Building
7749 146 Ter, Savage
New, Detached
- Dec 1, 2025
Turf and Landscaping
Call For ReinspectionInspectorIgor Khomyakov
Snow on the ground does not allow for physical verification of turf condition on Lot 8 and stabilization on vacant lot.
- Dec 1, 2025
As-built/grading
Not ApprovedInspectorIgor Khomyakov
Survey received 11/26/25. Snow on the ground does not allow for physical verification of grades. All notes based on Survey Existing Spot Elevations. 1. Flat swales at East and West property lines (raging from 0.3% to 1.2%) Min 2% required to drain over turf.
- Nov 25, 2025
Mechanical Final
ApprovedInspectorPhillip Skluzacek
- Nov 25, 2025
Temporary Certificate of Occupancy
ApprovedInspectorPhillip Skluzacek
- Nov 25, 2025
Framing
ApprovedInspectorPhillip Skluzacek
- Nov 25, 2025
Lath
Inspecton Not RequiredInspectorPhillip Skluzacek
- Nov 24, 2025
Plumbing Final
ApprovedInspectorPhillip Skluzacek
- Nov 24, 2025
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
- Oct 6, 2025
Insulation
ApprovedInspectorJason Wolf
- Oct 6, 2025
Erosion Control
Erosion Control ApprovedInspectorJason Wolf
- Oct 2, 2025
Mechanical Rough-In
ApprovedInspectorJason Wolf
- Oct 2, 2025
Gas Line Air Test
ApprovedInspectorJason Wolf
Main/Range/FP
- Oct 2, 2025
Sheathing
ApprovedInspectorJason Wolf
- Oct 2, 2025
Framing
Call For ReinspectionInspectorJason Wolf
Add portal frame straps on front door
- Oct 2, 2025
Erosion Control
Erosion Control ApprovedInspectorJason Wolf
- Oct 1, 2025
Plumbing Rough-In
ApprovedInspectorJason Wolf
- Sep 15, 2025
Erosion Control
Erosion Control ApprovedInspectorDavid Hauer
- Sep 11, 2025
Erosion Control
Not ApprovedInspectorDavid Hauer
1. Erosion control fencing or bio logs must be installed at street and sidewalk. 2. Re- install all perimeter control. 3. Street and side walk must be kept clean. 4. All areas a curb that are disturbed must have erosion control. 5. Remove all building material, biffy, and other items from boulevard and right of way. 6. All track out from sites and out lots where materials are currently sitting must also stay clean on street, sidewalk, and have erosion control in place. 7. Install erosion control around stock piles- dirt. Correct by September 15th at 3 p.m. or stop work order issued. No inspections until corrected.
- Sep 5, 2025
In Floor Heat
ApprovedInspectorPhillip Skluzacek
- Sep 5, 2025
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
- Sep 4, 2025
Plumbing Underground
ApprovedInspectorJason Wolf
- Sep 4, 2025
Radon Mitigation System/Poly
ApprovedInspectorJason Wolf
- Sep 4, 2025
Erosion Control
Erosion Control ApprovedInspectorJason Wolf
- Aug 28, 2025
Foundation
ApprovedInspectorJason Wolf
- Aug 25, 2025
Poured Wall
ApprovedInspectorPhillip Skluzacek
Show 3 earlier inspections
- Aug 25, 2025
Erosion Control
Erosion Control ApprovedInspectorPhillip Skluzacek
- Aug 21, 2025
Footing
ApprovedInspectorJason Wolf
- Aug 21, 2025
Erosion Control
Erosion Control ApprovedInspectorJason Wolf
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.