Building
9800 Fernbrook La N, Maple Grove
Add, 50,000 sf of additions & renovations throughout the building (includes storm shelter)
- Feb 25, 2026·10:30 AM - 12:00 PM
Framing - 90
scheduledInspectorDJ Hennessey
- Feb 18, 2026·10:30 AM - 12:00 PM
Framing - 90
scheduledInspectorDJ Hennessey
- Feb 4, 2026
Above Ceiling
Partial InspectionInspectorDJ Hennessey
Area "E" hard lid areas in locker rooms (showers, office) Also all spray applied fire proofing is complete on locker room roof structure.
- Jan 26, 2026
Framing - 90
Partial InspectionInspectorDJ Hennessey
Checked nail plates in area "E" locker rooms north of grid L
- Jan 21, 2026
Framing - 90
Partial InspectionInspectorDJ Hennessey
Framing in Area "E" locker rooms north of grid L
- Jan 21, 2026
Fire block/caulking
Partial InspectionInspectorDJ Hennessey
Fireproofing of bar joists in Weight room E101
- Jan 6, 2026
Underslab Vapor Barrier
Partial InspectionInspectorDJ Hennessey
Area "C" Main corridor and all Northeast of grid line C10
- Jan 6, 2026
Fire block/caulking
Partial InspectionInspectorDJ Hennessey
Storm shelter addn: 2nd floor fire proofing on steel I-beams, columns, and structural weld plates
- Jan 6, 2026
Site
ConsultationInspectorDJ Hennessey
Met on-site with GC & AOR, re: areas where new construction meets existing roof construction. Existing structural columns & beams are fire protected but the bar joists are not (IBC T601, roof construction and associated secondary members require 1hr protection for types II-A & I-B). Existing bar joists are enclosed in 1hr UL system. New construction all steel has spray applied 1hr. AOR will email all UL info (existing & proposed) with plan showing areas where transition occurs for BO approval of methods prior to submitting plan change for review..
- Dec 17, 2025
Framing 60
Partial InspectionInspectorDJ Hennessey
Storm shelter addn: Checked precast wall panel gaps (per ICC 500), no discrepancies noted.
- Dec 17, 2025
Underslab Vapor Barrier
Partial InspectionInspectorDJ Hennessey
Area "C" Main floor of storm shelter Northwest of grid line CJ and Southwest of C10
- Dec 17, 2025
Fire block/caulking
Partial InspectionInspectorDJ Hennessey
Storm shelter addn: 3rd floor fire proofing on steel I-beams, columns, and structural weld plates
- Nov 13, 2025
Site
Correction noticeInspectorDJ Hennessey
Inspected exercise room on north side of gymnastics gym for occupant use.
- Oct 1, 2025
Foundation-Exterior
Partial InspectionInspectorDJ Hennessey
OK to backfill footings from 9/29/05
- Sep 30, 2025
Underslab Vapor Barrier
Partial InspectionInspectorDJ Hennessey
Area E addition (Room E100/E140)
- Sep 29, 2025
Footing
Partial InspectionInspectorDJ Hennessey
remainder of footings for storm shelter in area C
- Sep 17, 2025
Site
Partial InspectionInspectorDJ Hennessey
No change from yesterday. Pouring wall section that was inspected yesterday
- Sep 17, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
Stem walls formed from grid C.11 to C.3 (CG to CJ) C.3 to C.1 not ready yet.
- Sep 15, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
Progress check on storm shelter foundation (Area C). Installing #11 hooks in column piers (currently working along gridline C.1)
- Sep 11, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
Checked stem wall rebar, same section as 9/8 footings. Rebar only, wall forms not set yet. Storm shelter (Gray area in "Area C"): all from grid line CG to the south and east (except column pads at C.7-CG & C.5.6-CG) and all from grid line C.3 to the south and west.
- Sep 11, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Large column pad at east end of existing commons connection to addition.
- Sep 10, 2025
Footing
Not ReadyInspectorDJ Hennessey
Site visit, no new work ready
- Sep 9, 2025
Footing
CancelInspectorDJ Hennessey
- Sep 8, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Storm shelter (Gray area in "Area C"): all from grid line CG to the south and east (except column pads at C.7-CG & C.5.6-CG) and all from grid line C.3 to the south and west.
- Aug 28, 2025
Final
Partial InspectionInspectorDJ Hennessey
Walk through for separation of construction areas from student occupied areas and emergency egress paths.
