Building
10702 Red Circle Dr, Minnetonka
Remodel/Alteration, Footing and Foundation Permit: Market-rate apt building with 269 dwelling units, formerly 275 units
- Mar 11, 2025
Foundation/Waterproofing
PARTIAL APPROVALInspectorMarshall Lind
Grid 2 Grid K - D
- Mar 10, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
SOG / Vapor barrier Grid F - R Grid 13.5 - 17
- Mar 10, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Grid 2 Grid K - P.7
- Mar 5, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
North Elevator pit, Foundation grid P grid 3 - 4.4
- Mar 4, 2025
Foundation Rebar/Form
CANCELLED APPOINTMENTInspectorMarshall Lind
Canceled by Brad
- Mar 3, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Strip grid 1.9 grid Q-D, Strip grid 2 grid Q-D, Elevator pit grid N.3 - P grid 3 -4.4, Pads grid 2 grid M,K,H,E.9, D.8, D.3, Pad grid Q grid 3
- Feb 28, 2025
Commercial Footing
NOT READYInspectorMarshall Lind
Nothing ready for today
- Feb 26, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
7 pads - Grid 12.2 P, Grid 12.2 P.7, Grid 12.7 P, Grid12.8 P.7, Grid 11.5 H5, Grid 11.5 G.3, Grid12.4 G.3
- Feb 25, 2025
Foundation Rebar/Form
CANCELLED APPOINTMENTInspectorMarshall Lind
Nothing ready for today
- Feb 24, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Strip Grid P - R Grid 1.9, Strip Grid R Grid 1.9 - 8, Strip grid 4.4 Grid Q - R, Pad grid N.3 grid 5, Pad grid Q grid 5, Pad grid N.3 grid 7
- Feb 21, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation & rebar Grid A 1-4, Grid A - C Grid 1
- Feb 19, 2025
Commercial Footing
CANCELLED APPOINTMENTInspectorMarshall Lind
Canceled per Brad due to cold weather 7:40
- Feb 14, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Strip footing Grid A 1 - 4, Strip footing Grid A - C Grid 1
- Feb 7, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation Grid 7.4 F - N, Grid N 7 - 8, Grid E7 7-8,5
- Feb 5, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation Grid N 8-10.3: Grid N-R 10.3:, Grid R 8-10.3
- Feb 5, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Strip Grid N-E.7 7.4: Grid E.7 7.4 - 8.5: 5 Pads Grid 5 M/L/J/G/E.3
- Feb 4, 2025
Foundation Rebar/Form
CANCELLED APPOINTMENTInspectorMarshall Lind
- Feb 3, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Strip & pads Grid N 8-10,3, Grid N-R 10.3, Grid R 8-10.3, 4 Pads Grid E.3 Grid 7 & 5, Grid E Grid 8.5 & 9
- Jan 30, 2025
Commercial Footing
PARTIAL APPROVALInspectorKevin McDermott
Stoop footing fix on west side OK. Interior pad footings: 8.5/P,Q. 9/Q; 9.4/P.
- Jan 29, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Tall wall Grid Q-R Grid 13.5-14.6
- Jan 28, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Exterior foundation Grid 14-16 grid P-R, 2 Stoops Grid A Grid 12.9-14
- Jan 24, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation Grid 17 Grid F-P, Add chairs for rebar to be in correct location on forms
- Jan 22, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation wall Grid 12.2 Grid N-R Rebar OK
- Jan 22, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Pads Grid C Grid 15, Pad Grid C Grid 16 Rebar OK, Stoop footing Grid 13.5 Grid A.9 Have to epoxy rebar in waiting for Braun before installing
- Jan 17, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Strip footing Grid F-R Grid 17-13.5 Outside Radius Already poured, Pads Grid E 12.8 & Grid E12 already poured, Pad Grid E 11 rebar OK
Show 22 earlier inspections
- Jan 14, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Grid F Grid 9-14 Forms & rebar
- Jan 10, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Grid F-L.1 Grid 14.6, Grid F Grid 14-14.6, Grid E-L.1 Grid 13.5, Rebar installed no forms at this time
- Jan 7, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation Grid F 9-14
- Jan 3, 2025
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Strip & pad footings on Grid F , Grid 9-14.6, Pad on Grid D.4, Grid 15, Pads on Grid E, Grid 14.6 & 14 & 13.7
- Dec 27, 2024
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Grid E-F Grid 17.5 Need to add chairs, Grid F Grid 17.5-16.5 Add chairs, Walls WC2 & WC1
- Dec 20, 2024
Commercial Footing
PARTIAL APPROVALInspectorKevin McDermott
Wall forms: grid 21, 2.2- 13.7. RW1, CW7.
- Dec 19, 2024
Commercial Footing
CANCELLED APPOINTMENTInspectorKevin McDermott
Cancelled due to inclement weather. Snow, 21 deg.
- Dec 17, 2024
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Strip footings Grid P.7-R, Grid 12.2-13.7
- Dec 16, 2024
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation Grid P-P7 Grid 13.5-14.6
- Dec 11, 2024
Commercial Footing
PARTIAL APPROVALInspectorDale Gronberg
POURED WALLS * Grids 16/D-L4: VERTS #7 OF, #5 IF @ #12" o.c. HORZ: #5 @ 18" o.c. * Grids 14A/B8: VERTS #4 @ 16" o.c. HORZ #4 @ 16" o.c.
- Dec 9, 2024
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
2 foundation walls, Grid 13.5 Grid A.9-B.3, Grid A.9 Grid 13.5-14.4
- Dec 6, 2024
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation wall Grid 9 A-B, Pier Grid 13.5 B.8
- Dec 4, 2024
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Elevator pit walls Grid 13-13.5 C-D, Pieir Grid 13 D
- Dec 3, 2024
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Piers grid D 4-12, CW2 Foundation walls Grid 4 A.6-B & B1-C
- Nov 27, 2024
Commercial Footing
PARTIAL APPROVALInspectorDale Gronberg
* Grids A & D/1-4 with WF8 & WF9 perimeter footings * Grid 4/A-D with WF9 and F-10 column pad
- Nov 26, 2024
Commercial Footing
PARTIAL APPROVALInspectorChris Weaver
S2.1B - 4-9/A STRIP FOOTING, STAIR TOWER FOOTING 4.5/A.5, A.5/4 TO 4/D STRIP WITH HUGE STEP AT 4/B.7 CONTINUING D.3/4 - D.3/9 STRIP FOOTING
- Nov 25, 2024
Commercial Footing
CANCELLED APPOINTMENTInspectorMarshall Lind
Canceled per EJ 9:00
- Nov 22, 2024
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
Foundation 13,5 - D OK
- Nov 19, 2024
Commercial Footing
CANCELLED APPOINTMENTInspectorMarshall Lind
Per LJ at 8:30
- Nov 14, 2024
Commercial Footing
PARTIAL APPROVALInspectorChris Weaver
STRIP FOOTING 11-1.5/A, 11-12/B PAD 13/B, 12.1/B
- Nov 12, 2024
Commercial Footing
PARTIAL APPROVALInspectorMarshall Lind
Marked in green on plan, Strip & pads 13.5-14.6 A-D, 13.3-17 B.8-F
- Nov 8, 2024
Commercial Footing
NOT READYInspectorMarshall Lind
Met with Brad & Doug on site, Canceled inspection, Not ready
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.