PULLFIRST[THE RECORD]
Permit / Minnetonka← Search
#MI282804

Building

12601 Ridgedale Dr, Minnetonka

IssuedJul 11, 2024
StatusUnknown
Value$763,000
Inspections10
Scope of work

Maintenance/Repair, Fire Damper replacement

Location context
Parcel0211722330004
Coordinates44.96559, -93.43845
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedJun 25, 2024
IssuedJul 11, 2024
Inspection record
Inspections10
Passed3
Failed0
  1. Sep 26, 2025

    Commercial Framing

    APPROVED

    InspectorDale Gronberg

    * THE FRAMING HAS BEEN COMPLETED IN MECHANICAL ROOM AT SHAFT * I was on site for mechanical. All corrections from previous inspections shall be verified (above ceiling at 2nd floor elevator lobby)
  2. Jan 16, 2025

    Commercial Framing

    PARTIAL APPROVAL

    InspectorKevin McDermott

    3rd floor penthouse knee walls framing and drywall @ new vertical damper area.
  3. Dec 13, 2024

    Commercial Framing

    SEE COMMENTS

    InspectorKevin McDermott

    N/A Jake was looking for damper inspections. I don't do damper inspections.
  4. Nov 25, 2024

    Commercial Framing

    SEE COMMENTS

    InspectorDale Gronberg

    * 2nd floor elevator lobby needs sheetrock above lid on west wall.to get fire & smoke rating * 3 new F/S dampers installed
  5. Oct 25, 2024

    Meet Contractor

    SEE COMMENTS

    InspectorDale Gronberg

    * Met with Jake and Karrie about requirements for F/S dampers * If air handlers are shutdown for energy saving reasons, fire dasmpers must be fail/safe * All dampers have electric motor controls. Weekly testing of newly installed dampers will be scheduled
  6. Oct 8, 2024

    Commercial Framing

    SEE COMMENTS

    InspectorChris Weaver

    ALL FIRE DAMPERS ORDERED ARE STATIC, MEANING ALL FANS MUST BE SHUT DOWN UPON FIRE DETECTION DOUBLE SIDE ANGLE INSTALLATION WITH SPEED FRAMES PROVIDED BY MANUFACTURER END SWITCHES INDICATING DAMPER POSITION WILL NOT BE USED VIEWED DAMPER INSTALLATION ON 4TH FLOOR MECHANICAL ROOM
  7. Oct 2, 2024

    Commercial Framing

    SEE COMMENTS

    InspectorDale Gronberg

    * Met with Josh, Jake, and Karrie * 2 hr fire-rated shaft at west side of mechanical room is oly open to 3 floors (1 hr required) * Ceiling in Electrical transformer room required to be 1 hr fire-rated. Karrie to demo & frame new ceiling for new dampers * Chase on east end of mechanical room is only open to the 2nd floor. Firestop holes at penthouse floor * The proposed new fire dampers are required on the east wall penetrating the mechanical room 1 hr fire-barrier
  8. Sep 27, 2024

    Commercial Framing

    CORRECTION NOTICE

    InspectorDale Gronberg

    * Mechanical contractor scheduled a site visit to discuss existing non-compliant fire damper framing * Electrical room 246 has a 1 hour fire rating * 2 existing ceiling mounted fire dampers were never installed correctly * Horizontal Core board ceiling assembly will need to be re-framed per Ruskin framing instructions
  9. Sep 19, 2024

    Commercial Framing

    PARTIAL APPROVAL

    InspectorDale Gronberg

    * 14' x 36" fire damper framing in main 1st floor electrical room
  10. Sep 17, 2024

    Commercial Framing

    SEE COMMENTS

    InspectorDale Gronberg

    * Met with Karrie (carpenter) and Jack (Tinner) 2 houir shaft wall framed in open area of existing CMU shaft wall * Fresh air needs F/S damper. Existing exhaust duct damper not in wall * Contact architect for direction on how to procede * All fire dampers will need framing inspection prior to covering