Permit / Edina← Search
#ED214421Building
417 John St, Edina
IssuedAug 19, 2024
StatusUnknown
Value$395,000
Inspections17
Scope of work
Addition, Add primary suite and living room to rear of home inc. stair to basement
Location context
Fees & payments
Total fees$1,975
Total paid$1,975
Timeline
ApprovedAug 13, 2024
IssuedAug 19, 2024
Inspection record
Inspections17
Passed14
Failed0
- Nov 24, 2025
Final (includes smoke and CO alarms)
ApprovedInspectorBrian Crask
- Nov 21, 2025
Engineering (call 952-903-5728)
ApprovedInspectorAndy Reinisch
- Nov 20, 2025
Final (includes smoke and CO alarms)
Not ApprovedInspectorBrian Crask
-Need final inspection from the Engineering department
- Aug 21, 2025
Tree Final (call 952-826-0308)
ApprovedInspectorLaura Beres
- Aug 21, 2025
Engineering (call 952-903-5728)
Progress ReportInspectorAndy Reinisch
Approved for hydro-seeding
- Aug 19, 2025
Final (includes smoke and CO alarms)
Not ApprovedInspectorBrian Crask
-Need final inspection from the Engineering department -Need final inspection from the Forestry department -Need final MECH inspection -Gas fueled dryers are prohibited from being located in the bedroom -1/2" gypsum board required on ceiling to cover I joists. -Missing house numbers
- Jul 1, 2025
Engineering (call 952-903-5728)
Progress ReportInspectorAndy Reinisch
Underground system is installed, Once fittings are installed it is approved for backfill and final restoration.
- Feb 25, 2025
Weather Barrier/Flashing
ApprovedInspectorScot Jandro
- Nov 21, 2024
Framing
ApprovedInspectorBrian Crask
Fire-blocking photos were submitted
- Nov 21, 2024
Insulation
ApprovedInspectorBrian Crask
Fire-blocking photos were submitted
- Nov 8, 2024
Insulation
Not ApprovedInspectorBrian Crask
Need fire-blocking everything else is OK
- Nov 8, 2024
Framing
Partial ApprovalInspectorBrian Crask
Need Fire-blocking. Everything else is OK Note: Beam calcs and engineering were by PE Mark Soderlund
- Nov 6, 2024
Framing
Partial ApprovalInspectorGodwin Annin
- Contractor to provide Engineering beam Calc at insulation inspection.
- Sep 19, 2024
Foundation Pre-Backfil
ApprovedInspectorScot Jandro
- Sep 10, 2024
Poured Foundation Reinforcement
ApprovedInspectorTedd Nelson
- Sep 6, 2024
Footing
ApprovedInspectorBrian Crask
- Sep 3, 2024
Footing
CancelledInspectorScot Jandro