PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED212492

Plumbing

4401 76th St W, Edina

IssuedJun 18, 2024
StatusUnknown
Value$911,730
Inspections34
Scope of work

New, Plumbing for new Fire Station #2. Pipe and fixtures.

Location context
Parcel3102824440001
Coordinates44.86545, -93.33424
Loading map…
199 nearby
This permitNearby
Fees & payments
Total fees$4,558.65
Total paid$4,558.65
Timeline
ApprovedJun 12, 2024
IssuedJun 18, 2024
Inspection record
Inspections34
Passed24
Failed0
  1. Sep 17, 2025

    Final - COMMERCIAL

    Approved

    InspectorJim Anderson

  2. Sep 12, 2025

    Final - COMMERCIAL

    Approved

    InspectorJim Anderson

    Plumbers work complete. Checking on state permit
  3. Sep 4, 2025

    Final - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Plumber is about 95% complete. Incomplete still: Sink in media room Emergency eye wash Bomb shelter toilet Lower level dishwasher Will call us one more time when 100% for visual
  4. Aug 27, 2025

    Final - COMMERCIAL

    Cancelled

    InspectorJim Anderson

  5. Aug 5, 2025

    Final - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Visual of fixtures done on west side of building. Manometer good **Missing 7 sinks and a urinal** Cont will call back for visual when complete. (Also noticed the water heaters piped without unions. Called cont and asked to have them added)
  6. Jun 3, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Final RI for far east bathrooms and DF. 5psi good
  7. Jun 3, 2025

    Final - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Start up of outside sink needed. RPZ's done and in 220164
  8. May 28, 2025

    Partial Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim G Meyer

    was in laundry area and clean room air on water and dwv for this section visual completed i this area also
  9. Apr 22, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    6" Overflow rain leader that runs across front of garage bay doors, 3psi good
  10. Apr 17, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Primary on NW garage bay. 5psi good Primary on exercise SE corner and overflow of same. 5psi each. good
  11. Apr 16, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Sanitary tested. 5psi good Fitness area NE corner; Rain leader and overflow both tested 5psi. Good
  12. Apr 14, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Plumber re tested all piping in the west portion of the station. Did not hold. Will check with gauge again on Wed.
  13. Apr 8, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    DWV holding 5psi good OK to rock
  14. Apr 7, 2025

    Rough-In - COMMERCIAL

    Not Approved

    InspectorJim Anderson

    Visual of all DWV on second floor. air test did not hold. Will reschedule for another test
  15. Mar 28, 2025

    Rough-In - COMMERCIAL

    Cancelled

    InspectorJim Anderson

  16. Mar 21, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Visual of more rain leaders. 4- 3" on deck. 2 primary/2 orl 6" olr and 6" primary in fire truck garage. ALL 5psi. good
  17. Mar 20, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Visual of 3 primarys and 2 overflow rain leaders. All 5psi good
  18. Mar 19, 2025

    Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    visual of 3 overflows out NW corner. 3,4 & 6. 5psi x 3 good visual of primary drains inside west side. 6 & 4. 5psi good
  19. Oct 8, 2024

    Partial Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Visual of more sanitary run over near mech room 5psi good
  20. Aug 29, 2024

    Partial Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Office area area A 5psi good Area A storm 5psi good
  21. Aug 28, 2024

    Partial Rough-In - COMMERCIAL

    Progress Report

    InspectorJim Anderson

    Visual of underground in north west side of bldg. Cont will have air back on tomorrow.
  22. Aug 27, 2024

    Partial Rough-In - COMMERCIAL

    Cancelled

    InspectorJim Anderson

  23. Aug 23, 2024

    Partial Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    West of grid line E underground. Offices with baths 5psi good
  24. Aug 22, 2024

    Partial Rough-In - COMMERCIAL

    Cancelled

    InspectorJim Anderson

  25. Aug 21, 2024

    Partial Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Middle apparatus bay sanitary 5psi good Storm in middle area to east 5psi good. Grid line E and east complete
Show 9 earlier inspections
  1. Aug 20, 2024

    Partial Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    RI tested from east wall to the east. 5psi. good
  2. Aug 16, 2024

    Partial Rough-In - COMMERCIAL

    Progress Report

    InspectorJim Anderson

  3. Aug 15, 2024

    Partial Rough-In - COMMERCIAL

    Cancelled

    InspectorJim Anderson

  4. Aug 14, 2024

    Partial Rough-In - COMMERCIAL

    Partial Approval

    InspectorJim Anderson

    Visual of workout/lockerroom area baths. Far east side of fire station. 5psi good
  5. Aug 13, 2024

    Partial Rough-In - COMMERCIAL

    No Physical Inspection Done

    InspectorJim Anderson

    Informed contractor of the issue with the prefab pipe and fittings being outside in the weather elements for over a month+
  6. Aug 2, 2024

    Partial Rough-In - COMMERCIAL

    Cancelled

    InspectorJim Anderson

  7. Jul 11, 2024

    Partial Rough-In - COMMERCIAL

    Approved

    InspectorJim Anderson

    De Con room piping, 5psi good Visual of turn out storage floor drains Visual of main sanitary ran between buildings.(cont will have air on this for next inspection)
  8. Jun 21, 2024

    Rough-In - COMMERCIAL

    Cancelled

    InspectorJim Anderson

  9. Jun 11, 2024

    Partial Rough-In - COMMERCIAL

    Approved

    InspectorJim Anderson

    Flammable waste tank looked at today. 1" water column with manometer. Good