Building
10600 Temple Drive, Maple Grove
New, 17,000 sf new community center
- Dec 19, 2025
Poured Wall
Partial InspectionInspectorRobert Griffin
Piers at grids A-12, B-12, C-12, and D-12,
- Dec 17, 2025
Footing
Partial InspectionInspectorRobert Griffin
Isolated pier pad footings grids A-12, B-12, C-12, and D-12, (Contractor stated footing at A-12 had sewer run through, and compromised geopier, but that the engineer assessed soil / foundation suitability, and a follow up report will be provided.
- Dec 15, 2025
Footing
CancelInspectorRobert Griffin
- Nov 26, 2025
Poured Wall
CancelInspectorRobert Griffin
- Nov 25, 2025
Poured Wall
Partial InspectionInspectorRobert Griffin
Interior column piers grid lines B and C, and grid lines 2,3,4,5,6,7,8,9, and 10. (18 piers total). Contractor in process of installing compression ties in stirrups. Special inspector will check ties prior to concrete placement per discussion with contractor.
- Nov 24, 2025
Footing
No AccessInspectorDJ Hennessey
Job sup not here, no footings ready
- Nov 20, 2025
Footing
Partial InspectionInspectorJason Bredenberg
Interior pads grid lines B/2-4, C/2-4 6 total
- Nov 19, 2025
Footing
Partial InspectionInspectorDylan DeMarais
Interior pads at grid lines B/5 to B/10 and C/5 to C/10. (12 total)
- Nov 18, 2025
Foundation-Exterior
PassInspectorDylan DeMarais
Foundation insulation from grid line 1/A.2 to 4/D.2.
- Nov 14, 2025
Poured Wall
Partial InspectionInspectorRobert Griffin
Foundation walls approximate grids 1(A.2 to D.2), and D.2(1 to 3.3)
- Nov 13, 2025
Footing
Partial InspectionInspectorKen Nelson
Grid Line (1): A.2 to D.2
- Nov 12, 2025
Foundation-Exterior
Partial InspectionInspectorRobert Griffin
Foundation insulation observed for approximate grids A.2 (1.1 to 7.5).
- Nov 10, 2025
Poured Wall
Correction noticeInspectorDylan DeMarais
Foundation wall A.2 (1.1 - 7.5), correction for pier column at A.2 - 2 engineering needed
- Nov 7, 2025
Poured Wall
Partial InspectionInspectorRobert Griffin
Foundation wall approximate grids A.2 (1.1 to 7.5). Discussed with contractor that special inspector is required to be on site to observe rebar and cast cylinders for concrete placement. (not all form pans installed yet during today's inspection)
- Nov 5, 2025
Foundation-Exterior
Partial InspectionInspectorRobert Griffin
Foundation insulation approximate grid lines A.2(7.5 to 11), 11(A.2 to D.2), and D.2(4.5 to 11).
- Oct 31, 2025
Footing
Partial InspectionInspectorRobert Griffin
Correction to widen misplaced previously poured footing between gridlines 2 and 3 on North side of structure. (Contractor provided documentation from SER and stated special inspector would be arriving to witness post installed rebar per engineer's fix)
- Oct 29, 2025
Poured Wall
Partial InspectionInspectorKen Nelson
Walls and Piers along grid line D. From grid line12 to between grid lines 1 & 2
- Oct 24, 2025
Poured Wall
Partial InspectionInspectorRobert Griffin
Walls/ integral piers, approximate grids ((A.2-7.5) to (A.2-11)), and ((11-A.2) to (11-B.3))
- Oct 22, 2025
Footing
Partial InspectionInspectorDylan DeMarais
Strip footings and pads from A.2/6.5 to before corner pad (stopped 6-8 feet from corner)
- Oct 17, 2025
Footing
Partial InspectionInspectorRobert Griffin
Footings including integral pier pad footings grids D.2(1.7 to 11), A.2(6.5 to 11), and 11(A.2 to D.2). Contractor plans to check with SER for use of 6" chairs to support rebar, plans show 3" distance specified, special inspector must also check soil as rain has occurred since the time footings were excavated.
- Oct 16, 2025
Footing
Partial InspectionInspectorDylan DeMarais
Inspected strip footing from grid line 11/A.2 (started after F1 pad) to 1/D.2 (stopped prior to F2 pad), no rebar matte in place, #8 dowels not in place for pier columns, missing #5 rebar at footing jump between 'C' - 'D' @ 11.
- Oct 15, 2025
Footing
CancelInspectorDylan DeMarais
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.