Building
1520 Clare La, Minnetonka
New, Memory Care
- Apr 3, 2026
Above Ceiling
APPROVEDInspectorBrian Stemwedel
looked at fire tape in kitchen, approved ok to install FRP DID NOTICE THAT FIRE WRAP STOPPED AT GYP CEILING, NEED TO VERIFY PROPER WRAP AT DUCT BELOW LID (STAGGER)
- Apr 2, 2026
Above Ceiling
SEE COMMENTSInspectorChris Weaver
FIRE CAULK AND HANGER CORRECTION WALKTHROUGH
- Apr 1, 2026
Above Ceiling
SEE COMMENTSInspectorChris Weaver
FIRE CAULK AND HANGER WALKTHROUGH
- Mar 31, 2026
Above Ceiling
CANCELLED APPOINTMENTInspectorDale Gronberg
- Mar 31, 2026
House Wrap/Lathing
PARTIAL APPROVALInspectorDale Gronberg
* Lathe on north end of east wall okay up to the FD connection
- Mar 26, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
ABOVE CEILING, STILL FIRE CAULKING TO DO, NORTH WING
- Mar 25, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
ABOVE CEILING PRIOR TO HANGING ROCK SOME PATCHING AND FIRE CAULK REQUIRED, WILL SEND PICTURES
- Mar 24, 2026
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Mar 23, 2026
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Mar 20, 2026
Commercial Framing
NOT READYInspectorBrian Stemwedel
work not ready to inspect
- Mar 19, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
SOUND INSULATION IN CENTER ISLAND WALLS AND SOUND CHANNEL WILL BE REQUIRED ON UNIT CORIDOOR WALLS
- Mar 13, 2026
Commercial Framing
SEE COMMENTSInspectorBrian Stemwedel
looked at Poly and tape in the center/ common area lid. also shear walls in south wing, screw pattern adequate. At smoke barrier (smoke compartment separation) the Gyp was not extending behind the frame, per NFPA 80, it must extend behind the frame 1/2" around the perimeter. also talked to sean about wrapping the framing, but after checking this is not required (i called to let him know)
- Mar 11, 2026
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Mar 10, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
--DISCUSSED MAIN GAS VALVE READY ACCESS --STILL NEED DETAIL ON DUCT THROUGH WALLS TO MECHANICAL TUNNELS POLY ON CORIDORS
- Mar 6, 2026
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
poly lid in plan west corridor and center common space OK to gyp lid
- Mar 4, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
--NEED DETAIL REGARDING FIRE RATING OF TUNNEL PENETRATION OF MUA DUCT FROM OUTSIDE. NEED ASSEMBLY NUMBER TO CORRECTLY INSPECT AREA POLY IN NORTH WING. GREASE DUCT INSULATION IS ON AND ACCESS DOOR HAS BEEN CUT. LINE SETS PEIRCING POLY ARE IN CLOSE CONTACT WITH SOUND CHANNEL CUT TO ACCOMODATE LINE SETS, SHARP EDGES TO BE PROTECTED MAIN GAS LINES MUST BE LABELED "2 PSI GAS"
- Mar 2, 2026
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Mar 2, 2026
Commercial Insulation
CANCELLED APPOINTMENTInspectorChris Weaver
- Feb 27, 2026
Commercial Insulation
SEE COMMENTSInspectorBrian Stemwedel
SE Wing: SPF @ exterior walls, plan called for 3.5 ", installed was that at a min. and in most cases exceeded 3.5. Unit dimising wall sound insulation (FG batt, also serves as draftstopping for 10' hor. requirement). Also looked at sound channel installation of corridor lid and corridor/ unit walls per plans. contractor were nor installing SC at 12" O.C. eliminating previous concerns where SC exceeded 12" O.C.
- Feb 26, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
CHECKED EXTERIOR SHEAR WALLS NAILING PATTERNS, OK NORTH WING SHEAR WALLS HOLD DOWN OK, DEMISING WALLS TO HAVE BRACKETS ON TOP TO HOLD WALL IN PLACE OK TO POLY
- Feb 25, 2026
Commercial Framing
SEE COMMENTSInspectorBrian Stemwedel
North wing shear walls Nut not seated @ hold down unit 112, verify at next inspection. all other shear walls looked good, need detail per C.W. notes on 2/23 South wing ceiling sound channel, detail shows S.C.@ 12" O.C., some areas were about 16" O.C. (per Sean this was approved by designer), provide documentation this is acceptable.