Show 30 earlier inspections
- Aug 25, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Large column underpins on north side
- Aug 20, 2025
Footing
Not ReadyInspectorDJ Hennessey
Mucking out excavations for new underpinned footings. Maybe ready tomorrow, probably Friday.
- Aug 19, 2025
Above Ceiling
Partial InspectionInspectorDJ Hennessey
Mezzanine at main gym
- Aug 14, 2025
Footing
Partial InspectionInspectorDJ Hennessey
column pads and strip footing from grid G-12 to J-13
- Aug 11, 2025
Site
ConsultationInspectorDJ Hennessey
Met with Job Sup re: temp exiting arrangement during construction when school starts. I reiterated the requirement to keep all required exits free and clear and to protect occupants from dangerous construction hazards. I suggested creating an emergency action plan and coordinating with fire inspector (EL). Overhead construction operations at the north exit would need to cease and potential hazards would need to be immediately removed in the event of an emergency evacuation, or a suitable egress tunnel would need to be in place to protect exiting occupants from falling construction materials.
- Jul 31, 2025
Site
ConsultationInspectorDJ Hennessey
No new work today, pouring walls they formed on 7/29 & 7/30
- Jul 30, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
Finished wall forms between grids C.14 - C.16 and CK - CL
- Jul 29, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
Walls formed between grids C.13 - C.17 and CF - CK Walls partially formed between grids C.14 - C.16 and CK - CL
- Jul 28, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Under pinned column footings on grid Q between grids 10 and 14
- Jul 24, 2025
Footing
Not ReadyInspectorDJ Hennessey
Nothing new formed today
- Jul 23, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Pads at C.13-CE and C.5-CK.3
- Jul 22, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Finished forms between grids C.11 to C.17 and CF to CK also completed area between grids C.14 to C.16 and CK to CL
- Jul 21, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Partially formed between grids C.11 to C.17 and CF to CK Rained out this morning
- Jul 17, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
short wall and 3 piers next to existing building wall at northern (NE) most corner of building (grid C.11 between CK and CK.5
- Jul 16, 2025
Footing
CancelInspectorDJ Hennessey
Rain
- Jul 15, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
Piers and walls in area D, grids F, G, & H 10-12
- Jul 10, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Columns & strip footings from F-10 to G-12 Columns along existing wall on Grid 10 between G and P.2
- Jul 9, 2025
Footing
Partial InspectionInspectorDJ Hennessey
column footings next to existing building at NE corner
- Jul 9, 2025
Foundation-Exterior
Partial InspectionInspectorDJ Hennessey
Poured wall from grid B-7 to B-5 to C-5; grid line 6 from B to K; grid L-5 to L-7
- Jul 8, 2025
Footing
CancelInspectorDJ Hennessey
- Jul 7, 2025
Foundation-Exterior
Partial InspectionInspectorDJ Hennessey
North side addition backfill fdn walls from grid C.5-7 to A-7 to A-9 to D-9 to D-10 to E-10 with interior fdn walls and stoop butts.
- Jul 7, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
Poured wall from grid B-7 to B-5 to C-5; grid line 6 from B to K; grid L-5 to L-7
- Jul 3, 2025
Footing
CancelInspectorColby Cartney
- Jul 2, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Interior footing from K-4 to K-5
- Jul 1, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Strip footing from grid B-7 to B-5 to C-5; grid line 6 from B to K; grid L-5 to L-7
- Jun 30, 2025
Poured Wall
Partial InspectionInspectorDJ Hennessey
North side addition fdn walls from grid C.5-7 to A-7 to A-9 to D-9 to D-10 to E-10 with interior fdn walls and stoop butts.
- Jun 26, 2025
Site
ConsultationInspectorDJ Hennessey
No inspection. Meeting on site near main entrance designer, contractors, school district, and Eric L (fire). Discussed construction phasing and firewall/dampers.
- Jun 23, 2025
Footing
Partial InspectionInspectorDJ Hennessey
North side addition strip footings from grid C.5-7 to A-7 to A-9 to D-9 to D-10 to E-10 with interior wall footings and stoop footings
- Jun 20, 2025
Footing
CancelInspectorColby Cartney
- Jun 12, 2025
Footing
Partial InspectionInspectorDJ Hennessey
Area "E" addition: grid C-4 to C-2, and C-1 to M-1 to M-2 to P-2 to P-3 to Q-3 to Q~4.2 (connects to existing wall). Includes grids M & P continuing east to existing structure. Correction for C-2 to C-1