PULLFIRST[THE RECORD]
Permit / Duluth← Search
#CSBLDGC-2412-0230

Sitework & Foundation - Commercial & 3+ Multi-Family

502 Helberg Dr, Duluth

IssuedJan 21, 2025
StatusComplete
Value$60,000
InspectionsNone listed
Scope of work

Northland Constructors is updating its bituminous asphalt production plant at 502 Helberg Drive. We are building a 54' X 60' secondary containment slab and foundation that will support up to four 32,000-gallon liquid vertical tanks. In addition to the four vertical tanks, the containment slab will be built to accommodate a hot oil boiler and a rack to store/pump Evotherm (an additive for liquid asphalt). Braun was contracted to perform the geotechnical report and Krech Ojard is designing and engineering the containment slab/foundation. All construction will be self-performed by Northland Constructors.

Location context
Timeline
ApprovedDec 3, 2024
IssuedJan 21, 2025
CompletedMar 25, 2026
Inspection record

No inspections recorded.

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.