Building
3909 54th St W, Edina
New, NEW HOME
- Jan 6, 2026
Temporary CO
ApprovedInspectorBrian Crask
- Dec 15, 2025
Planning
ApprovedInspectorKris Aaker
- Dec 15, 2025
Residential Redevelopment Coordinator
ApprovedInspectorLindsay Evans
- Dec 15, 2025
Engineering (call 952-903-5728)
Progress ReportInspectorAndy Reinisch
Engineering inspection to be completed in spring 2026.
- Dec 15, 2025
Final As Built Survey
Progress ReportInspectorBrian Crask
The final as-built grade & FFE survey has been submitted, saved to PIMs Photos & Lot Surveys and sent to Planning, Engineering, Forestry, and Residential Redevelopment for Final Reviews.
- Dec 5, 2025
Final-NEW HOME
Not ApprovedInspectorBrian Crask
-18" max to first rung of ladder at egress wells -Seal electrical penetration through siding at left side of home. -Seal sump lid and lid penetrations for radon -Need to fire-block 80 sq feet of un-rocked lid in MECH room -Submit final As-Built Grade & FFE permit for review -Need final approvals from Planning, Engineering, Forestry, and Residential Redevelopment.
- Nov 25, 2025
Final-NEW HOME
Not ApprovedInspectorBrian Crask
-18" max to first rung of ladder at egress wells -Seal electrical penetration through siding at left side of home. -Seal sump lid and lid penetrations for radon -Need to fire-block 80 sq feet of un-rocked lid in MECH room -Need final approval on all related permits -Submit final As-Built Grade & FFE permit for review -Need final approvals from Planning, Engineering, Forestry, and Residential Redevelopment.
- Nov 20, 2025
Final-NEW HOME
Not Approved, Not HomeInspectorBrian Crask
Contractor was not on-site / no access to house. Also, exterior correction items have not been addressed.
- Nov 17, 2025
Erosion Ctrl/Const Entrance
Approved, w/ CommentsInspectorLindsay Evans
Seasonal Inspection (Fall) - OK
- Oct 24, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Oct 10, 2025
Blower Door Test (Air Leakage)
ApprovedInspectorBrian Crask
Blower door test was approved at 1.148 ACH
- Oct 10, 2025
Final-NEW HOME
Not ApprovedInspectorBrian Crask
-18" max to first rung of ladder at egress wells -Seal electrical penetration through siding at left side of home. -Seal attic access -Seal sump lid and lid penetrations for radon -Seal foundation wall to slab in MECH room for radon. -Post energy efficiency certificate -Need to fire-block 80 sq feet of un-rocked lid in MECH room -Need final approval on all related permits -Submit final As-Built Grade & FFE permit for review -Need final approvals from Planning, Engineering, Forestry, and Residential Redevelopment.
- Jul 9, 2025
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
Sod installed and landscape complete. Overall site looked good but Site Sign has been removed.
- May 29, 2025
Lath
ApprovedInspectorBrian Crask
- May 27, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
EC missing along front needs to be reinstalled Establish proper rock entrance (or not permitted to drive on/off site) Reinstall site sign Clean up street in front of site so its free from sediment track out
- Apr 28, 2025
Bldg Progress
Progress ReportInspectorNate Borwege
Tree Permit and preliminary approval from forestry required prior to TEMP CO issuance.
- Apr 3, 2025
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
Boards have been removed and improvement in street (will clean a little better when snow melts a bit) Placed bio logs along curb in front of entrance (doesn't plan to add more rock at this time as they will be pouring driveway relatively soon, but will not drive onto site in meantime)
- Apr 1, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Replenish rock entrance Clean up street in front of site Remove boards that are in the street along the curb
- Jan 30, 2025
Insulation
ApprovedInspectorGodwin Annin
- Dec 30, 2024
Framing-New Home
ApprovedInspectorGodwin Annin
-
- Dec 4, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
Fall/Winter Redevelopment Inspection *Inspected by John Brennan
- Dec 2, 2024
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Fall/Winter Redevelopment Inspection *Inspected by John Brennan - Add bio log against the fence W of the property as there is disturbed sediment upstream of the fence
- Nov 8, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Nov 8, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Oct 24, 2024
Poured Foundation Reinforcement
ApprovedInspectorTedd Nelson
- Garage and front stoop
Show 27 earlier inspections
- Oct 23, 2024
Footing
ApprovedInspectorBrian Crask
GA approve main house footing on 8/1/24 & BC approved of garage & front porch on 10/23/24. All footings are now approved.
- Oct 21, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Oct 21, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Oct 3, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Oct 3, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Sep 24, 2024
Framing-New Home
No Physical Inspection DoneInspectorNate Borwege
Spoke with RYAN LABORE 651-592-4365. Question about rim blocking between the top chord bearing trusses. Truss MFG defered to the building official. Per R502.7 I advised that the only required blocking between the top chord bearing trusses should be at the braced wall locations.
- Sep 20, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Sep 20, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Sep 18, 2024
Floor Slab
ApprovedInspectorBrian Crask
- Sep 5, 2024
Bldg Progress
No Physical Inspection DoneInspectorPeter Akmenkalns
Surveyor called and told me his notes were messed up and the foundation is actually a bit lower than proposed. new survey received and letter from both neighbors affected by erosion. will back fill ASAP so garage footings can be poured.
- Sep 5, 2024
Foundation Pre-backfil (Top of foundation survey)
Partial ApprovalInspectorPeter Akmenkalns
foundation is .01 lower than proposed. in lot surveys and photos house foundation only garage still not poured.
- Sep 3, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Sep 3, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Aug 30, 2024
Bldg Progress
No Physical Inspection DoneInspectorPeter Akmenkalns
Called Sean and told him no engineered shoring was in stalled. need to either have property owners that abut the site sign off on no shoring or have enginnered shoring plan by wednesday sept 4th when we meet on site
- Aug 28, 2024
Construction Fence
Not ApprovedInspectorLindsay Evans
need to get fence back up
- Aug 28, 2024
Erosion Ctrl/Const Entrance
Partial Approval w/ CommentsInspectorLindsay Evans
Mostly good. Need to clean street better.
- Aug 27, 2024
Foundation Pre-backfil (Top of foundation survey)
Not ApprovedInspectorPeter Akmenkalns
proposed top of wall at 901.26 wall poured at 904.30 max new FFE is 903.51 stop work and prohibit is placed until we hear from contractor how this will be fixed.
- Aug 22, 2024
Foundation Pre-Backfil
Partial ApprovalInspectorPeter Akmenkalns
drain tile, insulation and waterproofing at house foundation. garage foundation still to be added. needed as built survey
- Aug 21, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Aug 21, 2024
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
Need to clean street at end of day and remove boards in street at rock entrance at end of day as well. Remove runoff debris from neighboring driveway and add additional bio logs along the entire side of neighboring driveway as stockpile keeps spilling over. Site sign and rock entrance good.
- Aug 14, 2024
Poured Foundation Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
House poured wall only, garage to be done after back fill as lot is tight and garage is at front of lot. compaction report required for garage footing as old house sat where garage will be.
- Aug 8, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Aug 8, 2024
Erosion Ctrl/Const Entrance
Approved, w/ CommentsInspectorLindsay Evans
Additional logs have been installed along side/neighboring driveway.
- Aug 2, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Aug 2, 2024
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
- Aug 1, 2024
Footing
ApprovedInspectorGodwin Annin
- Main house footing - ok
- Aug 1, 2024
Construction Fence
Not ApprovedInspectorLindsay Evans
Need to install remaining safety fence to enclose entire excavated area with steep slopes.