PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED215312

Building

4733 Annaway Dr, Edina

IssuedOct 10, 2024
StatusUnknown
Value$3,000,000
Inspections40
Scope of work

New, New Home with deck

Location context
Parcel2911721120004
Coordinates44.91732, -93.37219
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$15,000
Total paid$15,000
Timeline
ApprovedOct 10, 2024
IssuedOct 10, 2024
Inspection record
Inspections40
Passed33
Failed0
  1. Dec 28, 2025

    Final-NEW HOME

    Temp. Occupancy Approved

    InspectorScot Jandro

    C of O Issued
  2. Dec 23, 2025

    Final-NEW HOME

    Partial Approval

    InspectorScot Jandro

    -Install permanent handrail for deck stairs -Install permanent address -Complete exterior finishes -Provide final as-built survey -Obtain approvals from engineering, planning and forestry -Complete all MEP and related permits
  3. Dec 22, 2025

    Blower Door Test (Air Leakage)

    Approved

    InspectorScot Jandro

    1.63
  4. Dec 9, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  5. Dec 4, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

    Fall Inspection Site OK. (Inspected by Brandon Mensing)
  6. Dec 3, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Fall Inspection Move Biffy out of city ROW (Inspected by Brandon Mensing)
  7. Dec 2, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Fall Inspection Move Biffy out of city ROW (Inspected by Brandon Mensing)
  8. Dec 1, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Fall Inspection Move Biffy out of city ROW (Inspected by Brandon Mensing)
  9. Nov 26, 2025

    Bldg Progress

    Progress Report

    InspectorScot Jandro

    Discussed railing on winder stair sections. Ok to interupt rail with newel posts meeting code requirements Windows along stairs are tempered and less then 4" gap
  10. Nov 26, 2025

    Residential Redevelopment Coordinator

    Progress Report

    InspectorLindsay Evans

    Does not appear a permit obtained for LP tank. Forwarded to Fire Dept.
  11. Nov 26, 2025

    Lath

    Approved

    InspectorScot Jandro

  12. Nov 26, 2025

    Weather Barrier/Flashing

    Approved

    InspectorScot Jandro

  13. Nov 25, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorAndy Reinisch

    Fall Inspection Sweep street and make sure free of tracked material Move Biffy and materials out of city ROW Empty dumpster (Inspected by Drew Hollister)
  14. Nov 24, 2025

    Residential Redevelopment Coordinator

    Progress Report

    InspectorLindsay Evans

    LP tank observed during seasonal inspections. Sent email to contractor to obtain temp heat permit by noon 11/26/25.
  15. Nov 19, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorAndy Reinisch

    Clean up and replace broken biologs Fix broken safety fence in back of property Inspected by Francis Killen
  16. Sep 26, 2025

    Lath

    Partial Approval

    InspectorBrian Crask

    Following sections of lath are approved. -Front of house on sides of upper level4 wide window. -Left side porch, at sides of fireplace.
  17. Aug 14, 2025

    Lath

    Approved

    InspectorBrian Crask

    Lath at back wall of house is approved.
  18. Aug 5, 2025

    Insulation

    Approved

    InspectorPeter Akmenkalns

  19. Aug 5, 2025

    Framing-New Home

    Partial Approval

    InspectorPeter Akmenkalns

    still need pier log
  20. Aug 4, 2025

    Lath

    Approved

    InspectorScot Jandro

    Lath for stucco-ok
  21. Aug 4, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorScot Jandro

    Install rock entrance Redo erosion control
  22. Jul 22, 2025

    Framing-New Home

    Partial Approval

    InspectorScot Jandro

    Pending approvals -Pier log sheet per Peter's inspection on 10/30 -No fireplaces installed at this time-do not cover -Weather/lath barrier not ready at this time -TOF survey
  23. Jun 11, 2025

    Bldg Progress

    Progress Report

    InspectorScot Jandro

    Provide Helical log sheet per Peter A. on 10/30/24
  24. Jun 11, 2025

    Framing-New Home

    Not Approved

    InspectorScot Jandro

    Front porch foor, side porch roof, rear garage roof only. No other areas inspected. -Provide electrical RI for areas before covering. -Provide truss specs to check for truss bracing. -TOF as-built survey -Provide truss positive connection for up lift -Missing screws in steel gusset and beams -Provide support for beam hangers at wall connections.
  25. May 30, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorAndy Reinisch

    Spring 2025 Seasonal * Perimeter control both bio log and silt fence * Rear yard double row protection * Tree protection in * Edge of street with sediment track out to be monitored
Show 15 earlier inspections
  1. May 19, 2025

    Lath

    Partial Approval

    InspectorGodwin Annin

    - Lath inspection for the two chimneys only
  2. Feb 28, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  3. Feb 25, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Replace damaged bio logs
  4. Jan 7, 2025

    Foundation Pre-Backfil

    Approved

    InspectorScot Jandro

  5. Jan 7, 2025

    Foundation Pre-backfil (Top of foundation survey)

    Progress Report

    InspectorScot Jandro

    Proposed TOF 901.6 vs TOF as-built 901.7
  6. Jan 2, 2025

    Floor Slab

    Approved

    InspectorPeter Akmenkalns

  7. Dec 3, 2024

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

    Fall/Winter Redevelopment Inspection *Inspected by John Brennan
  8. Nov 27, 2024

    Foundation Pre-Backfil

    Partial Approval

    InspectorScot Jandro

    Pending TOF survey
  9. Nov 25, 2024

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Fall/Winter Redevelopment Inspection *Inspected by John Brennan - Fix damaged construction fence - Rock entrance is depleted, add more rock - Replace bio log at the entrance - Move portable bathroom out of the ROW - Silt required to be cleaned off the street - Silt required to be removed
  10. Nov 20, 2024

    Poured Foundation Reinforcement

    Approved

    InspectorGodwin Annin

    # 5 @ 36 vertical and #4 @ 24 horizontal
  11. Nov 18, 2024

    Poured Foundation Reinforcement

    Not Approved, Not Ready

    InspectorGodwin Annin

  12. Oct 30, 2024

    Footing

    Approved

    InspectorPeter Akmenkalns

    need helical pier logs, footings are on helical piers
  13. Oct 29, 2024

    Erosion Ctrl/Const Entrance

    Approved, w/ Comments

    InspectorLindsay Evans

    Overall site looks good. Added additional rock to extend/widen the entrance. Original driveway still intact.
  14. Oct 29, 2024

    Construction Fence

    Progress Report

    InspectorLindsay Evans

    No safety fence installed at this time. Majority of the site does not have any steep slopes. There is one small area along the front that should have fencing along it.
  15. Sep 12, 2024

    Preconstruction

    Approved, w/ Comments

    InspectorLindsay Evans

    Site looked good. EC in place. Double row of bio logs w/silt fence along back near water. Site sign up. Using existing driveway w/additional rock entrance area. No IP installed (no nearby CB). Pre-construction photos uploaded in PDox. Per Water Resources: Confirmed well on-site. Well sealing record H247272 uploaded in PDox.

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.