Permit / Farmington← Search
#FA058266

Building

21405 Dushane Pkwy, Farmington

IssuedAug 8, 2024
StatusUnknown
Value$3,200,000
Inspections26
Scope of work

Undefined, Apartment - Footing & Foundation (Only Permit)

Location context
Fees & payments
Total fees$28,525.47
Inspection record
Inspections26
Passed26
Failed0
  1. Nov 3, 2025

    Commercial Final

    Approved

    InspectorBroc Haskamp

  2. Mar 26, 2025

    Concrete forms before pouring

    Approved

    InspectorBroc Haskamp

  3. Mar 26, 2025

    Foundation

    Approved

    InspectorBroc Haskamp

  4. Mar 26, 2025

    Foundation Insulation

    Approved

    InspectorBroc Haskamp

  5. Dec 9, 2024

    Poured Wall

    Approved

    InspectorBroc Haskamp

  6. Dec 5, 2024

    Concrete Work

    Partial Approval

    InspectorSean Majewski

    S201B: (2) hashed areas with detail 2/S402; (2) areas noted 8" Hollow Core Sloped, either side of middle hashed area
  7. Dec 3, 2024

    Footing

    Approved

    InspectorBroc Haskamp

  8. Nov 26, 2024

    Concrete Rebar

    Approved

    InspectorBroc Haskamp

    Area A stairway
  9. Nov 26, 2024

    Poured Wall

    Partial Approval

    InspectorBroc Haskamp

    West wall of area A
  10. Nov 19, 2024

    Poured Wall

    Partial Approval

    InspectorBroc Haskamp

    East wall of area A
  11. Nov 12, 2024

    Concrete Rebar

    Partial Approval

    InspectorBroc Haskamp

    Southwest stairwell in parking level
  12. Nov 8, 2024

    Footing

    Partial Approval

    InspectorSean Majewski

    Elevator Pit: footings dug out, not formed yet (CF2 and (2) - F6-6 pads)
  13. Nov 8, 2024

    Poured Wall

    Partial Approval

    InspectorSean Majewski

    Just north of elevator pit on both sides and everything to the south of that
  14. Oct 30, 2024

    Poured Wall

    Partial Approval

    InspectorBroc Haskamp

    Underground parking entrance to just short of elevator pit
  15. Oct 22, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    Remainder of strip footings
  16. Oct 16, 2024

    Poured Wall

    Partial Approval

    InspectorBroc Haskamp

    South wall courtyard exits to include pool mech room
  17. Oct 16, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    Underground parking entrance footings
  18. Oct 8, 2024

    Poured Wall

    Partial Approval

    InspectorBroc Haskamp

    Elevator pit walls
  19. Oct 3, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    Elevator pit
  20. Oct 1, 2024

    Poured Wall

    Partial Approval

    InspectorBroc Haskamp

    south area of area C Grid line 29-33
  21. Sep 23, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    All grade beams in area B and C
  22. Sep 19, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    All footings for area B
  23. Sep 12, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    All interior pad footings and all strip footings in are C except grid line 17, A to F and grid line B, 22 to 17
  24. Sep 9, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    5 interior pad footings left on the north side of the northeast wing. the rest of the pad footings have been approved.
  25. Sep 5, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    All interior pad footings in area C
Show 1 earlier inspection
  1. Sep 4, 2024

    Footing

    Partial Approval

    InspectorBroc Haskamp

    Pad Footings in SW wing 33 D thru G to 17 D thru G- Outlined in red on the plan

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.