Permit / Crystal← Search
#CY089612

Building

7010 Dudley Ave N, Crystal

IssuedApr 7, 2025
StatusUnknown
Value$25,000
Inspections16
Scope of work

Alteration, Addition to back of house with new deck

Location context
Parcel0511821130107
Coordinates45.05937, -93.36904
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$683.33
Inspection record
Inspections16
Passed9
Failed7
  1. Jul 25, 2025

    Final

    Satisfactory as completed

    InspectorJoe Tomasetti

    Per home owner ok to final
  2. Jul 21, 2025

    Final

    Fails to comply

    InspectorJoe Tomasetti

    Use 2 X 2 X 10 not 2 X 2 X 8 Beam , add footing to center of beam call for inspection .
  3. Jul 15, 2025

    Final

    Fails to comply

    InspectorJoe Tomasetti

    ADD 2 X 2 X 10 BEAM TO CENTER OF DECK OVER NEW FOOTINGS INSTALLED.
  4. Jul 9, 2025

    Final

    Fails to comply

    InspectorJoe Tomasetti

    ADD 2 X 2 X 10 beam to center of deck over footings add center footing . Close stair risers
  5. Jun 26, 2025

    Framing

    Fails to comply

    InspectorJoe Tomasetti

    Add beam to center of deck 2 X 10 will not span 16 feet. Add 2 X 2 X 10 to beam by house with center footing with 2 X 2 X 10 beam .
  6. Jun 10, 2025

    Framing

    Fails to comply

    InspectorJoe Tomasetti

    Deck approved for 10 X 12 deck only .Stop all work until zoning approves deck
  7. May 20, 2025

    Insulation

    Satisfactory as completed

    InspectorJoe Tomasetti

    R - 13 with 4 mil poly
  8. May 16, 2025

    Insulation

    Fails to comply

    InspectorJeni Taylor

    Holes and gaps in paper backed insulation on walls.
  9. Apr 29, 2025

    Insulation

    Partial approval

    InspectorJeni Taylor

    R30 in floor
  10. Apr 29, 2025

    Framing

    Partial approval

    InspectorJeni Taylor

    2x4 studs 16 inch on center 2x10 floor joists 3 - 2x10 beams
  11. Apr 29, 2025

    Roofing - Ice Barrier

    Satisfactory as completed

    InspectorJeni Taylor

    2 rows of ice and water barrier
  12. Apr 25, 2025

    Framing

    Partial approval

    InspectorJoe Tomasetti

    2 X 11 7/8 LVL Add mechanical fasteners to rafters on ridge beam.
  13. Apr 24, 2025

    Framing

    Partial approval

    InspectorJoe Tomasetti

    Per pictures and conversation with contractor ledger locks @ 8 inch o/c 2 x 10 joist 16 inch o/c
  14. Apr 24, 2025

    Footing

    Satisfactory as completed

    InspectorJoe Tomasetti

    4 X 42 inch x 24 inch @ base for deck footings
  15. Apr 14, 2025

    Footing

    Satisfactory as completed

    InspectorJoe Tomasetti

    8 inch x 23 wide at base 42 inch deep
  16. Apr 11, 2025

    Footing

    Fails to comply

    InspectorJoe Tomasetti

    Plan shows 23 inch X 8 inch footing not 16 tube.

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.