Building
5341 Kellogg Ave, Edina
New, NEW HOME: Escrow Paid
- Aug 21, 2025
Escrow
Approved, w/ CommentsInspectorLindsay Evans
OK to issue escrow refund. Per Water Resources: No well on-site.
- Aug 21, 2025
Building Final
Approved, w/ CommentsInspectorNate Borwege
Escrow refund of $10,000 Approved.
- Aug 20, 2025
Escrow
Progress ReportInspectorLindsay Evans
Biffy and IP have been removed.
- Aug 14, 2025
Escrow
Progress ReportInspectorLindsay Evans
Site sign removed. *Biffy and IP are NOT removed yet. Contractor will notify me when complete
- Aug 12, 2025
Escrow
Progress ReportInspectorLindsay Evans
Conducted final site inspection, took new home pics and uploaded to PDox. **Site sign, biffy, and IP device still need to be removed.
- Aug 11, 2025
Planning
ApprovedInspectorKris Aaker
- Aug 11, 2025
Final-NEW HOME
ApprovedInspectorPeter Akmenkalns
- Aug 11, 2025
Blower Door Test (Air Leakage)
ApprovedInspectorPeter Akmenkalns
1.18
- Aug 11, 2025
Framing-New Home
Approved, w/ CommentsInspectorPeter Akmenkalns
no deck was built only patios. *All New Home Framing was complete and approved by Brian on 2/20/25
- Aug 11, 2025
Escrow
Progress ReportInspectorLindsay Evans
Received online escrow refund request. Working to process.
- Aug 7, 2025
Tree Final (call 952-826-0308)
ApprovedInspectorLaura Beres
planted 1 new tree.
- Aug 6, 2025
Final As Built Survey
Progress ReportInspectorBrian Crask
The final as built survey has been submitted, saved to PIMs & Lot Surveys, and sent to Planning, Engineering, Forestry, and residential redevelopment for reviews.
- Aug 5, 2025
Residential Redevelopment Coordinator
ApprovedInspectorLindsay Evans
- Aug 5, 2025
Engineering (call 952-903-5728)
ApprovedInspectorAndy Reinisch
- Jun 12, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Jun 6, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Bio logs along the front are damaged and need to be replaced and adjusted Clean up street around entrance
- May 22, 2025
Lath
ApprovedInspectorBrian Crask
Note: Contractor opting for an air gap with backer rod and caulking, instead of casing bead.
- Feb 24, 2025
Insulation
ApprovedInspectorBrian Crask
Garage tuck is included.
- Feb 20, 2025
Framing-New Home
Partial ApprovalInspectorBrian Crask
-OK to insulate -Deck footing and framing are to be done at a later date.
- Feb 19, 2025
Weather Barrier/Flashing
ApprovedInspectorBrian Crask
- Feb 19, 2025
Framing-New Home
Not ApprovedInspectorBrian Crask
-Missing hold down strap on side of house -Missing one squash block under point load -Post need shims to transfer load.
- Jan 17, 2025
Floor Slab
ApprovedInspectorTedd Nelson
- Dec 9, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
Fall/Winter Redevelopment Inspection *Inspected by John Brennan
- Dec 3, 2024
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
Fall/Winter Redevelopment Inspection *Inspected by John Brennan - Noticed a portable bathroom, it will need to be moved off of city ROW - clean soil behind the bio log a little more (near street)
- Nov 25, 2024
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Fall/Winter Redevelopment Inspection *Inspected by John Brennan - Put up house sign - Replace bio log and fence in the front yard - Extend the construction fence on the south side of the property - Add bio log against the white fence on the north - Fix both bio log and construction fence on the north side of the property - Silt required to be cleaned off street and DW(construction entrance)
Show 18 earlier inspections
- Nov 19, 2024
Foundation Pre-backfil (Top of foundation survey)
ApprovedInspectorScot Jandro
TOF matches proposed TOF
- Nov 14, 2024
Construction Fence
ApprovedInspectorScot Jandro
- Nov 14, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorScot Jandro
- Nov 14, 2024
Foundation Pre-Backfil
Partial ApprovalInspectorScot Jandro
Approved pending Foundation as-built survey
- Nov 8, 2024
Poured Foundation Reinforcement
ApprovedInspectorGodwin Annin
- Nov 8, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Nov 8, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Nov 4, 2024
Footing
ApprovedInspectorGodwin Annin
Footing for the house only. No deck footings
- Oct 31, 2024
Tree Plan
ApprovedInspectorLaura Beres
Tree fencing approved 8/19/2024
- Oct 29, 2024
Shoring needs to be done before footing inspection
ApprovedInspectorPeter Akmenkalns
push steel plates down to exaction bottom
- Oct 21, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Oct 21, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Oct 10, 2024
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Oct 10, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Oct 3, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Oct 3, 2024
Erosion Ctrl/Const Entrance
Approved, w/ CommentsInspectorLindsay Evans
No dust concerns. Overall, site looked good.
- Oct 1, 2024
Construction Fence
ApprovedInspectorLindsay Evans
- Oct 1, 2024
Erosion Ctrl/Const Entrance
Approved, w/ CommentsInspectorLindsay Evans
In process of demo