#ED216664

Building

5905 Beard Ave S, Edina

IssuedOct 30, 2024
StatusUnknown
Value$350,000
Inspections8
Scope of work

Addition, Rear addition

Location context
Parcel2002824310113
Coordinates44.89610, -93.32383
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$1,750
Total paid$1,750
Timeline
ApprovedOct 30, 2024
IssuedOct 30, 2024
Inspection record
Inspections8
Passed8
Failed0
  1. May 14, 2025

    Final (includes smoke and CO alarms)

    Approved

    InspectorPeter Akmenkalns

  2. Feb 3, 2025

    Insulation

    Approved

    InspectorBrian Crask

    Basement insulation is approved. Now insulation is approved on all levels.
  3. Jan 31, 2025

    Framing

    Approved

    InspectorGodwin Annin

  4. Jan 31, 2025

    Insulation

    Partial Approval

    InspectorGodwin Annin

    - ok to sheet rock main level and upper level - Basement insulation not ready
  5. Jan 29, 2025

    Framing

    Not Approved

    InspectorBrian Crask

    -Missing R3 lateral truss brace -Verify that all holes in the new steel I beam are filled at final. The beam will be exposed. -Note: Modification to existing floor trusses is per PE Trevor Axner's design.
  6. Nov 14, 2024

    Foundation Pre-Backfil

    Approved

    InspectorBrian Crask

  7. Nov 8, 2024

    Poured Foundation Reinforcement

    Approved

    InspectorGodwin Annin

  8. Nov 6, 2024

    Footing

    Approved

    InspectorScot Jandro