Building

8358 Cottonwood La N, Maple Grove

IssuedMar 7, 2025
StatusUnknown
Value$35,000
Inspections6
Scope of work

Interior Finish, Basement Finish with 1 bedroom and adding 1 bathroom. Adding a fireplace and wet bar.

Location context
Parcel2311922110092
Coordinates45.10689, -93.42620
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$50
Total paid$50
Timeline
ApprovedMar 5, 2025
IssuedMar 7, 2025
Inspection record
Inspections6
Passed3
Failed0
  1. Jun 27, 2025

    Framing30

    Pass

    InspectorRobert Griffin

  2. Jun 27, 2025

    Insulation

    Pass

    InspectorRobert Griffin

  3. Jun 27, 2025

    Final - 30

    Pass

    InspectorRobert Griffin

  4. Apr 10, 2025

    Framing30

    Partial Inspection

    InspectorRobert Griffin

    Pass pending fireplace rough in inspection.
  5. Apr 10, 2025

    Insulation

    Partial Inspection

    InspectorRobert Griffin

    Pass pending fireplace rough-in inspection
  6. Apr 8, 2025

    Framing30

    Correction notice

    InspectorRobert Griffin

    Ok to check corrections at insulation inspection.