Plumbing
4401 76th St W, Edina
New, Plumbing for new Fire Station #2. Pipe and fixtures.
- Sep 17, 2025
Final - COMMERCIAL
ApprovedInspectorJim Anderson
- Sep 12, 2025
Final - COMMERCIAL
ApprovedInspectorJim Anderson
Plumbers work complete. Checking on state permit
- Sep 4, 2025
Final - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Plumber is about 95% complete. Incomplete still: Sink in media room Emergency eye wash Bomb shelter toilet Lower level dishwasher Will call us one more time when 100% for visual
- Aug 27, 2025
Final - COMMERCIAL
CancelledInspectorJim Anderson
- Aug 5, 2025
Final - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Visual of fixtures done on west side of building. Manometer good **Missing 7 sinks and a urinal** Cont will call back for visual when complete. (Also noticed the water heaters piped without unions. Called cont and asked to have them added)
- Jun 3, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Final RI for far east bathrooms and DF. 5psi good
- Jun 3, 2025
Final - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Start up of outside sink needed. RPZ's done and in 220164
- May 28, 2025
Partial Rough-In - COMMERCIAL
Partial ApprovalInspectorJim G Meyer
was in laundry area and clean room air on water and dwv for this section visual completed i this area also
- Apr 22, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
6" Overflow rain leader that runs across front of garage bay doors, 3psi good
- Apr 17, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Primary on NW garage bay. 5psi good Primary on exercise SE corner and overflow of same. 5psi each. good
- Apr 16, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Sanitary tested. 5psi good Fitness area NE corner; Rain leader and overflow both tested 5psi. Good
- Apr 14, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Plumber re tested all piping in the west portion of the station. Did not hold. Will check with gauge again on Wed.
- Apr 8, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
DWV holding 5psi good OK to rock
- Apr 7, 2025
Rough-In - COMMERCIAL
Not ApprovedInspectorJim Anderson
Visual of all DWV on second floor. air test did not hold. Will reschedule for another test
- Mar 28, 2025
Rough-In - COMMERCIAL
CancelledInspectorJim Anderson
- Mar 21, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Visual of more rain leaders. 4- 3" on deck. 2 primary/2 orl 6" olr and 6" primary in fire truck garage. ALL 5psi. good
- Mar 20, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Visual of 3 primarys and 2 overflow rain leaders. All 5psi good
- Mar 19, 2025
Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
visual of 3 overflows out NW corner. 3,4 & 6. 5psi x 3 good visual of primary drains inside west side. 6 & 4. 5psi good
- Oct 8, 2024
Partial Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Visual of more sanitary run over near mech room 5psi good
- Aug 29, 2024
Partial Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Office area area A 5psi good Area A storm 5psi good
- Aug 28, 2024
Partial Rough-In - COMMERCIAL
Progress ReportInspectorJim Anderson
Visual of underground in north west side of bldg. Cont will have air back on tomorrow.
- Aug 27, 2024
Partial Rough-In - COMMERCIAL
CancelledInspectorJim Anderson
- Aug 23, 2024
Partial Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
West of grid line E underground. Offices with baths 5psi good
- Aug 22, 2024
Partial Rough-In - COMMERCIAL
CancelledInspectorJim Anderson
- Aug 21, 2024
Partial Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Middle apparatus bay sanitary 5psi good Storm in middle area to east 5psi good. Grid line E and east complete
Show 9 earlier inspections
- Aug 20, 2024
Partial Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
RI tested from east wall to the east. 5psi. good
- Aug 16, 2024
Partial Rough-In - COMMERCIAL
Progress ReportInspectorJim Anderson
- Aug 15, 2024
Partial Rough-In - COMMERCIAL
CancelledInspectorJim Anderson
- Aug 14, 2024
Partial Rough-In - COMMERCIAL
Partial ApprovalInspectorJim Anderson
Visual of workout/lockerroom area baths. Far east side of fire station. 5psi good
- Aug 13, 2024
Partial Rough-In - COMMERCIAL
No Physical Inspection DoneInspectorJim Anderson
Informed contractor of the issue with the prefab pipe and fittings being outside in the weather elements for over a month+
- Aug 2, 2024
Partial Rough-In - COMMERCIAL
CancelledInspectorJim Anderson
- Jul 11, 2024
Partial Rough-In - COMMERCIAL
ApprovedInspectorJim Anderson
De Con room piping, 5psi good Visual of turn out storage floor drains Visual of main sanitary ran between buildings.(cont will have air on this for next inspection)
- Jun 21, 2024
Rough-In - COMMERCIAL
CancelledInspectorJim Anderson
- Jun 11, 2024
Partial Rough-In - COMMERCIAL
ApprovedInspectorJim Anderson
Flammable waste tank looked at today. 1" water column with manometer. Good