Building
1732 Spruce St, Farmington
New, Single Family Home
- Oct 21, 2025
Turf Inspection
ApprovedInspectorRich Schimmel
- May 22, 2025
As-Built
ApprovedInspectorRich Schimmel
Clean up erosion on south prop. line by slope on side of house.
- Mar 26, 2025
Final
Not Approved/CorrectionsInspectorMatt Olson
- Mar 7, 2025
Final
Not Approved/CorrectionsInspectorMatt Olson
- Feb 21, 2025
Mech Final
Not Approved/CorrectionsInspectorMatt Olson
AC not installed
- Feb 20, 2025
Framing
ApprovedInspectorSean Majewski
- Feb 20, 2025
Manometer (Plumbing)
ApprovedInspectorSean Majewski
- Feb 20, 2025
Plbg Final
Not Approved/CorrectionsInspectorSean Majewski
- Jan 29, 2025
Lathe - before stone/brick if applicable
ApprovedInspectorBroc Haskamp
- Jan 24, 2025
Shower Pan
ApprovedInspectorSean Majewski
- Jan 21, 2025
Gypsum Board/Interior BWL
ApprovedInspectorSean Majewski
- Jan 21, 2025
Shower Pan
Not ReadyInspectorSean Majewski
- Nov 27, 2024
Gypsum Board/Interior BWL
Partial ApprovalInspectorMatt Olson
Garage side still needs to be done
- Nov 25, 2024
Insulation
ApprovedInspectorSean Majewski
- Nov 21, 2024
Sheathing
ApprovedInspectorSean Majewski
- Nov 21, 2024
Rim Boad/Key Blocking - Future Attchment of Deck
ApprovedInspectorSean Majewski
Measured from inside edge of patio door: Engineered rim board extends: ~16" east, 6" west; Key blocking at: ~44" east (above edge of window), 32" west; in addtion to 19.2" OC floor trusses
- Nov 21, 2024
Framing
Not Approved/Verify at InsulationInspectorSean Majewski
- Nov 18, 2024
Plbg Rough In
ApprovedInspectorBroc Haskamp
- Nov 13, 2024
Mech Rough In
ApprovedInspectorJoshua Lawrenz
- Oct 30, 2024
Sheathing
Not Approved/CorrectionsInspectorSean Majewski
Check at framing
- Oct 21, 2024
Poly - Radon
ApprovedInspectorMatt Brown
- Oct 15, 2024
Plbg Underground
ApprovedInspectorMatt Olson
- Sep 9, 2024
Foundation
ApprovedInspectorSean Majewski
- Sep 6, 2024
Foundation
Not ReadyInspectorSean Majewski
West side insulation not installed, crew on-site working won't be finished until late this evening - reschedule insp
- Sep 4, 2024
Poured Wall
ApprovedInspectorSean Majewski
Show 1 earlier inspection
- Aug 28, 2024
Footing
ApprovedInspectorSean Majewski
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.