Permit / Minnetonka← Search
#MI294685Building
917 Carlson Pkwy, Minnetonka
IssuedSep 3, 2025
StatusUnknown
Value$775,460
Inspections14
Scope of work
New, 2-unit, 3 story, wood framed condo building
Location context
Fees & payments
Total fees$20
Total paid$20
Timeline
ApprovedSep 3, 2025
IssuedSep 3, 2025
Inspection record
Inspections14
Passed7
Failed0
- Feb 6, 2026
Commercial Insulation
CORRECTION NOTICEInspectorMarshall Lind
Common areas only, Wall between B garage & common area is not insulated, Talked to contractor on site, All other closed cell spay foam & batt insulation & fire stopping OK
- Jan 23, 2026
Commercial Framing
APPROVEDInspectorMarshall Lind
Framing on Common space on ground level OK
- Jan 23, 2026
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Insulation in common area outside Unit A OK
- Jan 16, 2026
Commercial Insulation
PARTIAL APPROVALInspectorMarshall Lind
Unit A only, Exterior wall & fire caulk OK, Need to blow in ceiling. Need common areas done on upper level
- Jan 14, 2026
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Framing UNIT B ONLY, Framing OK, NEED FIRE CAULK AROUND SPRINKLER PIPE/HOLE WHERE WIRE WAS REMOVED ON EAST WALL/AROUND ELECTRICAL WIRES IN FLOOR IN STAIR AREA
- Jan 12, 2026
Commercial Framing
PARTIAL APPROVALInspectorMarshall Lind
Unit A ONLY, Trusses/Beams/Headers/Framing OK, Needs Fire blocking
- Jan 6, 2026
Commercial Framing
SEE COMMENTSInspectorBrian Stemwedel
917 and 921 are exactly 10' apart Unit a ductwork in attic covered with SPF insulation. Need to verify Flame/ Smoke for SPF is compliant with 2601.4.1.6 MSBC (covered with ignition barrier)
- Dec 29, 2025
Commercial Framing
SEE COMMENTSInspectorBrian Stemwedel
Check separation distance between 917 and 921 and make sure it is a min (or exactly 10' apart) if exterior walls are closer than 10', then per Table 602 MSBC 1 hour fire resistance rating is required from both sides [705.5 MSBC] distance is measured to lot line between buildings. if less than 5' from property line, then openings are also limited to 15% of exterior wall area
- Dec 9, 2025
Commercial Framing
CORRECTION NOTICEInspectorMarshall Lind
SHEATHING INSPECTION ONLY, One edge on North side from second floor up to roof needs to be nailed 4 inches on center
- Dec 8, 2025
Commercial Framing
CALL FOR REINSPECTIONInspectorMarshall Lind
SHEATHING INSPECTION ONLY, No one new about inspection, Didn't t know where braced walls are or nailing schedule, Talked to Randy & Jared
- Oct 8, 2025
Foundation/Waterproofing
SEE COMMENTSInspectorDan Menth
Underslab vapor barrier/ radon ok
- Sep 26, 2025
Poured Wall
APPROVEDInspectorBrian Stemwedel
Foundation waterproofing (spray applied asphalt) Foundation insulation, 2" rigid foam (R10) also noted poly slip sheet
- Sep 22, 2025
Poured Wall
APPROVEDInspectorBrian Stemwedel
8" poured wall. #4 verts 48"O.C. w/ (2) #4's (Top and Bottom) informed contractor of requirement to keep verts 3" max distance from soil side of wall( also require 3" min cover to earth, so bar has a tight tolerance of 3" from face of wall on soil side)
- Sep 17, 2025
Commercial Footing
SEE COMMENTSInspectorChris Weaver
FOOTING AS PER PLAN CONCERNS OVER RETAINING WALLS
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.