- Feb 23, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
DISCUSSED SHEAR WALL TOP PLATE FASTENING, SHEATHING TO BE UNINTERUPTED
- Feb 20, 2026
Commercial Insulation
PARTIAL APPROVALInspectorBrian Stemwedel
Plan SW corner units123-126 VB and insualtion for pre rock upper 4' of corridor walls
- Feb 18, 2026
Commercial Framing
CANCELLED APPOINTMENTInspectorChris Weaver
- Feb 17, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
SOUTH WING HOLD DOWNS AND POLY FOR PREROCK
Show 14 earlier inspections
- Feb 10, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
TRUSS FRAMING INSPECTIONS COMPLETE AS OF 2/10 PREVIOUS ISSUES HAVE BEEN CORRECTED DISCUSSED INSULATING OF THE STAIR CHASES, DRYWALL AND SPRAY FOAM WAS DECIDED UPON
- Feb 9, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
SOUTH WING COMPLETED, MISC LATTERALS MISSING, MISSING DOUBLE STUDS UNDER GIRDER TRUSSES, TRUSS FIX INCORRECT - MUST BE LAMINATED ON BOTH FACES. LEFT OFF AT KITCHEN
- Feb 9, 2026·9:00 AM - 10:00 AM
Commercial Framing
scheduledInspectorChris Weaver
- Feb 6, 2026
Commercial Framing
PARTIAL APPROVALInspectorDale Gronberg
*TRUSS BRACING INSPECTION* * A very complex truss system which will take a couple inspections to complete * Started from plan north through unit 127 (OK) * Add nailing to girder H57GR * Warm walls to attic space must meet energy code
- Feb 5, 2026
Commercial Framing
SEE COMMENTSInspectorChris Weaver
DISCUSSED FRAMING INSPECTIONS AS WE MOVE FORWARD -TRUSS SPECS AND LAYOUT WILL BE AVALIABLE AT TIME OF INSPECTION FOR AREA TO BE INSPECTED -HEADDERS, KING, JACK REQUIREMENTS THEY STILL PLAN TO PUT VERTICAL DOORS IN THE MECHANICAL PITS TO WALKWAYS ACROSS THE ATTIS TO NOTHING. cOULD ACT AS ONLY ACCESS TO ATTIC?
- Oct 28, 2025
Radon
APPROVEDInspectorBrian Stemwedel
Under slab radon barrier lapped and taped as required. all penetrations sealed. OK to cast slab
- Sep 15, 2025
Commercial Footing
PARTIAL APPROVALInspectorChris Weaver
WAITING ON MECHANICAL PAD FOR DISPOSABLE FORMS LAST BIT OF WALL AT BACK, SOUTH SIDE
- Sep 4, 2025
Poured Wall
SEE COMMENTSInspectorChris Weaver
ANOTHER SECTION OF POURED WALL, NOTES ON PLANS REBAR AS PER PLAN
- Aug 28, 2025
Commercial Footing
PARTIAL APPROVALInspectorChris Weaver
POURED WALL, LOCATIONS MARKED ON PLANS, REENFORCEMENT AS PER PLAN
- Aug 22, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorMarshall Lind
South end going from West to East wall jog, Marked on plans/No grid lines
- Aug 20, 2025
Commercial Footing
SEE COMMENTSInspectorChris Weaver
POURED WALLS AROUND EAST SIDE, MARKED ON PLANS
- Aug 15, 2025
Commercial Footing
PARTIAL APPROVALInspectorDale Gronberg
* Footings as marked on job plan * CF1-8, CF6 and F4.5 pads per plan * SE corner needs rebar cut back 2" for clearance to forms * 90% of footings done. West side needs to stay for site entry
- Aug 15, 2025
Foundation Rebar/Form
PARTIAL APPROVALInspectorDale Gronberg
* Poured walls as noted on job plans (OK)
- Aug 12, 2025
Commercial Footing
PARTIAL APPROVALInspectorChris Weaver
---REQUESTED PLAN FOR MARK-UPS IN TRAILER, GC WILL MARK UP WHAT WAS COMPLETED STRIP FOOTINGS NEARLY COMPLETE BEING FORMED AND TIED, NO GRIDS ON PLANS ALL AS PER PLAN
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.