCSF in rim joist. Un-Faced FG batt insulation R20 installed in the exterior walls of the new addition w/ VB. VB installed on ceiling joists. Cellulose to be installed at after drywall installation
- Feb 17, 2026
Framing
Need CorrectionInspectorMike Lockman
Non-compliant portal straps installed @ header location. Allowed contractor to take photos to review at future inspection.
- Feb 11, 2026
Framing
Partial ApprovalInspectorGarrett Heins
Pending engineers report for interior bearing wall bracing.
- Feb 4, 2026
Framing
Need CorrectionInspectorGarrett Heins
Engineering required for bearing wall at entry of existing space. Wall exceeds notching allowed. SEE R602.6 Caught at HVAC R/I. Contractor to provide report at framing inspection.
- Jan 29, 2026
Insulation - Under Slab
CompletedInspectorGarrett Heins
Dupont 2" XPS insulation with radon 6 mil poly installed in new conditioned space. Garage unconditioned space verified radon control.
- Jan 14, 2026
Other-Slab On-Grade Perimeter Insulation
CompletedInspectorGarrett Heins
XPS 3" foam verified entire foundation structure. Water proofing on east wall for swell at grade.
- Jan 13, 2026
Poured Wall
CompletedInspectorGarrett Heins
Revised copy of plans dated 12/5/2025 received.
- Jan 9, 2026
Poured Wall
Partial ApprovalInspectorGarrett Heins
Foundation changed from CMU to poured wall, revised plans on site at time of inspection. Require set of revised plans showing reinforcements and additional lift on east wall before final approval.
- Jan 8, 2026
Footing - Reinforcing
CompletedInspectorBret Eggers
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.