PULLFIRST[THE RECORD]
Permit / Maple Grove← Search
#MG407433

Building

13950 Grove Dr N 100, Maple Grove

IssuedAug 14, 2025
StatusUnknown
Value$800,000
Inspections5
Scope of work

Alteration, NTI: Demo existing suite & build out for new tenant

Location context
Parcel2211922230030
Coordinates45.10412, -93.45633
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$3,031.28
Total paid$3,031.28
Timeline
ApprovedAug 14, 2025
IssuedAug 14, 2025
Inspection record
Inspections5
Passed0
Failed0
  1. Dec 29, 2025

    Final

    Partial Inspection

    InspectorDJ Hennessey

    Close all open sub-permits **Two sub-permits have not been paid for** (Gilbert Mech)
  2. Dec 15, 2025

    Final

    Partial Inspection

    InspectorKen Nelson

    Walk thru with contractor
  3. Nov 20, 2025

    Above Ceiling

    Partial Inspection

    InspectorRobert Griffin

    Rated wall for med gas area not yet firestopped. (Contractor plans to provide access to view at final)
  4. Nov 13, 2025

    Framing 60

    Partial Inspection

    InspectorDylan DeMarais

    Lower level mechanical room ceiling.
  5. Oct 8, 2025

    Framing 60

    Partial Inspection

    InspectorDylan DeMarais

    Inspected main level north of grid line 'C', lower level and structural repair/additions will need to be re-inspected, South of grid line 'C' will need city approved revised plans.