PULLFIRST[THE RECORD]
Permit / White Bear Lake← Search
#WB090512

Building

2501 Jansen Ave, White Bear Lake

IssuedOct 1, 2024
StatusUnknown
Value$301,158
Inspections20
Scope of work

New, NEW TOWNHOME (1 of 5)

Fees & payments
Total fees$4,867.41
Timeline
ApprovedOct 1, 2024
IssuedOct 1, 2024
Inspection record
Inspections20
Passed15
Failed4
  1. Apr 2, 2026

    Final Building Inspection

    Approved

    InspectorBEN EGGAN

  2. Oct 30, 2025

    Shear Wall

    Approved

    InspectorBEN EGGAN

  3. Oct 16, 2025

    Insulation

    Approved

    InspectorBEN EGGAN

  4. Sep 8, 2025

    Framing

    Approved

    InspectorBEN EGGAN

  5. Aug 17, 2025

    Erosion Control

    Failed

    InspectorBEN EGGAN

    On site Sunday August 17th and found that the erosion control largely held however there is some slit on the sidewalk and around the storm drain at the northwest corner of the site. I photographed the condition and forwarded to the developer and asked that he investigate the breach and make adjustments as needed to prevent further erosion. Ben
  6. Aug 13, 2025

    Erosion Control

    Failed

    InspectorBEN EGGAN

    Erosion control was recently re-installed. Overall the installation is well done. There are some areas that need ground cover, some silt fence that has been knocked down and not all of the rain gutters have been piped to the drainage basin. I called Ryan, sent pictures of what needs work and told him to shore up the site because we are expecting multiple days of rain. Ben
  7. Aug 5, 2025

    Lath

    Approved

    InspectorBEN EGGAN

  8. Jul 11, 2025

    House Wrap (Email Pictures or On-Site Inspection)

    Approved

    InspectorBEN EGGAN

  9. Jun 12, 2025

    Floor Poly

    Approved

    InspectorWILLY WEICHT

  10. Jun 9, 2025

    Radon

    Partial Pass

    InspectorWILLY WEICHT

    4" PVC pipe and 4" PVC pipe with sock in ground. Rock was already covering pipe and pictures were provided. None of above ground was completed at this inspection.
  11. May 30, 2025

    Wall Bracing (Pre-Housewrap)

    Approved

    InspectorWILLY WEICHT

  12. Mar 26, 2025

    Erosion Control

    Approved

    InspectorBEN EGGAN

    All erosion control correction have been completed. This site is in compliance and approved. Ben
  13. Mar 19, 2025

    Erosion Control

    Failed

    InspectorBEN EGGAN

    Emailed the contractor photographs of the areas that need correction.I let him know we will re-inspected erosion control again next Wednesday. Ben
  14. Mar 12, 2025

    Erosion Control

    Failed

    InspectorBEN EGGAN

    The following needs to be completed to protect your site from unwanted erosion. 1. Re-establish a 50’ long rock construction entrance. 2.Repair degraded and down silt fencing around the perimeter of the project. (south, west, north, and east sides of the project) 3. Sweep up dirt and sediment tracked out onto Jansen street.
  15. Dec 17, 2024

    Rough Drain Tile

    Approved

    InspectorWILLY WEICHT

  16. Dec 16, 2024

    Foundation Pre-Backfill

    Approved

    InspectorWILLY WEICHT

  17. Dec 16, 2024

    Water Proofing

    Approved

    InspectorWILLY WEICHT

  18. Dec 3, 2024

    Foundation Pre-Pour

    Approved

    InspectorWILLY WEICHT

    Adding additional #4 rebar to have 18" or 24" each way per engineering. Blankets were on site to cover after wall is poured.
  19. Dec 3, 2024

    Erosion Control

    Misc. Notes

    InspectorWILLY WEICHT

    Rock entrance, silt fence and bio logs in place during inspection.
  20. Nov 15, 2024

    Footing

    Approved

    InspectorWILLY WEICHT

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.