#WB090527

Building

2513 Jansen Ave, White Bear Lake

IssuedOct 1, 2024
StatusUnknown
Value$301,158
Inspections14
Scope of work

New, NEW TOWNHOME (2 OF 4)

Fees & payments
Total fees$4,867.41
Timeline
ApprovedOct 1, 2024
IssuedOct 1, 2024
Inspection record
Inspections14
Passed12
Failed1
  1. Apr 2, 2026

    Final Building Inspection

    Partial Final

    InspectorBEN EGGAN

    Final approved pending: 1. Pour curb and restore boulevard landscaping 2. Provide Final Inspection Summary Report from Braun 3. Obtain rain garden approval from Connie Taillon 4. Install Handicap parking sign 5. Caulk all AC lines at exterior of the building 6. Repair and add flashing to fully cover foundation insulation
  2. Sep 30, 2025

    Wall Bracing (Interior)

    Approved

    InspectorBEN EGGAN

  3. Sep 19, 2025

    Insulation

    Approved

    InspectorBEN EGGAN

  4. Sep 4, 2025

    Framing

    Failed

    InspectorBEN EGGAN

    Rough framing fialed. Correct the following: 1. Obtain fireplace permits and call for fireplace rogh in inspections. 2. Provide rated electrical box listing information. 3. Add lateral bracing and t-Bracing at roof trusses as required by the roof truss specifications. 4. Add drywall at drop soffit along the common fire wall. 5. Lower the leower level bedroom egress window to a maximum of 44" above the finished floor. 6. Add A35 clips at upper level top p[late per engineered design. 7. Provide your approved plan set on the job site. Correct and recall inspection
  5. Aug 5, 2025

    Lath

    Approved

    InspectorBEN EGGAN

  6. Jul 11, 2025

    House Wrap (Email Pictures or On-Site Inspection)

    Approved

    InspectorBEN EGGAN

  7. Jun 12, 2025

    Floor Poly

    Approved

    InspectorWILLY WEICHT

  8. Jun 9, 2025

    Radon

    Partial Pass

    InspectorWILLY WEICHT

    4" PVC pipe and 4" PVC pipe with sock in ground. Rock was already covering pipe and pictures were provided. None of above ground was completed at this inspection.
  9. Mar 11, 2025

    Wall Bracing (Pre-Housewrap)

    Approved

    InspectorWILLY WEICHT

  10. Dec 17, 2024

    Rough Drain Tile

    Approved

    InspectorWILLY WEICHT

  11. Dec 16, 2024

    Foundation Pre-Backfill

    Approved

    InspectorWILLY WEICHT

  12. Dec 16, 2024

    Water Proofing

    Approved

    InspectorWILLY WEICHT

  13. Dec 10, 2024

    Foundation Pre-Pour

    Approved

    InspectorWILLY WEICHT

  14. Nov 18, 2024

    Footing

    Approved

    InspectorWILLY WEICHT

    Will send compaction report by Braun