Building
8480 Mccoll Dr, Savage
New, Detached
- Dec 27, 2024
Fireplace Final
ApprovedInspectorPhillip Skluzacek
- Dec 27, 2024
Mechanical Final
ApprovedInspectorPhillip Skluzacek
- Dec 27, 2024
Temporary Certificate of Occupancy
ApprovedInspectorPhillip Skluzacek
- Dec 27, 2024
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
- Dec 11, 2024
Plumbing Final
ApprovedInspectorJason Wolf
- Oct 1, 2024
Insulation
ApprovedInspectorPhillip Skluzacek
- Oct 1, 2024
Lath
ApprovedInspectorPhillip Skluzacek
- Sep 6, 2024
Mechanical Rough-In
ApprovedInspectorPhillip Skluzacek
- Sep 6, 2024
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
- Sep 6, 2024
Insulation
Partial ApprovalInspectorPhillip Skluzacek
Ceiling being spray foamed, need verification of ceiling having a vapor barrier,
- Sep 3, 2024
Sheathing
ApprovedInspectorPhillip Skluzacek
- Sep 3, 2024
Plumbing Rough-In
ApprovedInspectorPhillip Skluzacek
- Sep 3, 2024
Framing
ApprovedInspectorPhillip Skluzacek
- Sep 3, 2024
Fireplace Rough-In
ApprovedInspectorPhillip Skluzacek
- Sep 3, 2024
Gas Line Air Test
ApprovedInspectorPhillip Skluzacek
- Sep 3, 2024
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
- Sep 3, 2024
Mechanical Rough-In
Partial ApprovalInspectorPhillip Skluzacek
Need to seal Duct work in Attic
- Aug 15, 2024
In Floor Heat
ApprovedInspectorPhillip Skluzacek
Basement
- Aug 15, 2024
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
- Aug 14, 2024
Radon Mitigation System/Poly
ApprovedInspectorDavid Hauer
Basement
- Aug 14, 2024
Erosion Control
Erosion Control ApprovedInspectorDavid Hauer
- Aug 13, 2024
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
- Aug 13, 2024
Plumbing Rough-In
Partial ApprovalInspectorPhillip Skluzacek
Basement not done yet
- Jun 25, 2024
In Floor Heat
ApprovedInspectorPhillip Skluzacek
- Jun 25, 2024
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
Show 9 earlier inspections
- Jun 24, 2024
Radon Mitigation System/Poly
Partial ApprovalInspectorDavid Hauer
Main level. Basement not being completed until later date.
- Jun 12, 2024
Plumbing Underground
ApprovedInspectorDavid Hauer
- Jun 12, 2024
Erosion Control
Erosion Control ApprovedInspectorDavid Hauer
- Jun 6, 2024
Foundation
ApprovedInspectorJason Wolf
- Jun 6, 2024
Erosion Control
Erosion Control ApprovedInspectorJason Wolf
- May 31, 2024
Poured Wall
ApprovedInspectorJason Wolf
- May 31, 2024
Erosion Control
Erosion Control ApprovedInspectorJason Wolf
- May 29, 2024
Footing
ApprovedInspectorJason Wolf
- May 29, 2024
Erosion Control
Erosion Control ApprovedInspectorJason Wolf
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.