#MI291047Building
19050 Stratford Rd, Minnetonka
IssuedMay 15, 2025
StatusUnknown
Value$373,340
Inspections12
Scope of work
Remodel/Alteration, Remove & rebuild 34 decks & railings-19050 building only
Location context
Parcel3011722330002
Coordinates44.90810, -93.52070
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedMay 13, 2025
IssuedMay 15, 2025
Inspection record
Inspections12
Passed11
Failed0
- Oct 29, 2025
Commercial Framing
APPROVEDInspectorMarshall Lind
Last 3 stacks framing OK
- Oct 29, 2025
Commercial Final
APPROVEDInspectorMarshall Lind
Last units OK Units 201, 301, 303
- Oct 23, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Stack 5 OK, Stack 6 NOT READY, Stack 7 NEEDS MECHANICAL FASTENERS
- Oct 23, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
UNITS 106, 202, 214, 213, 211, 209, 207, 205, 305, 307, 309, 311, 313 OK
- Oct 15, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Stacks 3, 4, 5 from North end, Framing OK Add mechanical fasteners on stack 5 top deck
- Oct 8, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
East side the South 6 decks framing OK, West side North 12 decks framing OK BUT NEED MECHANICAL FASTENERS ON ALL DECKS
- Oct 8, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
Deck finals on Units 102, 104, 108, 110, 112, 114, 204, 206, 208, 210, 212, 302, 304, 306, 308, 310, 312, 314 OK UNITS 106, 202 & 214 COULD NOT ACCESS
- Oct 3, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
West side of apartment building, 1st set of decks on the North end of structure, Framing & mechanical fasteners OK
- Sep 16, 2025
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
First 2 stacks of decks from North end framing OK, Middle 2 stacks new beams OK,NEED MECHANICAL FASTENERS ON BEAMS
- Sep 9, 2025
Commercial Footing
APPROVEDInspectorMarshall Lind
Diamond piers, Helical piers meet engineering & required torque, Contractor stated engineering sent to BN to be added to project Doc
- Sep 9, 2025
Commercial Final
PARTIAL APPROVALInspectorMarshall Lind
2 North end stacks of decks framing OK, 3 - 2x10 beams with mechanical fasteners
- Sep 2, 2025
Commercial Footing
CORRECTION NOTICEInspectorDale Gronberg
* THIS INSPECTION WAS FOR THE BACK SIDE 21 DECKS* *Diamond Piers #75 used. Have Engineer verify this size * Helical piers used for center post of double stacks. Have engineer verify and provide report * The Beams next to stoop will now be cantilevered. Have engineer verify beam size * Plans show double LVL. Triple 2x10 used. Have engineer verify size *PROVIDE THIS INFORMATION AT FRAMING INSPECTION. DO NOT COVER FRAMING