Permit / White Bear Lake← Search
#WB090525Building
2509 Jansen Ave, White Bear Lake
IssuedOct 1, 2024
StatusUnknown
Value$301,158
Inspections14
Scope of work
New, NEW TOWNHOME (5 of 5)
Location context
Fees & payments
Total fees$4,867.41
Inspection record
Inspections14
Passed13
Failed0
- Apr 2, 2026
Final Building Inspection
Partial FinalInspectorBEN EGGAN
Final approved pending: 1. Pour curb and restore boulevard landscaping 2. Provide Final Inspection Summary Report from Braun 3. Obtain rain garden approval from Connie Taillon 4. Install Handicap parking sign 5. Caulk all AC lines at exterior of the building 6. Repair and add flashing to fully cover foundation insulation
- Oct 30, 2025
Shear Wall
ApprovedInspectorBEN EGGAN
- Sep 30, 2025
Insulation
ApprovedInspectorBEN EGGAN
- Sep 8, 2025
Framing
ApprovedInspectorBEN EGGAN
- Aug 5, 2025
Lath
ApprovedInspectorBEN EGGAN
- Jul 11, 2025
House Wrap (Email Pictures or On-Site Inspection)
ApprovedInspectorBEN EGGAN
- Jun 12, 2025
Floor Poly
ApprovedInspectorWILLY WEICHT
- Jun 9, 2025
Radon
Partial PassInspectorWILLY WEICHT
4" PVC pipe and 4" PVC pipe with sock in ground. Rock was already covering pipe and pictures were provided. None of above ground was completed at this inspection.
- May 30, 2025
Wall Bracing (Pre-Housewrap)
ApprovedInspectorWILLY WEICHT
- Dec 17, 2024
Rough Drain Tile
ApprovedInspectorWILLY WEICHT
- Dec 16, 2024
Foundation Pre-Backfill
ApprovedInspectorWILLY WEICHT
- Dec 16, 2024
Water Proofing
ApprovedInspectorWILLY WEICHT
- Dec 3, 2024
Foundation Pre-Pour
ApprovedInspectorWILLY WEICHT
Adding additional #4 rebar to have 18" or 24" each way per engineering. Blankets were on site to cover after wall is poured.
- Nov 15, 2024
Footing
ApprovedInspectorWILLY WEICHT
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.